• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

East Kilbride/Barrhead electrification updates

Glaswegian

Member
Joined
30 Sep 2021
Messages
19
Location
Falkirk
Are you talking about recently electrified lines or ones done in the past? Recently done lines seem to have lots of TTCs.
I have looked at the very recently electrified Barrhead line. It does indeed have more twin track cantilevers than I expected. But there seem to be special reasons for many of them; for instance they are common at stations. It must surely be possible to have a twin track cantilever almost everywhere there are in fact two single track cantilevers, so I still believe that a pair of single track cantilevers is the preferred option, or was so until recently, but I may be wrong.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Southsider

Member
Joined
10 Aug 2015
Messages
759
Going by the noise in the distance overnight, there was piling between Clarkston and Busby. They’re certainly pressing on with it.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,746
Location
Leeds
A new press release


Major works on Thornliebank Road bridge will begin early next month as part of a project to electrify the East Kilbride to Glasgow railway corridor.

The bridge, which crosses the railway near Thornliebank station, is being demolished and reconstructed over a 14-month period, from Tuesday 2 April until June 2025.

During this time, vehicles are being diverted via Thornliebank Road, Rouken Glen Road, Fenwick Road, Kilmarnock Road and Nether Auldhouse Road (and vice versa).

First Bus is operating a diversion for the 57 and 57A services throughout the works, with full details available at firstbus.co.uk/greater-glasgow.

This £5.5m programme of work is being delivered by Network Rail and its contractor Story and is part of a wider £140m investment in the East Kilbride Enhancement project.

Engineers will create the required clearance height to allow the new overhead line equipment to run underneath the bridge so electric trains can run on the line, as well as installing a new and improved road surface.

Over the coming months until September, the first phase involves diverting a number of service utilities from the existing structure onto a temporary footbridge that is being installed towards the end of April.

Following completion of the utilities diversion, the road bridge will be demolished, from 27 to 30 September, and then the reconstruction work will begin.

Pedestrian and cyclist access will be maintained, and train services at the station will operate as normal – with the exception being the weekend of the bridge demolition.

Simon Humble, project manager, Network Rail, said: “Thornliebank Road bridge represents the largest civils structure on the East Kilbride Enhancement project and is a significant undertaking.

“Although the first phase is a labour intensive period of diverting a number of utilities from the bridge, including fibre optic, water and gas, it allows a substantial part of the work to be delivered during the day.

“When we start the construction phase later this year, this involves more complex engineering – some of which can only be done overnight when no trains are running, and we will update the community in advance of this.

“While we do appreciate the inconvenience of having to close the bridge, it is the only way we can deliver this part of the project and we would encourage everyone to add in some extra travel time.”

Shops and businesses on Thornliebank Main Street and in the surrounding area are open as usual during the works.

The new bridge has been designed in collaboration with East Renfrewshire Council’s active travel team to include enough space for a segregated cycle lane to be introduced in the future.

To find out more on the East Kilbride Enhancement project email [email protected] or call the Network Rail helpline on 03457 11 41 41. For the latest information and updates as the project progresses, follow on X (Twitter) @NetworkRailScot or visit www.scotlandsrailway.com.

Notes to Editors

The East Kilbride Enhancement project is part of a wider £140m investment at the centre of the Scottish Government’s ongoing strategy to decarbonise Scotland’s Railway.

Large numbers of passenger and freight journeys are already made on electrified routes in Scotland. By converting the remainder of the diesel-powered railway network to being powered by electricity and low carbon sources, this will result in fewer greenhouse gas emissions, generating an even greener railway – with East Kilbride Enhancement project representing the current phase of the wider decarbonisation programme.

Some interesting snippets there:

Actual demolition of the old bridge is 27 to 30 September

This is the biggest bridge job on the project

“Although the first phase is a labour intensive period of diverting a number of utilities from the bridge, including fibre optic, water and gas, it allows a substantial part of the work to be delivered during the day.

“When we start the construction phase later this year, this involves more complex engineering – some of which can only be done overnight when no trains are running, and we will update the community in advance of this."
 
Last edited:

MadMac

Member
Joined
13 Jun 2008
Messages
967
Location
Moorpark, CA
Given that Clarkston Toll is no longer a problem rebuilding wise, what’s the biggest problem bridge now other than Thornliebank? Thorntonhall?

post #1692 gives a heads up on the line closure to come in 2025 along the route from Busby jncn to EK station.

This will include no services running to/from East Kilbride for 16 weeks from 01/02/25 to 24/05/25 then another 4 weeks closure from 02/08/25 to 30/08/25. Between those two main periods there will also be successive Sunday closures across the summer.

I'm not sure the options put forward by the project team, a few years ago, about how to deliver these works included such a sustained period of withdrawn rail services. The alternative during the 16 week closure will offer passengers a much poorer, longer road journey during a time of poor weather.
Disclaimer: I lived in, and commuted from, EK for 17 years, so I’m familiar with the potential for very poor winter weather there. When I first saw this, I wondered if someone had lost their mind trying to do major work there in February and March. I’m not seeing why a blockade of that length is necessary.
 
Last edited:

Southsider

Member
Joined
10 Aug 2015
Messages
759
I was crossing Strawhill Road bridge this morning and could see lots of single track cantilever masts heading in the direction of Busby. Will get some photos next time I’m on foot.

Looking south from Strawhill Road, Clarkston station behind me.

Edit :

Two large, poured foundations and masts heading towards Busby.

IMG_0246.jpeg
 
Last edited:

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,498
Location
Between Peterborough & Bedlington
I was crossing Strawhill Road bridge this morning and could see lots of single track cantilever masts heading in the direction of Busby. Will get some photos next time I’m on foot.

Looking south from Strawhill Road, Clarkston station behind me.

Edit :

Two large, poured foundations and masts heading towards Busby.

View attachment 154736
Lovely to see tangible signs of progress at last on this. Looks like the 2no. concrete foundations are for SSAs (Simply Supported Anchors), also known as "wicketkeepers" in this parish; I can see another pair of SSAs in the background which leads me to believe that the 2no. STCs closest to the camera are mid-points.
The tie wires for the mid-point cantilevers will come from the SSAs in the background and the foreground, once the foreground masts are in, as per this rather crude annotation of your photo (new masts in red, tie wires in blue):
IMG_0246.jpeg
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
Some more shots, this time from the Giffnock area.

Masts for what I assume will be twin track cantilevers on the embankment between Church Road and Sutherland Drive bridges.

IMG_0248.jpeg

Large mast and cantilever at the end of the Giffnock platform extension.

IMG_0249.jpeg

Giffnock platform extension.

IMG_0250.jpeg

Giffnock platform renewal.

IMG_0251.jpeg

Preformed blocks for platform construction.

IMG_0252.jpeg
 

Charged up

Member
Joined
22 Oct 2023
Messages
8
Location
South Lanarkshire
Looking north at works ongoing at the site of the new Hairmyres station earlier this evening. View attachment 155032
Thanks for the photograph and it's good to see the new site progressing. This will make a massive difference to accessing the railway from the wider East Kilbride/ Jackton/ Eaglesham area as well as free up much needed parking capacity at the hospital car park by removing rail users.

I'm still puzzled why it will take until December 2025 for it to be fully opened and surely some interim solution [new single platform and bus interchange facility] could be delivered by spring 2025 whilst the remainder of the new station/ car park on north side is completed?
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
Booms and other bits have been fitted to some of the masts on the embankment between Church Road and Sutherland Drive.

IMG_0262.jpeg
 

OB23Gone

Member
Joined
22 Aug 2022
Messages
87
Location
Glasgow
Some from around Shaws West Today. Post #1915 gives Fencing Complete by the end of March Some platform alterations BY 12th April. There is really a whole lot of both platforms requiring to be done
 

Attachments

  • 1 Park Entrance.jpg
    1 Park Entrance.jpg
    402 KB · Views: 112
  • 2 Fence Change - Copy.jpg
    2 Fence Change - Copy.jpg
    556.3 KB · Views: 98
  • 3 Spot The Difference.jpg
    3 Spot The Difference.jpg
    481.5 KB · Views: 106
  • 4 Platform Wor At shaws West -.jpg
    4 Platform Wor At shaws West -.jpg
    448.1 KB · Views: 109
  • 5 General view.jpg
    5 General view.jpg
    375.5 KB · Views: 112
  • 6 Don't touch the mast fence.jpg
    6 Don't touch the mast fence.jpg
    457.3 KB · Views: 111
Joined
14 Mar 2021
Messages
192
Location
Glasgow
Last night, there was a report by Brandon Cook on the STV news at 6pm about the demolition of the Shields Road bridge (not part of this project) and the 14 month closure of the bridge at Thornliebank (part of this project).

See Milestone reached in Glasgow southside bridge upgrade

A major milestone has been reached in a year long upgrade of a key bridge linking the Southside of Glasgow to the City Centre.

The original structure has been torn down and engineers say they’re on track to complete the project as planned by August.

But that might come too late for one local shopkeeper who says the drop in passing trade has killed his business.
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,481
But that might come too late for one local shopkeeper who says the drop in passing trade has killed his business.
Surprises me as I've never seen anyone else in that shop. Also surprised the bridge has made that much difference for passing trade, the bridge is still open to pedestrians/cyclists.
 

E400Lover101

Member
Joined
13 Apr 2023
Messages
38
Location
Glasgow
Lovely to see tangible signs of progress at last on this. Looks like the 2no. concrete foundations are for SSAs (Simply Supported Anchors), also known as "wicketkeepers" in this parish; I can see another pair of SSAs in the background which leads me to believe that the 2no. STCs closest to the camera are mid-points.
The tie wires for the mid-point cantilevers will come from the SSAs in the background and the foreground, once the foreground masts are in, as per this rather crude annotation of your photo (new masts in red, tie wire

Looking north at works ongoing at the site of the new Hairmyres station earlier this evening. View attachment 155032
There has been a bit more progress on the Giffnock platform works when I last used the EK line.
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
There has been a bit more progress on the Giffnock platform works when I last used the EK line.
The Giffnock platform is almost complete, another couple of weeks should see it done. Also, all the twin track cantilevers between Giffnock and Clarkston have booms and wire supports fitted.
 

380101

Member
Joined
18 Feb 2015
Messages
1,001
There has been a bit more progress on the Giffnock platform works when I last used the EK line.

Good progress is also being made on the platform extension at East Kilbride and the new Hairmyres station, which now has the platform base completed on what will be the "down" platform and 3/4s of the bases for the "up" platform installed.
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
Giffnock platform nearly done. I thought they might have laid in mounting points for the electrification masts but nothing visible.


IMG_0276.jpeg
 

380101

Member
Joined
18 Feb 2015
Messages
1,001
Giffnock platform nearly done. I thought they might have laid in mounting points for the electrification masts but nothing visible.


View attachment 156208

Strong likelihood that they'll install twin track cantilever masts on the "Up" side behind the platform fence in a similar fashion to what they've done at Pollockshaws West and other stations on the EK/Barrhead lines.
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
Some large trees have been felled at Busby station, presumably in preparation for masts.

The platform at Giffnock is not quite finished but six car trains are running again.
 
Last edited:

apjsco

New Member
Joined
24 Feb 2024
Messages
1
Location
Glasgow
Some large trees have been felled at Busby station, presumably in preparation for masts.

The platform at Giffnock is not quite finished but six car trains are running again.
Speaking of cars: does anyone know when the ridiculous 2 car provision in the evenings for the EK line will be restored to at least 4 carriages?

Over the past few months, every evening service using 2 cars I have travelled on is overcrowded. Post covid, the EK service has declined significantly and most notably with the reduction to an hourly service which is inconvenient and unnecessary when you look at how busy the hourly services are. It makes me wonder what the post electrification service provision will look like?
 

92002

Member
Joined
27 Mar 2014
Messages
1,134
Location
Clydebank
According to RTT the 1247 yesterday was 6 cars with 4 on Friday The 1317 both yesterday and Friday was a 4. The only 2 car was the 1347 both Friday and Saturday. None are really peaks though.
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
There are now formers for concrete bases throughout the cutting between Giffnock station and Church road bridge, some have had the concrete poured.
 

Top