Start of new service to Newport now delayed until possibly mid-late January. Letter from James Price to AM.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Joined
22 Jun 2013
Messages
388
Yet they've sent the 175s, 170s and Northern 150s back, weird planning. The 175s are doing literally nothing. I'm not sure that James Price is a very competent CEO.
 

Anonymous10

Established Member
Joined
19 Dec 2019
Messages
2,080
Location
wales
Yet they've sent the 175s, 170s and Northern 150s back, weird planning. The 175s are doing literally nothing. I'm not sure that James Price is a very competent CEO.
It's been posted here before that 175s required a dedicated depot and Chester could not maintaine both and believe there was supposed to have been a new home initially.

Also the class 170s I believe have had multiple deadlines which couldn't be pushed back for going to EMR.

Re the northern class 150s it might be northern have requested them back as they're sub loaned.
 

Tom125

Member
Joined
27 Jan 2019
Messages
40
Oh dear! "Transport for Fails"! Please don't turn the comments on here into a childish copy of WalesOnline.
Except for those of us who use the miserable service in the valleys it is a daily occurrence of failure. 2/3 trains allocated for Ebbw Vale to Cardiff services and frequent delays because there is no slack in the turn around times. Under Arriva 3 trains were allocated and the line was so reliable! We even got 4 coaches on a Saturday and during school holidays (those were the days).
 
Joined
13 Feb 2011
Messages
1,063
Location
Cardiff
…2/3 trains allocated for Ebbw Vale to Cardiff services and frequent delays because there is no slack in the turn around times. Under Arriva 3 trains were allocated and the line was so reliable! We even got 4 coaches …
Are you talking about trains or carriages?

…Under Arriva 3 trains were allocated and the line was so reliable! We even got 4 coaches on a Saturday and during school holidays (those were the days).

I knew it would happen at some point, but I didn’t think it would be a commuter from the Valleys who’d say it first!
 

Dai Corner

Established Member
Joined
20 Jul 2015
Messages
6,352
Are you talking about trains or carriages?
Trains I think.

The round trip from Cardiff to Ebbw Vale and back takes about two hours so they really need three trains to provide a resilient service, with one laying over at Cardiff for about 50-55 minutes.
 

Brissle Girl

Established Member
Joined
17 Jul 2018
Messages
2,664
It's the lack of notice that stinks here, given that they must have known for a couple of weeks that this was highly likely. Given that the Treherbert line is currently OOU, which will be saving at least 4 units (unless the remaining services up the Taff Vale are strengthened to compensate?) that will be needed at some point in the New Year (Feb?), what confidence is there that the delay will only be a month?
 

Woolos 22

Member
Joined
27 May 2022
Messages
81
Location
Newbridge
Which January no year given in his letter. As it was planned for 2018 another so will we have to wait 5 more years for it to happen
 

Tom125

Member
Joined
27 Jan 2019
Messages
40
Trains I think.

The round trip from Cardiff to Ebbw Vale and back takes about two hours so they really need three trains to provide a resilient service, with one laying over at Cardiff for about 50-55 minutes.
Trains it was. It was always 3 trains allocated to the line to run a reliable and resilient timetable under Arriva. Nowadays there are only 2 trains allocated which causes a timetable that is neither reliable nor resilient.

Are you talking about trains or carriages?



I knew it would happen at some point, but I didn’t think it would be a commuter from the Valleys who’d say it first!
Arriva certainly weren’t perfect but you did know that if you turned up at Ebbw Vale station the train was there are mostly on time. When you have an hourly timetable to work with to commute to work, it unacceptable for the train to be delayed and cancelled.
 
Last edited:

56xx

Member
Joined
19 Jun 2021
Messages
116
Location
Merthyr Tydfil
Realtime Trains showing the Ebbw Vale to Newport service commencing on Saturday 20th January and then weekdays from w/c 22nd January.

Will have to wait and see if TfW have enough units.
 

oglord

Member
Joined
13 Oct 2010
Messages
331
Location
Newport, Monmouthshire
Realtime Trains showing the Ebbw Vale to Newport service commencing on Saturday 20th January and then weekdays from w/c 22nd January.

Will have to wait and see if TfW have enough units.
That's just because they haven't got around to cancelling them in the system yet. It has been a rolling two-week's ahead since December 11th!
 

Last Hurrah

Member
Joined
17 Jan 2023
Messages
67
Location
Canton
With depot space being something of a premium, would a small depot capable of housing 3/4 trains overnight, similar to Machynlleth be a worthwhile investment, rather than last service returning ecs to Canton depot

With the introduction of Newport services being imminent, a 2nd track from EVP to EVT, along with 2nd terminus platform in conjunction with a depot, would continue enhancement of the line
 

Brissle Girl

Established Member
Joined
17 Jul 2018
Messages
2,664
With depot space being something of a premium, would a small depot capable of housing 3/4 trains overnight, similar to Machynlleth be a worthwhile investment, rather than last service returning ecs to Canton depot

With the introduction of Newport services being imminent, a 2nd track from EVP to EVT, along with 2nd terminus platform in conjunction with a depot, would continue enhancement of the line
Given how over budget the whole metro project is, I suspect the Ebbw Vale branch has had its share of enhancements for the foreseeable future. Unless your proposal had a benefit for passengers, it seems a lot to spend for little benefit.
 

oglord

Member
Joined
13 Oct 2010
Messages
331
Location
Newport, Monmouthshire
Realtime Trains showing the Ebbw Vale to Newport service commencing on Saturday 20th January and then weekdays from w/c 22nd January.

Will have to wait and see if TfW have enough units.
As predicted the Ebbw <-> Newport services for the week of the 22nd have all vanished from the timetable. Has there ever been a worse operator in the history of the railway than TfW?
 

The exile

Established Member
Joined
31 Mar 2010
Messages
2,724
Location
Somerset
As predicted the Ebbw <-> Newport services for the week of the 22nd have all vanished from the timetable. Has there ever been a worse operator in the history of the railway than TfW?
Almost certainly - the difference now being the fact that everyone can see what is going on and easily comment about it. In the not too distant past, the best the public would have got would have been a footnote to the timetable saying “service may commence during the validity of this timetable”. IIRC, sometimes it did; sometimes it didn’t!
 

56xx

Member
Joined
19 Jun 2021
Messages
116
Location
Merthyr Tydfil
As predicted the Ebbw <-> Newport services for the week of the 22nd have all vanished from the timetable. Has there ever been a worse operator in the history of the railway than TfW?
Still showing from Monday 29th January on RTT.

Bookings for direct service also showing on TfW from the same date. Don't know if this was the case previously.
 

Tom125

Member
Joined
27 Jan 2019
Messages
40
I just asked the TfW twitter team and the reply was “Hi Tom, we are expecting the Ebbw Vale - Newport services to start on the 29th January, thank you for your patience ^Gwen” . There has been no advertising about it starting online which isn’t great for attracting passengers!
 

Western 52

Member
Joined
19 Jun 2020
Messages
1,124
Location
Burry Port
I just asked the TfW twitter team and the reply was “Hi Tom, we are expecting the Ebbw Vale - Newport services to start on the 29th January, thank you for your patience ^Gwen” . There has been no advertising about it starting online which isn’t great for attracting passengers!
Maybe no publicity due to the high risk of it not actually starting!
 

jayah

On Moderation
Joined
18 Apr 2011
Messages
1,889
I believe there is a requirement now that PA announcements must be heard along the full length of the platforms on a scheme that sees new PA installed.

This has also happened in recent years at Pontypridd and Barry as part of an accessibility improvement package, and is also due to happen with Pontypool and possibly Grangetown and Llantwit Major.


Source: https://www.gov.uk/government/news/...-funding-boost-for-accessibility-improvements
That will add a few more hundreds of thousands to the cost of building a new station.
The people who invent these requirements are the ones who need to explain the rampant inflation impacting infrastructure costs in this country. It is a small miracle anything gets built any more.

While they seem to have got CCTV and loudspeakers on the same posts on the new platform, is it also a requirements that signs, CIS screens and CCTV all need their own set of metal posts? A CIS screen can apparently hang off one post, but a station name board with 11 letters in two languages seems to need two great big posts.
 