Custom House DLR has been closed for the whole of 2017, for works to tie it in with the adjacent Crossrail platforms. It still is described as "reopening late 2017".
Well, we (at 16 December) have two weeks to go. And looking at progress today, if they can have that all completed in the next two weeks I will eat my hat. The whole platform is still dug up and a building site. No change in the notices however.
But for the past year of closure, particularly at the beginning, there seem to have been months when nothing was being done at all. This seems to be a characteristic of current big closure projects, the Goblin is another.
Well, we (at 16 December) have two weeks to go. And looking at progress today, if they can have that all completed in the next two weeks I will eat my hat. The whole platform is still dug up and a building site. No change in the notices however.
But for the past year of closure, particularly at the beginning, there seem to have been months when nothing was being done at all. This seems to be a characteristic of current big closure projects, the Goblin is another.