richieb1971
Established Member
- Joined
- 28 Jan 2013
- Messages
- 2,018
We need to be a dictatorship with sensitivities then. Lol
They take time in most democracies. We are comparatively rapid. The recently opened LGV SEA fr9m Tours to Bordeaux was proposed by SNCF in 1992, first consultation in 1994, primary consent granted in 2009, opened in 2017. The continuation to the Spanish border was consulted 12 years ago, and there is still no agreement for it to be built. In Germany it takes far longer.
Tell me about it - four years!!! I had to drive to the Haydock area a couple of weeks ago. I lost count of the number of sets of roadworks - I think it was 6.
It sounds as if it is the bureaucracy surrounding the whole process (and I include within that issues of funding etc) which slows things down a lot more than the technical side, or the actual construction
Well it is my specialised subject.
I didn’t mention - the timescales quoted assume a positive and supportive political environment at all levels.
It might be more appropriate to say mothballed railway
I might site the new Berlin airport here. Scheduled to open in 2011
M25:
First proposed in 1913, more seriously in 1937, again in Abercrombie’s report of 1944, then again in GLCs ringways report of the 60s, which was taken forward (sort of). First few sections built 1973-76, most of the rest then built in stages 1979-1986.
In terms of process, the timescales are exactly the same, except for construction. Because road schemes don’t need signalling, electrification, or integration testing, their construction is usually in the 18-30 month timescale (for any given section), unless here are very major civils (eg Queensferry Crossing).
Although it’s not always that quick - regular users of the MK to Northampton section of the M1 should note that there are 4 years of roadworks starting in the next few weeks, to enable all lane running. Which added to the 13 miles of roadworks between Coventry and Coleshill means that over a third of the route from the M25 to Birmingham will have roadworks... time for rail to advertise accordingly!
Read the very helpful information from @Bald Rick - he is prepared to give much more detail than I am and, frankly, has more patience than me! The process isnt, actually, overly bureaucratic when followed. The issue here is that this is a big project with a large number of vocal stakeholders each with their own desire for the project coupled with the "fluid" nature of the government financial commitment and their desire for "something different" in the delivery method
That's why I was trying to define 'bureaucratic' in the widest sense, to include ' fannying about by politicians and civil servants', or alternatively 'a constant buzz of purposeless activity to disguise the fact that they'd rather spend money on roads'
I suspect the process is as involved for a new road.
More of them seem to get built, though
I suspect the process is as involved for a new road.
Correct.
I think that when I have time (which isn’t now, sandwich in mouth) that I will explain wha is involved in getting to the start of the consents process, and what is involved in the consents process.
They really don’t.
There needs to be a distinction between:
1) projects that are someone’s pet idea that gets some traction and ‘widespread support’ (that someone could be a person, organisation or even a local authority)
2) projects that have official support from a funder that has money to do something about it.
The road schemes you tend to hear about are in the second category. Many of the rail schemes you hear about on these pages are in the first.
There are countless road schemes that don’t get built. One example - the A10 Foxton bypass; its been on the blocks since at least 1955; it has been designed at least twice. But not happening.
There are countless that do.
I live in the north-west. I can think of quite a few new road schemes built round here in the last couple of decades. As for railways, I can think of a couple of chords a few hundred yards long
They really don’t.
There needs to be a distinction between:
1) projects that are someone’s pet idea that gets some traction and ‘widespread support’ (that someone could be a person, organisation or even a local authority)
2) projects that have official support from a funder that has money to do something about it.
The road schemes you tend to hear about are in the second category. Many of the rail schemes you hear about on these pages are in the first.
There are countless road schemes that don’t get built. One example - the A10 Foxton bypass; its been on the blocks since at least 1955; it has been designed at least twice. But not happening.
There are countless road schemes that don’t get built. One example - the A10 Foxton bypass; its been on the blocks since at least 1955; it has been designed at least twice. But not happening.
Ironically, that particular road scheme would be of great benefit to the railway as it would divert a main trunk route away from a level crossing on a busy line......
Which isn't going to work, optioneering, design and consultation is always more time consuming.
So what happens in a time in the future when we must absolutely have something built or its going to have major consequences and you have to go through all this drivel? Each month that passes the trains are getting more crowded, the roads are getting more congested. If you have a process to build that takes up to 10 years to build anything, the problem has magnified into a bigger problem by virtue of following process.
There will become a time where the perception doing nothing isn't on the table. It may work up until now and it may work into the future a bit, but beyond that there will be pressure points.
I don't necessarily want to change the process as it seems sensible. What doesn't seem sensible is how long it all takes. Your using 2 extremes to describe something. On the one hand a communist way which shows results almost immediately vs a process which takes so long that half the staff that started the project are dead by the end of it.
All I am asking is would/could the process be accelerated in extreme circumstances. Say 1 million extra people went on trains tomorrow and people got home at 2am. Would EWR get a priority shove to be built in those circumstances if that was to alleviate the problem? Or would it takes another 5 years of pain on the railways?
Sounds like your saying it takes as long as it takes. But what ever problems arise in a project are eventually over ridden.
As of next month, from London to Cheshire there will be 4 major sets of roadworks:
1) M1 J13-J16 (unlikely to be the whole stretch at first) (finish 2022)
2) M6 J2-J4 (2020)
3) M6 J13-J15 (2022)
4) M6 J16-J19 (March 2019).
But 1 million extra people travelling is just not going to happen. In the unlikely event that they did, East West rail would not be a major priority. Putting the fares up, discouraging leisure travel etc. would kick in first, then maybe extra carriages on what train are running, with some platform extensions. Is your journey really necessary?I don't necessarily want to change the process as it seems sensible. What doesn't seem sensible is how long it all takes. Your using 2 extremes to describe something. On the one hand a communist way which shows results almost immediately vs a process which takes so long that half the staff that started the project are dead by the end of it.
All I am asking is would/could the process be accelerated in extreme circumstances. Say 1 million extra people went on trains tomorrow and people got home at 2am. Would EWR get a priority shove to be built in those circumstances if that was to alleviate the problem? Or would it takes another 5 years of pain on the railways?
Sounds like your saying it takes as long as it takes. But what ever problems arise in a project are eventually over ridden.
thanks. pretty much nailed it,even if I was going off on a bit of a rant.It think the point is (and this thread is about progress after all) that glacial could be accelerated to merely slow without loss of democracy if the will were there. As it is all the people involved have a vested interest in making it as slow as possible as when they finish they need to find another job. Back more on topic the Eastern part of E-W has a lot of options (which seem still unresolved despite 25 years elapsed) and the Western part had basically one option plus the question of Bletchley and Bedford station arrangements, the latter largely contingent on the result of the three decades of fevered thought about the Eastern section. Back completely on topic where are we with the plans for Bletchley, Bedford and the Eastern section?