Can anyone please answer some questions on the GE and LTS electrification.
When the 25 Kv system was introduced in the early 1960s, there were several sections where there was insufficient clearance for this, mainly at the inner London ends of the system, and they were electrified at quarter voltage, 6.25 kv. The emus were fitted with automatic changeover equipment, operated magnetically like AWS, but I believe the magnets were mounted just outside the rails rather than between them. Apparently both the GE and the LTS had this arrangement. What were the actual sections this was done on? When were they finally changed over to the standard 25 kv (I think some time in the 1980s)? I seem to recall reading that the entire Chingford line was at 6.25 kv.
I once heard that the same approach was taken on the Glasgow North/South Clyde lines, is there any documentation of which sections these were?
The West Coast main line electrification of the same period nearly got the same arrangement where clearances were tight, but there was some redesign and it was not done.
Would also be interested in detail of the changeover to this system from the old 1500v DC electrification out of Liverpool Street. The trains were converted from DC to AC in what must have been quite an extended programme, but the electrification itself must have been changed from one voltage to another over a weekend. When did this happen? Is it correct that it was about 1961, and the trains for the LTS line were built early and all used on the GE line from changeover date until the conversions were done? The first 20 or so LTS units were never moved on, and operated out of Liverpool Street for most of their lives.
Thank you anyone with information.
When the 25 Kv system was introduced in the early 1960s, there were several sections where there was insufficient clearance for this, mainly at the inner London ends of the system, and they were electrified at quarter voltage, 6.25 kv. The emus were fitted with automatic changeover equipment, operated magnetically like AWS, but I believe the magnets were mounted just outside the rails rather than between them. Apparently both the GE and the LTS had this arrangement. What were the actual sections this was done on? When were they finally changed over to the standard 25 kv (I think some time in the 1980s)? I seem to recall reading that the entire Chingford line was at 6.25 kv.
I once heard that the same approach was taken on the Glasgow North/South Clyde lines, is there any documentation of which sections these were?
The West Coast main line electrification of the same period nearly got the same arrangement where clearances were tight, but there was some redesign and it was not done.
Would also be interested in detail of the changeover to this system from the old 1500v DC electrification out of Liverpool Street. The trains were converted from DC to AC in what must have been quite an extended programme, but the electrification itself must have been changed from one voltage to another over a weekend. When did this happen? Is it correct that it was about 1961, and the trains for the LTS line were built early and all used on the GE line from changeover date until the conversions were done? The first 20 or so LTS units were never moved on, and operated out of Liverpool Street for most of their lives.
Thank you anyone with information.