Hartlepool to have a platform reinstated as funding now confirmed

Status
Not open for further replies.

td97

Established Member
Joined
26 Jul 2017
Messages
1,449
There's an update from the p-way subcontractor on LinkedIn. Extracts below, but photo only accessible through the link.
Sounds like a very bare bones budget but they've made the best of it.

WK05 – Hartlepool Final Quality Tamp
The KGJ Price Rail Team successfully completed the final quality tamp through Hartlepool Station in WK05 (weekend). This will allow our client Story Contracting to undertake the platform coper installs commencing in WK05.

As a summary of these works, KGJ Price were contracted to:-
Ø Provide all aspects of Permanent Way services.
Ø Remove the existing jointed track through platform 3;
Ø Scarify the ballast, fettle and spot re-sleeper the timber check rail panels;
Ø Re-lay the existing jointed track to the new platform alignment;
Ø Average of 150mm lifts and 270mm slues all on a tight <250m Radius;
Ø Undertake the Core works during a 54-hour blockade during WK51 March 2023;
Ø Final Quality Tamp undertaken in WK05.

Due to the late cancellation of the eng trains for the Core works, KGJ Price Rail re-planned the works utilising RRV’s and boxes. Our Rail Delivery Manager attended meetings with Story Contracting and NR to provide confidence to the route that the risk from such a late change was being managed and implemented in a safe and controlled manner. The QSRA was approved 2 weeks before the Core works with successful delivery in WK51.

This project has been a fantastic example of ECI, clear communication and collaborative teamwork to deliver a safe and successful package of work. Thank you to our team and supply chain!!!!

A good job from start to finish, anyone who has relaid jointed track on a tight radius curve will know it’s not the easiest - made even more difficult by having to reuse the same materials! What’s not detailed below is the non scoped work that we competed to leave a better railway as a whole: 1. Removed a rail defect by being smart with our closure rail use / location 2. Removed some long standing wet beds thus improving track quality and less maintenance intervention 3. Used excess top stone to top up the adjacent line and then brushed it which has removed a CRT risk for the maintainer. A by product of removing the CRT risk on the adjacent line is that it looks like both lines have been relaid - finishing the project off aesthetically to the general public to match the soon to be complete lifts, stairs and platform. During these times of increased financial pressure on maintenance budgets it’s these little things that a bit of attention to detail and a bit more effort can achieve a big improvement to the railway as a whole.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Coolzac

Member
Joined
8 Nov 2014
Messages
329
Fantastic.

I think it's great - it will open up opportunities for more trains in the future, as well as removing a passing place where delays can occur/get worse. Let's hope they can get it done by July as planned!

I just hope they give Middlesbrough a third platform too, in the near future.
 

jkkne

Member
Joined
13 Aug 2012
Messages
416
Details of the improved service below

The Newcastle-Middlesbrough line – which stops at Horden, Hartlepool, Seaton Carew and Billingham stations – will increase from a train every hour to three trains every two hours later this year.
Should help with match day trains for Sunderland at least
 
Last edited by a moderator:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
32,891
Details of the improved service below


Should help with match day trains for Sunderland at least
The timings are already in RTT and were discussed in a separate thread here:
 

Freightmaster

Established Member
Joined
7 Jul 2009
Messages
3,816
On the subject of 'reinstating third platforms at stations in the Teesside area',
what has happened to the (arguably more useful) plan to add a additional platform
on the goods line at Middlesbrough? Is that no longer happening?




MARK
 

Harvester

Established Member
Joined
9 Nov 2020
Messages
1,552
Location
Notts
Was this reinstated ‘up’ platform at Hartlepool station back in use in July as planned?
 

3RDGEN

Member
Joined
6 Mar 2023
Messages
392
Location
Hull
Was this reinstated ‘up’ platform at Hartlepool station back in use in July as planned?
No still to be opened. The Northern December Timetable announcement says the additional services will run once open, as it did in May.

https://www.northernrailway.co.uk/travel/timetables/timetable-change

Middlesbrough and Newcastle: The additional two hourly service being introduced once platform work is complete at Hartlepool will be part of the December 2023 timetable
 
Last edited by a moderator:

Pinza-C55

Member
Joined
23 May 2015
Messages
1,035
The increased Sunderland - Middlesbrough service will be a good thing but it will have the negative effect of adding yet more trains to Sunderland stations 2 (physical) platforms. The new station building is now complete but the restricted platform and track layout has not been addressed, nor the dismal platform level environment which resembles an underground car park.
 

ainsworth74

Forum Staff
Staff Member
Global Moderator
Joined
16 Nov 2009
Messages
29,074
Location
Redcar
I must admit I'm curious why it's slipped so much. The original plan was for it to be open in time for the Tall Ships at the start of July but now it may well not be until into the next timetable period!
 

rg177

Established Member
Associate Staff
International Transport
Joined
22 Dec 2013
Messages
4,234
Location
Newcastle-upon-Tyne
Currently on a GC service looking at the new platform now.

The platform and bridge look to be essentially completed - the drains on the platform just need gaps filling in.

It looks like it mostly just needs the canopy adding. The frame is in situ, but no actual canopy just yet.
 