This press release has been up since Friday but i ignored it at first because I didn't notice it related to this thread.


Network Rail has delivered a £1.3 million investment of platform works at Giffnock and Pollokshaws West stations.

The five-month programme at Giffnock station in East Renfrewshire, on the East Kilbride to Glasgow line, replaced the 153-metre long section of Platform 1 that’s been in place for over 80 years.

Precast units were laid on top of 85 concrete foundations that spanned the platform and 75 per cent of materials on site were processed and reused as a backfill.

Part of the work also involved engineers extending the section to the south end of the platform by 15-metres to improve future signalling in this location.

At Pollokshaws West station, on Glasgow’s southside, more than 65 tonnes of brickwork was removed and the wall rebuilt to improve the existing condition of the platform that serves both the Glasgow-Barrhead and East Kilbride to Glasgow lines.

For safety reasons, trains with only four carriages were in operation on both lines during the works but trains of up to six carriages will restart from tomorrow (20 April).

Ian Clark, project manager for the works at Giffnock station, said: “The work at Giffnock station is part of our wider maintenance strategy to run a safe and reliable railway by protecting and improving our assets.

“We thank residents living close to Giffnock station for their patience, given much of our work could only be done overnight, and also passengers who had to contend with a four-carriage service to allow the safe delivery of the project.

“However, the renewal work to Platform 1 means that it shouldn’t require an intervention on the scale again for at least another 80 years.”

Michelle McCaig, project manager for the works at Pollokshaws West station, said: “The platforms works at each station were necessary to improve the railway so that it continues to remain fit for purpose for our passengers and freight customers.

“We are very grateful for the support shown by the wider Pollokshaws community during delivery of the works.”

With the majority of work at Pollokshaws West station now complete, the final element will involve resurfacing Platform 2 and will be carried out later in the year.

Throughout the works at Giffnock, 33 parking spaces at the station were utilised to house the site compound – this will continue to remain in place to deliver the East Kilbride Enhancement project.


-------------- the dreaded automerge --------------------------



Press release announcing reopening yesterday of Thornton Road bridge.


Network Rail reopened the bridge over the railway at Thornton Road in East Kilbride today, Monday 22 April.

The bridge has been replaced as part of a wider £140m Scottish Government investment in the East Kilbride Enhancement project to decarbonise passenger services.

Thornton Road bridge is one of several along the East Kilbride to Glasgow railway corridor being raised to provide more space underneath.

This will allow engineers to install the required overhead line equipment so that electric trains can run on the route.

Network Rail, along with contractor Story, started work in December 2023 and the bridge is the second to be completed after a new footbridge near Hairmyres station opened last month.

Simon Humble, Network Rail’s project manager for the bridge works, said: “The team’s made incredible progress since starting the bridge replacement works towards the end of last year. This hasn’t been without its challenges given the very wet and windy weather, particularly over the last few weeks.

“The re-opening of Thornton Road represents an important milestone on the enhancement project overall, as it marks the final element of our bridge replacement works in East Kilbride.

“I would like to thank the community for their patience both during the delivery of this work and the on-going activity across the wider route.”

After the old bridge was demolished at Thornton Road over the Christmas period, the team focused on building the new one by craning six precast concrete units into place that each weighed up to 35 tonnes.

Elsewhere, progress is continuing at the site of the new Hairmyres station, where the team recently installed 184 concrete units to create two new platforms.

At East Kilbride station, work to extend the existing platform by 51m is nearing completion. This will accommodate moving the station buffer to allow the construction of the new station building.

In addition, a 14-month programme to replace Thornliebank Road bridge in East Renfrewshire started earlier this month, with the old structure due to be demolished in the autumn.

Electric services will be introduced on the East Kilbride line following completion of the project in December 2025 and will offer enhanced operational performance and flexibility of service on the route.

Here's what it looked like before (Streetview link):


I've updated my list of bridges in #1826.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

OB23Gone

Member
Joined
22 Aug 2022
Messages
89
Location
Glasgow
Some photo updates:-Pollokshaws Road fence now all renewed. Shaws West Station strange happening at platform 1. Giffnock:- Good work on platform, 2 masts in

Some photo updates at Thornliebank Station and Bridge works. Station:- Some masts nearer from Busby Junction, Cantilever in & some poured piles. Bridge Works:- Difficult to see much progress on the actual Road bridge as 3 sides are behind boarding but Work progressions in preparation for temporary pedestrian footbridge
 

Attachments

  • 1.jpg
    1.jpg
    676.6 KB · Views: 115
  • 2.jpg
    2.jpg
    530.4 KB · Views: 119
  • 3.jpg
    3.jpg
    446 KB · Views: 118
  • 4.jpg
    4.jpg
    356.8 KB · Views: 115
  • 5.jpg
    5.jpg
    467.9 KB · Views: 115
  • 6.jpg
    6.jpg
    548.6 KB · Views: 115
  • 7.jpg
    7.jpg
    465.5 KB · Views: 118
  • 10.jpg
    10.jpg
    540.7 KB · Views: 121
  • 18.jpg
    18.jpg
    668.2 KB · Views: 122
  • 11.jpg
    11.jpg
    495.9 KB · Views: 122
  • 12.jpg
    12.jpg
    599.5 KB · Views: 114
  • 13.jpg
    13.jpg
    524.9 KB · Views: 107
  • 14.jpg
    14.jpg
    717.7 KB · Views: 107
  • 15.jpg
    15.jpg
    595.3 KB · Views: 104
  • 16.jpg
    16.jpg
    473.9 KB · Views: 103
  • 17.jpg
    17.jpg
    575.3 KB · Views: 109
Last edited:

E400Lover101

Member
Joined
13 Apr 2023
Messages
41
Location
Glasgow
Some photo updates:-Pollokshaws Road fence now all renewed. Shaws West Station strange happening at platform 1. Giffnock:- Good work on platform, 2 masts in

Some photo updates at Thornliebank Station and Bridge works. Station:- Some masts nearer from Busby Junction, Cantilever in & some poured piles. Bridge Works:- Difficult to see much progress on the actual Road bridge as 3 sides are behind boarding but Work progressions in preparation for temporary pedestrian footbrige
We are definitely getting somewhere with the electrification, A few piles seen at Clarkston Station and a few poured piles outside the station. The vegetation works at Busby bridge is presumably where a pile will be placed.
 

OB23Gone

Member
Joined
22 Aug 2022
Messages
89
Location
Glasgow
Big Crane Wee Bridge. Thornliebank Station Temp. Footbridge main section now in position
 

Attachments

  • Station Road Bridge 05-05-24.jpg
    Station Road Bridge 05-05-24.jpg
    504.1 KB · Views: 93
  • Footbridge Just Dropped in.jpg
    Footbridge Just Dropped in.jpg
    919.8 KB · Views: 95

E400Lover101

Member
Joined
13 Apr 2023
Messages
41
Location
Glasgow
Network Rail have posted on Twitter that they'll be starting work on getting steelwork installed on the Overlee Viaduct (Between Clarkston and Busby) over the next few weeks.
 

och aye

Member
Joined
21 Jan 2012
Messages
807
Network Rail press release regarding the rebuilding of EK station. The project is due to be completed by December 2025.

Three key pieces of work completed at East Kilbride station​



Network Rail has hit three important milestones as part of its ongoing improvement works at East Kilbride station.

Engineers demolished the kiosk building, removed part of the platform at one side and extended it at the other to allow the construction of a new station building and installation of overhead line equipment.

The platform work is vital in allowing the station to accommodate longer trains on the East Kilbride to Glasgow route as part of the East Kilbride enhancement project.

In addition, the railway buffer, which is used to mark the end of the line, was moved in preparation for the platform to be extended by 25m next year - a move which will create space for more passengers.
 