The East West Rail phase 1 works between Oxford Parkway and Aristotle Bridge (north of Oxford Station) are progressing well. We have almost completed civils work on First Turn Bridge and await the completion of rediversion works by the utilities companies ahead of plans to reopen the road bridge to traffic on 21 March 2016.
Activity to 14 February 2016
SOUTH OF WOLVERCOTE TUNNEL - IN THE VICINITY OF BLENHEIM DRIVE, BLADON CLOSE, ULFGAR ROAD, ST PETER’S ROAD, FIRST TURN, SHERIFF’S DRIVE, FAIRLAWN END AND UPPER CLOSE.
Backfilling of the RediRok retaining wall system continues. We are also installing trackside drainage on the east side of railway working northwards from Canal Bridge, and removing excavated material formed from drainage and Redi-Rok wall excavations.
We are also commencing installation of working platforms on both sides of the railway, two to the south and two to the north of First Turn Bridge to allow works on the noise barrier installations to start. This involves placing fill material to the embankments and compacting with a roller.
FIRST TURN BRIDGE
We are currently waterproofing the bridge deck, laying kerbs and installing ducts in preparation for mains and service diversion works by utility Companies.
WOLVERCOTE TUNNEL
Brickwork repairs to tunnel walls continue and we are installing pile caps to the north and south tunnel portals.
Inside Wolvercote tunnel
Wolvercote tunnel opposite end
The Wolvercote Tunnel was built in 1850 with stone walls and a brick arch barrel roof, and is a known flight corridor for bats, who also use it as an occasional roost. Ensuring bat welfare during the works is a high priority for the team, and we are working closely with Natural England to plan the works and gain the necessary licences and consents. The works required have been specifically designed and scheduled to minimise disruption to the roost, and will take place between July 2015 and end 2016.
NORTH WOLVERCOTE TUNNEL PORTAL TO NORTH OXFORD GOLF CLUB – IN THE VICINITY OF FIVE MILE DRIVE, CAREY CLOSE, WOODSTOCK ROAD AND LAKESIDE ADJACENT TO CUTTING
We continue to backfill behind Redi-Rok wall to the bottom of cutting slope on west side of railway
We are also commencing installation of working platforms on both sides of the railway to allow noise barrier works to start. This involves placing fill material to the embankments and compacting with a roller.
LAKESIDE FROM PEARTREE SITE COMPOUND TO OXFORD PARKWAY STATION – IN THE VICINITY OF LAKESIDE AND NORTH OXFORD GOLF CLUB
Track formation works are being undertaken working southwards towards Lakeside, along with the replacement of an existing culvert to the north of Lakeside. Installation of permanent boundary fence also continues.
PEARTREE SITE COMPOUND TO GOSFORD AND WATER EATON FOOTBRIDGE (NORTH OXFORD GOLF CLUB)
Installation of permanent boundary fence also continues, working southwards from the footbridge towards Pear Tree site compound.