No RAIB report yet for the Bulwell Derailment on 12/6/23

tram21

Member
Joined
29 Dec 2022
Messages
139
Location
Nottingham
RAIB have yet to release their report into the Bulwell Derailment which caused a lot of speculation into what caused it, especially on this forum.

It was 6 months yesterday as to when this happened- is it normal for the investigations to take this long?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

DanNCL

Established Member
Joined
17 Jul 2017
Messages
4,296
Location
County Durham
That’s normal. It can take well over a year for a report to be released.

The Salisbury crash for example, that occurred on 31st October 2021 and the report wasn’t released until 24th October 2023.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
RAIB have yet to release their report into the Bulwell Derailment which caused a lot of speculation into what caused it, especially on this forum.

It was 6 months yesterday as to when this happened- is it normal for the investigations to take this long?
I think over 6 months is perfectly normal, sometimes you can wait a year or two. Sometimes there are interim reports.

Are you already sure there’s an investigation going on?
 

Mcr Warrior

Veteran Member
Joined
8 Jan 2009
Messages
11,861
I think over 6 months is perfectly normal, sometimes you can wait a year or two. Sometimes there are interim reports.

Are you already sure there’s an investigation going on?
Reports at the time of the incident indicated that there would indeed be an RAIB report.


Extract...
Tram derailment at Bulwell
Investigation into the derailment of a tram at Bulwell, Nottingham, 12 June 2023.

From: Rail Accident Investigation Branch...
We will publish our findings, including any recommendations to improve safety, at the conclusion of our investigation.
This report will be available on our website.

See also...

P.S. Noted that the RAIB report into the track worker struck by a train at Bulwell, Nottingham over a decade ago on 6th August 2012 wasn't published until October the following year.
 

ModernRailways

Established Member
Joined
21 Apr 2011
Messages
2,050
RAIB have yet to release their report into the Bulwell Derailment which caused a lot of speculation into what caused it, especially on this forum.

It was 6 months yesterday as to when this happened- is it normal for the investigations to take this long?
In short, yes.

Most full RAIB reports will take around 9+ months with some taking significantly longer, it all depends on the complexity and other agencies involved. There may be interim reports, especially if it's something safety related that the operator could immediately act upon to help ensure no repeats.
 