Composing Possessions

Status
Not open for further replies.

Curioustra

New Member
Joined
21 Nov 2024
Messages
2
Location
Bletchley
Hi,
I am new to the railway and excited to start my journey of learning. Could someone talk me through the process of writing and validating possessions against Rules of the route. How are the protection limits, times and blocked lines created? What are the different types of protection? is there a manual somewhere as I can not find one? I am quite young and everyone seems to have so many years of knowledge compared to this newbie
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,365
Location
Dalton GA USA & Preston Lancs
Hi,
I am new to the railway and excited to start my journey of learning. Could someone talk me through the process of writing and validating possessions against Rules of the route. How are the protection limits, times and blocked lines created? What are the different types of protection? is there a manual somewhere as I can not find one? I am quite young and everyone seems to have so many years of knowledge compared to this newbie
Welcome to the forum.
 

Supercoss

Member
Joined
5 Jun 2016
Messages
338
Quite a bit of reading but rule book basics attached, outside of planning stage a person in charge of possession is appointed , PICOP takes ‘ possession’ of the line from the signaller then allows various staff to book in such as Engineering Supervisors . Staff known as possession support place protection on the closed piece of line and in general terms on multi line areas, the line is closed from beyond a junction to the approach of next junction, with trains diverted onto unaffected line(s)
log in required
 

Curioustra

New Member
Joined
21 Nov 2024
Messages
2
Location
Bletchley
Quite a bit of reading but rule book basics attached, outside of planning stage a person in charge of possession is appointed , PICOP takes ‘ possession’ of the line from the signaller then allows various staff to book in such as Engineering Supervisors . Staff known as possession support place protection on the closed piece of line and in general terms on multi line areas, the line is closed from beyond a junction to the approach of next junction, with trains diverted onto unaffected line(s)
log in required
Thanks so much :)
 
Joined
30 Jan 2024
Messages
9
Location
North-East
There will be quite a bit of information available online about how you take a possession, the types of protection etc. But I think OP is asking more about the planning process that leads up to this?

My experience from working on the fringes of this planning process:

All requests to work in a possession are booked in Network Rail's Possession Planning System (PPS) with details of the location, the team responsible, and the type of work. Because there are lots of different teams with work to do and limited time to do it in, PPS will also collect information to help decide which works are compatible with each other (maybe surveyors measuring the track at the same time as signal technicians checking wiring) and which will clash (such as using a rail-mounted tree-chipper at the same time as using a machine to replace worn rails).

There are then a series of 'T minus' meetings in the run up to the possession, named for how many days or weeks they are before the job (eg: T-8 weeks, T-10 days)... conflicts can be resolved at these. Compatible jobs may be grouped together into worksites under the control of a single Engineering Supervisor. Or a job might be cancelled, requiring another team to take control of the worksite. One team might agree to use a different access than originally planned so that they don't conflict with another workgroup. Possession limits might be extended to include an important junction or shortened to avoid stabled trains.

The biggest, most disruptive works that require possessions outside the rules of the route (such as a three-day long blockade) are booked in at T-40 weeks or even earlier. I think most 'rules of the route' works that take place outside of timetabled running hours (mostly overnight) are booked in around T-13 weeks or T-8 weeks. The nearer it gets to the job, the harder it is to change details, and the higher the chance is that someone else has already planned clashing works that make your works impossible.

Final possession details are agreed the week before, and the details published in the Weekly Operating Notice (WON) which is sent to anyone who needs to have it.
 