No. Loco changing was done, but sub optimally, reducing the capacity of Preston station as a whole.
So which trains could not fit in the timetable because of the necessary engine changes at Preston eating up capacity?
No. Loco changing was done, but sub optimally, reducing the capacity of Preston station as a whole.
You want me to produce a notional timetable from 1976 indicating which trains had to be removed due to lack of capacity? No can do.So which trains could not fit in the timetable because of the necessary engine changes at Preston eating up capacity?
You want me to produce a notional timetable from 1976 indicating which trains had to be removed due to lack of capacity? No can do.
What I can say is that, at the time, we were told the new track layout was designed to accommodate 80% of the trains currently running, as that was the estimated requirement for trains going forward.
After remodelling, it was demonstrated that 80% of the trains that previously ran were now running, thus proving the accuracy of the previous estimates! Such are the policies/economics (call it what you will) of the madhouse.
No. Loco changing was done, but sub optimally, reducing the capacity of Preston station as a whole.
Nasty cough you've got there Joseph. Of course those lines are NOW electrified, as I mentioned in my post, 40 years later. Meanwhile, for most of those 40 years loco changing was a sub optimal process eating into station capacity.
It could hardly have accommodated any more, so less trains ran! Cause and effect?In other words, the layout successfully accommodated the level of service it was designed for.
It could hardly have accommodated any more, so less trains ran! Cause and effect?
Most of those increases involve MUs. There is no way of knowing just what services never saw the light of day in the late 1970s-1980s due to restrictions on loco changing and other restrictions caused by the remodelling.Fundamentally the same layout has accommodated all the various service increases from the mid-1990s to the present day.
I really can't let comments like this pass unchallenged. A quick check of the 1976 timetable (after the electrified WCML timetable had settled down) confirmed my recollection. For example, a normal weekday morning in Preston:Most of those increases involve MUs. There is no way of knowing just what services never saw the light of day in the late 1970s-1980s due to restrictions on loco changing and other restrictions caused by the remodelling.
It has to be remembered that "making the services fit the layout" included things like removal of Blackpool to London services.
?A remodelling of Preston in the early 1970s allowed for no engine movements for loco changing on Blackpool, Liverpool and Manchester trains
It has to be remembered that "making the services fit the layout" included things like removal of Blackpool to London services.
It would appear that my recollections are wrong. My only defence is that by the time the scheme was completed I had left the Preston drawing office for pastures new.I really can't let comments like this pass unchallenged. A quick check of the 1976 timetable (after the electrified WCML timetable had settled down) confirmed my recollection. For example, a normal weekday morning in Preston:
0941 Liverpool Lime Street-Glasgow Central. Arr 1033, changes traction, departs 1041
0956 Manchester Victoria-Glasgow Central and Edinburgh. Arr 1040, changes traction, departs 1048
0800 Euston-Blackpool North. Arr 1058, changes traction, departs 1107
0800 Glasgow Central-Manchester Vic and Liverpool Lime Street. Arr 1040, changes traction on front portion, departs for Manchester at 1051.
Fresh locomotive then attached to rear portion and departs for Liverpool at 1059.
How on earth could five trains be dealt with like this in around half an hour if...
?
It would appear that my recollections are wrong. My only defence is that by the time the scheme was completed I had left the Preston drawing office for pastures new.
Maybe a few extra crossovers were slipped into the scheme at the last minute when it was realised that electrification wasn't going to happen.
Around the time the electrification of the northern WCML was completed I used to do 6-8 round trips per year between Manchester and Edinburgh. I always found it frustrating that changing locomotives at Preston took so long, cancelling much of the time gains elsewhere.
I also bought a copy (which I probably still have somewhere) of the book "Electric Euston to Glasgow" by O.S. Nock. If I remember correctly, Nock compares the layout at Preston unfavourably with that at Crewe, criticising the lack of features to facilitate quick and easy locomotive changing, such as the handily-placed shunting necks that then existed at Crewe. Perhaps this is the point furnessvale intended to make.
Isn't that what I said in #22?Although at the time it was probably expected that Manchester/Liverpool electrification would have followed quickly in the subsequent years negating the need for loco changes...which then proved not to be the case.
Isn't that what I said in #22?
I'll try to find my copy. I'm fairly sure it said the things I mentioned. I don't think I have a later edition. My copy is full of pre-wiring photographs, perhaps due to the time it took to produce a book in those days. I think it was written late enough that he had had sight of the post-May-1974 timetable.Well, I've re-skimmed Nock's book and found no reference to problems at Preston such as Snowball describes. Perhaps there was a second edition (?) as the first one was published before the overall scheme was completed in May 1974.
Exactly what I said in #30.Yes, but the loco changes could still happen, just a bit less elegantly.
Reminds me on Bearley Jct near Stratford OA. The junctions diamond crossing actually had point blades within it as the angle was tight; it was not a slip, only worked as a diamond.
I'd read switch diamonds were not considered very favourably.A switch diamond? Pretty common (or were, there are fewer of them around these days).
I'd read switch diamonds were not considered very favourably.
Are there any informative resources about track design (thinking of in urban areas and station vicinities)? How switches, slips and crossings are organised and laid out? Are the more complex elements built are required, or do they generally simpler if space allows?
As a child I was always amazed at the complexity on some routes. And wondered if there was a ‘design manual’.
And train planning, many an occasion in the past where we have been forgotten, things have developed and a sponsor gets a bit upset when we say "that doesn't deliver the timetable"As stated above, there are various documents.
Officially track layouts (especially junctions, complex station areas and other complex areas) are supposed to be designed after discussions between the relevant train operator(s) (both passenger and freight), Network Rail operations, the Permanent Way engineering section, the Signalling engineering section, if relevant, the overhead line (OHL) or third rail engineering section, and if relevant the structure engineering section.
Factory made track panels are the preferred method of construction at the moment. Whereas in the past, bespoke designs constructed on site were sometimes used to fit a more complex layout in.
The overall cost of the design is a very big factor, so wherever the cost can be reduced by simplifying the layout, this will take place. Hence single lead junctions with standard crossovers having displaced more traditional junction layouts.
As well as the very practical consideration of fitting points and crossings in to the layout. Clearances, overlaps, standing room, braking distances all have to be considered during the design of the signalling system. As does the positioning of the signals.
And if if the line is electrified or due to be electrified, the relevant infrastructure (e.g. the poles, masts etc.) all have to be considered.
If there is a level crossing, the highways authority may also need to be consulted.
So it can be a very complex task.
Each engineering section has its own documentation on the requirements in a design.
Or someone comes up with an operational requirement they hadn't thought of before, that throws everything back to square 1.And train planning, many an occasion in the past where we have been forgotten, things have developed and a sponsor gets a bit upset when we say "that doesn't deliver the timetable"