Ivo
Established Member
I am trying to work out exactly how expensive it would be to build a Metro system with the following statistics. If anyone on here is able to provide even a small amount of data or assistance I would be very grateful. Note that the system would be designed for tram use to simplify construction, including things like signalling, platforms and more.
Tunnels: Approx. 6m wide and 3.5m tall with a rectangular shape and concrete walls with a length of roughly 7½ miles. An additional mile would have to be 9m wide to allow either a third track or a platform between the other two. Space to be provided for walkway. Built using cut-and-cover method.
Tracks: Mostly two tracks at metre guage with a small central rail for power; occasional third track in-between the other two. As well as the 8½ miles double track in tunnels, an additional three miles of double track would be required in open air. A small depot facility capable of holding 16 units would be required, totalling roughly 1.2km of track allowing for junctions etc. One short 500m stretch, 420m of which would be single track, would not have the central rail as it would be on-street and would depend on battery power.
Units: 16 units of similar design to Nottingham trams, but of up to 50m length; width restricted to roughly two metres only. To be powered by small central conductor rail, although battery capability would be required to service easternmost station; battery should be recharged using regenerative braking. At least 20m should be fully accessible with two wheelchair spaces per unit. Two 25m units semi-permanently coupled to be accepted if cheaper; smaller units may be useful in certain circumstances.
Stations: 24 island platforms of 60m length including ramps with platforms about 40cm high, 19 of which are underground. One lift and one spiral stairwell at each underground station, each climbing about five metres. TVMs capable of accepting cards and cash to be provided at all stations, with most having two (two stations would have only one and four would have three). All underground stations to be staffed by at least two persons at all times, with some having up to five; three open-air stations would also have two staff members at all times. Very basic otherwise.
Signalling: Tram signalling only, with the same system employed for points.
Staffing: Estimated to be 180 employees; assume £20K p/a average (i.e. £3.6M p/a total).
I think that's everything, but I'm not sure. Obviously there may be other issues such as compensation and the like, but I'm not asking for figures for this kind of thing at this stage. Everything is to be as basic as possible, subject to Legal requirements, to keep the cost down.
Tunnels: Approx. 6m wide and 3.5m tall with a rectangular shape and concrete walls with a length of roughly 7½ miles. An additional mile would have to be 9m wide to allow either a third track or a platform between the other two. Space to be provided for walkway. Built using cut-and-cover method.
Tracks: Mostly two tracks at metre guage with a small central rail for power; occasional third track in-between the other two. As well as the 8½ miles double track in tunnels, an additional three miles of double track would be required in open air. A small depot facility capable of holding 16 units would be required, totalling roughly 1.2km of track allowing for junctions etc. One short 500m stretch, 420m of which would be single track, would not have the central rail as it would be on-street and would depend on battery power.
Units: 16 units of similar design to Nottingham trams, but of up to 50m length; width restricted to roughly two metres only. To be powered by small central conductor rail, although battery capability would be required to service easternmost station; battery should be recharged using regenerative braking. At least 20m should be fully accessible with two wheelchair spaces per unit. Two 25m units semi-permanently coupled to be accepted if cheaper; smaller units may be useful in certain circumstances.
Stations: 24 island platforms of 60m length including ramps with platforms about 40cm high, 19 of which are underground. One lift and one spiral stairwell at each underground station, each climbing about five metres. TVMs capable of accepting cards and cash to be provided at all stations, with most having two (two stations would have only one and four would have three). All underground stations to be staffed by at least two persons at all times, with some having up to five; three open-air stations would also have two staff members at all times. Very basic otherwise.
Signalling: Tram signalling only, with the same system employed for points.
Staffing: Estimated to be 180 employees; assume £20K p/a average (i.e. £3.6M p/a total).
I think that's everything, but I'm not sure. Obviously there may be other issues such as compensation and the like, but I'm not asking for figures for this kind of thing at this stage. Everything is to be as basic as possible, subject to Legal requirements, to keep the cost down.
Last edited: