There have been previous threads about this topic but they all seem to be closed down so I thought I would start a new one.
I saw this on the Network Rail Media website:-
www.networkrailmediacentre.co.uk
Also this on the GWR website
www.gwr.com
According to the above articles it starts in earnest tomorrow which is 10/09/2022 with the main line closed between Plymouth and Penzance. The bulk of the work will be completed in October/November this year with the main line closed between St Austell and Penzance Tuesday 31/10/2023-05/11/2023 and Plymouth-Penzance 06/11/2023-12/11/2023 throughout.
Also I found this from the Rail Engineer dated 20/04/2022:-
www.railengineer.co.uk
From what I can gather it looks like everything west from current boundary of Exeter Power Box comes under the scheme with new work stations taking over, these are to be installed in the current Exeter PB.
As a matter of interest the Plymouth Power Box started operations on 26/11/1960 which now makes it 63 years old, so never mind how old the Semaphore Signals are that exist west of Saltash.
Of course it is sad to see these Semaphore Signals go, I feel they have been iconic for this part of the railway world, but sooner or later it was on the cards.
Also I see that Network Rail are installing new lifts at St Erth Station which are due for completion next spring, I have struggled myself with very heavy suitcases over the existing bridge to get onto the St Ives Branch so this is very welcome.
So anybody that can get down to or lives in Cornwall there is not much time left to get photos of one of the few remaining main lines in this country to be controlled by Semaphore Signals.
I saw this on the Network Rail Media website:-

Signal upgrade set to modernise Cornwall’s railway
This weekend Network Rail will begin the core phase of work to change the way the railway is run in Cornwall.

Also this on the GWR website
Planned Engineering Work and Disruption | Great Western Railway
Find out about planned engineering works, travel disruption and changes to Great Western Railway's published train timetables here.

According to the above articles it starts in earnest tomorrow which is 10/09/2022 with the main line closed between Plymouth and Penzance. The bulk of the work will be completed in October/November this year with the main line closed between St Austell and Penzance Tuesday 31/10/2023-05/11/2023 and Plymouth-Penzance 06/11/2023-12/11/2023 throughout.
Also I found this from the Rail Engineer dated 20/04/2022:-

A modular approach to signalling in Cornwall - Rail Engineer
Plans to replace the traditional mechanical signalling and associated signal boxes in Cornwall have been around for over three decades. In the late 1980s, a proposal to outsource the project to one of the major signalling suppliers was seriously considered by the British Railways Board but was...

As a matter of interest the Plymouth Power Box started operations on 26/11/1960 which now makes it 63 years old, so never mind how old the Semaphore Signals are that exist west of Saltash.
Of course it is sad to see these Semaphore Signals go, I feel they have been iconic for this part of the railway world, but sooner or later it was on the cards.
Also I see that Network Rail are installing new lifts at St Erth Station which are due for completion next spring, I have struggled myself with very heavy suitcases over the existing bridge to get onto the St Ives Branch so this is very welcome.
So anybody that can get down to or lives in Cornwall there is not much time left to get photos of one of the few remaining main lines in this country to be controlled by Semaphore Signals.