absolutelymilk
Established Member
- Joined
- 18 Jul 2015
- Messages
- 1,407
None of the TBMs have updated on my map, and Emily has 1,086m to go, not 1.6k
Another great milestone. Good to see.Northolt West tunnels are now both complete.
![]()
Second HS2 tunnelling machine completes 5-mile drive under the capital
TBM Caroline has arrived at Green Park Way in Ealing, the second TBM in London to complete this year HS2's Northolt tunnel is now 93% completemediacentre.hs2.org.uk
Interesting, back in February they wrote in an update "Twelve cross passages have been completed on the NTW and 7 completed on the NTE. There are 12 remaining CP to be built across both tunnel phases."HS2 has also released a video, about Northolt tunnels, following Caroline's completion including some info on Ruislip portals with acoustic pores. Also mentions 10 of 34 cross passages (at 500m intervals) now finished
== Doublepost prevention - post automatically merged: ==
per tunnel tracker
Emily (Northolt East) 4.74km on 3rd April, +168m in 8 days
other TBMs not updated
The "In your area" map produced by HS2 themselves shows it as 4.74km as of 28 March, not 3 April - wonder if 3 April is the date that Tunnel Tracker spotted the change?per tunnel tracker
Emily (Northolt East) 4.74km on 3rd April, +168m in 8 days
other TBMs not updated
I think the readings could both be true *if* Emily had been stopped between the two readings (4 April vs 5 April), and Anne had covered 22m, which is possible if the reading from the map had been made earlier in the day compared to the reading from TBMEngineer (taken at 17:40)The progress graphic on the HS2 web site has been updated for Northolt East, but it doesn't quite match the obviously genuine data shown by TBMEngineer above.
Firstly the date given is April 4 (7 days from Mar28), and secondly the data for TBM Anne is different.
Emily is shown at 4771m (+29m), Anne at 4582m (+86m).
Progress has slowed from recently, but as noted above the ground conditions are changing as the finish line approaches.
![]()
In your area map
Search our interactive In Your Area Map to find information about current or planned HS2 construction works taking place across the route.www.hs2.org.uk
Downline has been stopped for the past weeek or so for some maintenance and repairs.I think the readings could both be true *if* Emily had been stopped between the two readings (4 April vs 5 April), and Anne had covered 22m, which is possible if the reading from the map had been made earlier in the day compared to the reading from TBMEngineer (taken at 17:40)
Apologies yes ha we only call them Downline and UplineDownline = Emily (western tunnel of the pair, Birmingham bound).
Upline = Anne (eastern tunnel, OOC/Euston-bound).
There’s scope for faster but not required.30m a day is good going!
Mary Ann showing as 5382m on April 7th with 218m to goBromford TBMs both updated, with another roughly 200m done since the last update 14 days ago. Mary Anne should be done in another 14 days if it it keeps up this pace!
Wow- that is good.Apologies yes ha we only call them Downline and Upline
== Doublepost prevention - post automatically merged: ==
There’s scope for faster but not required.
We could definitely go 45m per 24 hours. Depends on ground and machine breakdowns - other factors etc
The portal at northern end is still under construction, the approach portal is longer, so will add about 300m to the bored tunnel length.Contractors building HS2 have completed work on a pair of innovative extensions to the southern portal of its longest tunnel to eliminate the possibility of ‘sonic boom’ being created by high-speed trains entering at 200mph.
The structures, built at the southern end of the railway's 10-mile Chiltern Tunnel to the north-west of London, are near identical to those now under construction at its northern portal in Buckinghamshire.
All trains entering tunnels anywhere in the world force air forward, creating pulses of energy that roll along the tunnel causing a small release of air pressure into the outside world at the far end. Known scientifically as ‘micro pressure waves’, they are inaudible on conventional railways. But in high-speed rail tunnels, air shoved forward without escape routes can create powerful pressure waves that emerge as an audible ‘thud’ or ‘sonic boom’.
In a first for the UK rail network, HS2’s design includes extensions on all eight tunnels where trains enter at speeds above 140mph. However, the length, physical setting and aesthetic of those at each end of the line’s tunnel beneath the Chiltern Hills mark them out as unique even to HS2.
HS2 Ltd chief engineer, Mark Howard explains,
“The maximum speed of HS2 varies along the route. But where the train is entering a tunnel travelling above 140mph we are building portal extensions to prevent ‘sonic boom’ occurring. Although there are several tunnels on the line where train speed will be higher than in the Chiltern Tunnel, no other combines speeds of 200mph with length of 10 miles. Its these unique physical characteristics that demand unique structures at each end.”
First identified in 1974 during train testing on Japan’s then new 187mph ‘Sanyo’ shinkansen line, when people nearby noticed ‘booms’ near tunnel exits, the problem was solved by the invention of perforated portals extending from the tunnel entrance. Later, as train speeds gradually increased and further slight improvements in the control of micro-pressure waves were required, the solution was to radically enhance the train’s aerodynamics rather than retrospectively adding the pressure-dissipating portal extensions to tunnels that had already been built. The famous super-sleek, elongated aerodynamic snouts of Japanese high-speed trains cause the pressure to build up more gradually when the train enters a tunnel.
Building on over 40 years of research by the international rail community, the engineering team from HS2 Ltd, engineering consultancy Arup together with the University of Birmingham and Dundee Tunnel Research, developed and laboratory-tested HS2’s tunnel portal design.
To mitigate against ‘sonic boom’ HS2’s tunnel beneath the Chiltern Hills requires bespoke portal extensions. Protruding up to 220 metres – around the length of two full-size football pitches – from a chalky cutting near the M25 motorway, they are each punctuated along one side with ventilation portholes. These enable some air pushed forward by the train to escape, making the pressure increase more gradual so that the micro-pressure wave emitted from the other end of the tunnel is undetectable.
Great progress all round!From the HS2 in your area map,
Bromford tunnels
Mary Ann 5560m, 40m to go, updated 21st April
Elizabeth 3440m, 2160m to go, updated 28th (sic) April
Northolt tunnels
Anne 4843m, 657m to go, updated 18th April
Emily 4992m, 557m to go, updated 18th April
![]()
In your area map
Search our interactive In Your Area Map to find information about current or planned HS2 construction works taking place across the route.www.hs2.org.uk
Exactly my thoughts. Really good steady progress which is great to see. Thanks for posting the updates.Great progress all round!
Looks like there will be a flurry of three completions in the next few weeks: Mary Ann at Bromford, Emily and Anne at Greenford.Progress is currently pretty rapid on the Downline (Emily)
Production record on our shift the other day at 13 rings in 10 hours.
Roughly 2 weeks and we will be finished.
Anne is roughly one month
Great work! Am I right that 1 ring is 2.0m wide?Progress is currently pretty rapid on the Downline (Emily)
Production record on our shift the other day at 13 rings in 10 hours.
Roughly 2 weeks and we will be finished.
Anne is roughly one month
1.9mGreat work! Am I right that 1 ring is 2.0m wide?
No doubt there will be PR events to celebrate.
Could be, also all 4 NT tunnels are not breaking through in the normal fashion and are just going into a steel can.I'm not sure about how much PR there will be.
It seems that politicians mainly want HS2 to stay under the radar.