LNW-GW Joint
Veteran Member
They are coming from Padacar (specialist Spanish concrete manufacturer) on the the Isle of Grain.Thanks, it would be interesting to know where the tunnel segments are being produced.
They are coming from Padacar (specialist Spanish concrete manufacturer) on the the Isle of Grain.Thanks, it would be interesting to know where the tunnel segments are being produced.
Ah ok. Thanks!, I thought the large site near the M25 producing the chiltern tunnel segments would be logical seeing as its nearby and operational but then again its not near a railway line/or connecting to the Chiltern line would be a challenge!They are coming from Padacar (specialist Spanish concrete manufacturer) on the the Isle of Grain.
There are different contractors for the two tunnels, and they have different supply strategies.Ah ok. Thanks!, I thought the large site near the M25 producing the chiltern tunnel segments would be logical seeing as its nearby and operational but then again its not near a railway line/or connecting to the Chiltern line would be a challenge!
We have revealed the final designs for the North Portal of the Chiltern Tunnel – the last of seven key structures. Once construction is complete, the ‘Key Design Elements’ will be the only parts of the tunnel visible to the community. Learn more: gloo.to/6sCM
HS2 Careers: Tunnelling Operative
new drone shot of the tunnelhs2 COPTHALL TUNNEL
Dorothy has probably finished its drive apart from the final few metres to the PR-staged breakthrough, which will have all the lights and cameras and VIPs that HS2 can muster as the twin-bore tunnel will be "finished".No news yet about Dorothy...
With no internet you had to ring a number to get a voice recording of the positions, much like getting the score at Test Matches...
Me too!Exactly what I did!
Did the Channel Tunnel progress have a Ceefax page? I'm not old enough to remember ringing for Test Match scores, but do remember the agonising wait for the ceefax page number to tick around.Exactly what I did!
no. Just a phone number in Folkestone.Did the Channel Tunnel progress have a Ceefax page? I'm not old enough to remember ringing for Test Match scores, but do remember the agonising wait for the ceefax page number to tick around.
No, the only railway information on Ceefax was the "Train Service Alterations" page in the Travel section, often in highly imprecise language.Did the Channel Tunnel progress have a Ceefax page? I'm not old enough to remember ringing for Test Match scores, but do remember the agonising wait for the ceefax page number to tick around.
Tunnelling was from intermediate locations, as close to the sea as possible, with drives doing inland and out to sea from both, so four TBMs for the main tunnels on each sideOut of interest, why did they need 5 TBMs on each side for what ended up being 3 bores? As I understand, one each direction + evacuation in middle.
It's a long time ago and I've lost the data I collected, but while there were 11 TBMs deployed, I think only 10 were in use at the maximum.For the Channel Tunnel I’m reasonably sure it was 11 TBMs. Only on the French side was one reused - for both the running tunnels from the shaft at Sangatte to Coquelles.
HS2 teasing something about Dorothy. Idk Dorothy's progress but perhaps a video of end to end?Good morning ! Some exciting news coming from TBM Dorothy today, keep your eyes peeled.
Video of Dorothy breaking through on the HS2 Instagram story. At long Itchington right?Login • Instagram
Welcome back to Instagram. Sign in to check out what your friends, family & interests have been capturing & sharing around the world.instagram.com
Dorothy fully broken throughTunnel boring machine (#TBM) ‘Dorothy’ has successfully completed her second one-mile tunnel drive underneath Long Itchington Wood in Warwickshire
When will this begin?eastern portal of Bromford tunnel to bore its third drive
Do you happen to know how many drives each TBM will be doing and in what order? (Or is there a link I've not found yet?).Dorothy now gets dismantled for the second time, and is then transported northwards to the eastern portal of Bromford tunnel to bore its third drive, 5.5km towards Curzon St.
I suspect there is still work to construct (without a TBM) a couple of emergency cross-passages between the two 1.5km tunnels, as these are normally at 500m intervals.
Preceding post referred to contractors, not TBMs?Out of interest, why did they need 5 TBMs on each side for what ended up being 3 bores? As I understand, one each direction + evacuation in middle.
As far as I know, only Dorothy will be doing more than one drive. The others are doing fairly long drives and it's common for them to only be used once. Parts do get reused, but they are not expensive when compared to the budget (£10-20m each), with each mile of tunnel costing at least £100mDo you happen to know how many drives each TBM will be doing and in what order? (Or is there a link I've not found yet?).
Would be interesting to see because the HS2 website sometimes implies a new TBM for each drive which seems somewhat excessive.
I suppose with the distances it would potentially extend the timescales if they had to wait for another TBM to finish, and geology probably comes into it.As far as I know, only Dorothy will be doing more than one drive. The others are doing fairly long drives and it's common for them to only be used once. Parts do get reused, but they are not expensive when compared to the budget (£10-20m each), with each mile of tunnel costing at least £100m
When will this begin?
Do you happen to know how many drives each TBM will be doing and in what order? (Or is there a link I've not found yet?).
Would be interesting to see because the HS2 website sometimes implies a new TBM for each drive which seems somewhat excessive.
Today [Thursday 30 March] HS2’s tunnelling team in Warwickshire celebrated the milestone breakthrough of tunnel boring machine ‘Dorothy’ as the giant cutterhead broke through the wall of the Long Itchington Wood Tunnel south portal.
Launched in November last year, it’s only taken four months for the 2,000 tonne TBM to complete its one-mile second bore, making this the first complete twin-bore tunnel on the HS2 project.
thanksThe first Bromford TBM is due to start up "soon", with Dorothy joining in "by the end of the year".
Only the Thames tunnel did, the others were all being driven at the same timeIIRC Crossrail reused most of it's TBMs at least once?
IIRC Crossrail reused most of its TBMs at least once?
As far as I know Dorothy is the only TBM doing more than one drive, and I think it will be partially rebuilt for Bromford.
All the other tunnels are long enough to have dedicated TBMs (5.5km or longer).
The first Bromford TBM is due to start up "soon", with Dorothy joining in "by the end of the year*".
The end of the year is also supposed to see the launch of the Northolt East pair of TBMs, with the Euston tunnels last to start early next year.
It's just possible the Chiltern pair will finish their job before the Euston pair start.
All the Phase 1 tunnelling is due to complete by end-2024, except the Euston tunnels which are a year later.
There are two short tunnels on Phase 2a, at Whitmore and Madeley, both of 700m.
With the recent pause situation for 2a, it's possible Dorothy or another Phase 1 TBM will bore them rather than deploying new ones.
Yet another TBM will be launched shortly to bore the logistics tunnel under the OOC site which will feed the Euston TBMs.
That is a smaller diameter tunnel than HS2 rail tunnels, and is 753m long.
It's not clear what that tunnel will be used for long-term.
* I see from today's announcement that Dorothy will start work at Bromford "early in 2024".
![]()
HS2 tunnelling team celebrate milestone TBM breakthrough in Warwickshire
2,000 tonne tunnel boring machine ‘Dorothy’ completes second bore of Long Itchington Wood Tunnel in Warwickshire Milestone breakthrough marks full completion of first twin bore tunnel on HS2 The Balfour Beatty VINCI tunnelling team celebrate the momentous event at the tunnel’s south portal...mediacentre.hs2.org.uk
Only the Thames tunnel did, the others were all being driven at the same time
Much obliged to you all for the info!nope. There were 8, and two were used twice.
most TBMs are on ‘first refusal’ with Herrenknecht For sale back and refurb of the parts.
For the Channel Tunnel I’m reasonably sure it was 11 TBMs. Only on the French side was one reused - for both the running tunnels from the shaft at Sangatte to Coquelles.
No, the French landward TBM, had its backup train split and was physically turned 180degrees in the cutting just beyond the tunnel portAl, it then worked back to Sandgatte shaft.
Not easy process to turn a TBM, think a concrete platform was laid, and it rolled onto air sledges, sort of cross between a hovercraft and giant air hockey game.
Temporary spoil disposal was used for that TBM return drive, not the piped slurry from the shaft to the reservoir by the forts.
To avoid going off topic, all TBMs are effectively a series of modules, otherwise wouldn't be able to deliver them to site, so unbolting the sections, moving them and rejoining is easy (the difficult part is road transport due to their size)