Based on what I have just read in the New Civil Engineer and been told by contacts, these are the opening dates being suggested.
When the Elizabeth line opens to passengers this year, it will mark the completion of the long-delayed central section, known as Stage 3. A full service
www.newcivilengineer.com
Target date to open = March 6th. To do so would get the railway running at its earliest date but would delay late running stations from opening, such as Woolwich / Bond Street / Abbey Wood and delay GE services to Shenfield & GW services by a lot.
Best current date to open all in stages by not delaying through running or late stations = Mid June
Down to earth plan - start timetabled running in May, open to passengers when ready maybe with reduced operating hours.