Believe preliminary work is expected to start quite soon and, overall, the project could take maybe a full year to complete. Demolition of the old Greek Street railway bridge in Stockport is scheduled for August 2025. Would imagine this will be majorly disruptive for railway operations which normally pass through the area.Does anyone know the time period set for the replacement of the Greek Street roundabout bridge that affects all services coming into Stockport railway station and the time that the bridge replacement will take?
More info here....

Greek Street bridge replacement - Network Rail
We’re replacing the bridge that takes the Greek Street roundabout, in Stockport, over the West Coast main line.

Extract...
Network Rail said:In August 2025, we need to close the railway in Stockport for 21 days. During this time, we will remove the old bridge and install the new one.
P.S Possibly this is worthy of a separate new thread.