Drivers at TPE have now been told due to an "error" by Network Rail 185's will not be currently running at MU speeds.
Possibly to do with unsprung weight?Given the millions of tonnes of freight on the Hope Valley line, I doubt it is axle loading on a slightly heavier than normal DMU causing the problem.
Possibly a case of braking distances etc?
The initial email sounded speculative in nature anyway from what commentors are saying. I certainly wouldn't make any changes until I saw something concrete.Drivers at TPE have now been told due to an "error" by Network Rail 185's will not be currently running at MU speeds.
A new footbridge has been installed in Dore & Totley as part of the Hope Valley Railway Upgrade
It’s the latest milestone reached at Dore & Totley station which will see improvements for rail passengers travelling between Manchester and Sheffield.
Six staircase units, each weighing 11.2t, were lifted into place using a 200t road mobile crane, before the main bridge span was installed, weighing 14.5t and 15m in length.
The new structure will lead passengers onto a second platform, which is currently being restored over 30 years after the original island platform was demolished in the 1980s.
Accessibility has been at the forefront of the work, with two working lifts included as part of the bridge design.
Over the past two years, Network Rail and the contractor, VolkerRailStory JV, have also met with local disability groups to gain feedback on more detailed elements of the station build.
Changes have been incorporated as a result, including additional tactile wayfinding on the platform and brighter colour bands on lighting posts to aid those with visual impairments.
...
The station upgrades, which also include the installation of new track, will help to facilitate longer trains with more carriages and improve the reliability of passenger journeys.
The work is planned to be completed at the end of a 9-day railway line closure at the end of March.
Which totally winds up Sheffield area users and those local residents who have endured 2 years of construction work that was, back at the 2013 first public consultation, going to deliver 2 extra fast trains an hour between Sheffield and Manchester by 2018.Another press release
Accessible footbridge installed at Dore & Totley Station
A new footbridge has been installed in Dore & Totley as part of the Hope Valley Railway Upgradewww.networkrailmediacentre.co.uk
For what it's worth, the surfacing on the existing platform is complete and that is how it is expected to be left. Shame there is no levelling up funding to resurface the other half.Another press release
Accessible footbridge installed at Dore & Totley Station
A new footbridge has been installed in Dore & Totley as part of the Hope Valley Railway Upgradewww.networkrailmediacentre.co.uk
I haven't seen that yet but was told last weekend it would all be done to match.For what it's worth, the surfacing on the existing platform is complete and that is how it is expected to be left. Shame there is no levelling up funding to resurface the other half.
There are more seats to come and the group at the south end should be staying.I hope they replace or don’t remove the seats at the south end, even though they’re in the open. The leaning benches in the shelter are useless.
Time travelling photos?17th February 2024
Haha. Amended. CheersTime travelling photos?
Always nice to see the progress.
Future-proofing? Also does it look high because of its roof and maybe the lift towers too. Any photos with a train in the platform?does it really need to be that high?
I think it looks really fitting - Great choice - very traditional colour scheme for Midland. What's with green, are you from Southern or GWR?That bridge seems quite visually intrusive to me... 2 questions:
a) couldn't it have been (maybe) pale green
Yes., it is a bit tall.. Ultimately all railway bridges are intrusive, viaducts too - Ribblehead isn't invisible - some structures are just "good intrusive"and b) does it really need to be that high? Is the height the outcome of (rumoured) over-interpretation or just misunderstood/mistaken application of OLE clearances?
Probably needs to be high enough that any future OLE (less unlikely here than in many other places) fully meets the standard for clearance from the platform surface. Where pre-existing structures limit the clearance then a lower value might be accepted, but it wouldn't be for a new structure.Future-proofing? Also does it look high because of its roof and maybe the lift towers too. Any photos with a train in the platform?
Is zoom/telephoto contributing to the appearance ?That bridge seems quite visually intrusive to me...
…..b) does it really need to be that high?
Probably needs to be high enough that any future OLE (less unlikely here than in many other places) fully meets the standard for clearance from the platform surface. Where pre-existing structures limit the clearance then a lower value might be accepted, but it wouldn't be for a new structure.
Is zoom/telephoto contributing to the appearance ?
I hope they don't spoil the new platform at Dore by providing nothing more than a bus shelter. Surely it deserves something a bit more substantial and user friendly than that!
One would hope they wire the whole delta junction. It would be perverse if a Class 99 hauling a heavy stone train couldn't use AC to get itself up the hill to the Bradway tunnel.However it has been suggested that token wires might be included with MML work through the station towards Totley Tunnel. All total speculation but all new bridges have to be built high enough for future wiring no matter how long it may be before it comes.
One would hope they wire the whole delta junction. It would be perverse if a Class 99 hauling a heavy stone train couldn't use AC to get itself up the hill to the Bradway tunnel.
I suspect nothing's got as far as determining limits of electrification. IMHO the most likely outcome will be that overruns on each junction will be provided from the MML. These would probably be to the Manchester end of Dore and Totley platforms to allow bi-modes to change in the station, and far enough on the south curve to allow the freight to pan up while waiting for the road.. The only way I could see the whole triangle being wired is if there were regular turning moves required for operational purposes (I don't believe there are any, and electrification is unlikely to create a need for this facility), or if the wires were going further up the Hope Valley line (a long way out now).Bradway Tunnel is on the MML where Platforms 3 and 4 used to be and that is supposed to be wired. The bridge is on the Hope Valley line to Totley Tunnel and that may be wired, but costs will be a major factor.
Some have suggested that both the Dore chord/loop from Dore South Junction through Dore,Tunnel and the section from new Dore Station Junction up to Totley Tunnel might be electrified. A declaration of ultimate intent? But shoestring budgets probably won't even stretch that far by 2040.
Yes the tunnel will be wired, but a stone train coming off the Dore South chord won't be able to use it if the pan isn't already raised.Bradway Tunnel is on the MML where Platforms 3 and 4 used to be and that is supposed to be wired. The bridge is on the Hope Valley line to Totley Tunnel and that may be wired, but costs will be a major factor.
Give it a few years and it'll be a pile of rust like the one at Swinton.That bridge seems quite visually intrusive to me... 2 questions:
a) couldn't it have been (maybe) pale green
and b) does it really need to be that high? Is the height the outcome of (rumoured) over-interpretation or just misunderstood/mistaken application of OLE clearances?
It's certainly designed for that, and it looks to be the modular design so it presumably has been designed to clear OLE and W12 clearances if it was based at rail level, which might explain the extra height as the platform height has added to the clearances as well. Worth pointing out this isn't necessarily a 'mistake' in double-counting, just a compromise of using a single standard design.I would guess the bridge has been constructed to W12 clearances + OLE?
In terms of OLE around Sheffield, that probably needs to wait until all the track going into and out of Sheffield station is ripped up and replaced, similar to the remodeling in Derby.
I would guess the bridge has been constructed to W12 clearances + OLE?
Give it a few years and it'll be a pile of rust like the one at Swinton.
I would guess three track would run bi di? Probably not so bad if the track splits before Dore & Totley, rather than having to share a single track through the station too.No doubt there are plans for remodelling Sheffield and they include some form.of 3 tracking from Dore. 4 would be very difficult to restore throughout but would be possible in parts. It's taken over 25 years for the current work to evolve so it will be interesting to see how long it takes for whatever finally emerges.
Yes the tunnel will be wired, but a stone train coming off the Dore South chord won't be able to use it if the pan isn't already raised.