• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Transpennine Route Upgrade and Electrification updates

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,607
Location
Nottingham
EXACTLY. If the teams can now just to be left to get on with it quietly and without fuss or interference, great results can be had.
That depends if they are delivering the cost improvements needed to justify continuing electrification.

The contractors and the customer need continual pressure to get costs down, and to disseminate best practice across the industry. And my limited understanding of the process suggests that isn't really happening.
 

John R

Established Member
Joined
1 Jul 2013
Messages
4,508
That depends if they are delivering the cost improvements needed to justify continuing electrification.

The contractors and the customer need continual pressure to get costs down, and to disseminate best practice across the industry. And my limited understanding of the process suggests that isn't really happening.
But TRU is a lot more than just electrification. Maybe progress on the MML is a better litmus test for future "vanilla" electrification projects?
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,607
Location
Nottingham
But TRU is a lot more than just electrification. Maybe progress on the MML is a better litmus test for future "vanilla" electrification projects?
Well it's both. The MML and GWEP projects mentioned were pure electrification. TRU is electrification and upgrade with extra tracks too.

But the cost of TRU was estimated at £2.9bn in 2018, and then jumped to £11.5bn in 2022. (plus an extra £1bn added since then) So TRU has been suffering from the same unconstrained cost explosion that all rail projects seem to have experienced in the past five years. Just letting the rail industry get on with it and paying whatever bill they eventually present to the taxpayer is not getting good value for money,
 

josh-j

Member
Joined
14 Sep 2013
Messages
224
Well it's both. The MML and GWEP projects mentioned were pure electrification. TRU is electrification and upgrade with extra tracks too.

But the cost of TRU was estimated at £2.9bn in 2018, and then jumped to £11.5bn in 2022. (plus an extra £1bn added since then) So TRU has been suffering from the same unconstrained cost explosion that all rail projects seem to have experienced in the past five years. Just letting the rail industry get on with it and paying whatever bill they eventually present to the taxpayer is not getting good value for money,
I thought the scope of TRU has been increased quite a lot since 2018 though. Generally I think value for money would be much improved by bringing a lot of engineering skill in-house rather than having contractors subcontracting to subcontracting subcontractors - as well as by proper planning without constant chopping and changing of scope.
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,363
It's arguably the section that gives the least benefit, as all it allows is LNER to run out of Leeds via Micklefield on Electric, which they don't do particularly often, and have bi-modes if they do need to do it in an emergency. OLE projects need to be based on a regular operation use-case, which is why I'd prioritise Doncaster-Hull via Selby, to get the benefits of the highest-revenue trains with the biggest economic impact (to/from London) to cover the largest section of costs. Once that's done, Selby-Micklefield is a smaller section of infill to allow local trains to go all-electric and the 4 chords (Sherburn-Gascoigne Wood, both Hambletons, and Selby avoiding) would be essentially part of the overruns anyway.

Possibly, although it's presumably not had any recent investigation or design work so you'd need to jump through PACE 1 and 2 extremely quickly to be able to follow on from the existing project without a break in the workflow.
I don't think Doncaster to Hull has a better business case than Micklefield to Hambleton. 5 to 6 trains daily that could use the wires doesn't look great. I think you need Hull to Leeds with the links between Selby and Doncaster and Selby and York (via both routes) all wired to make it worthwhile.

Oh trust me I agree with you. On time and under budget and continuing cost reductions needed.
In a way I think the East Kilbride wiring will be a better measure of how costs could be reduced simply because its a simple close, construct the scheme and reopen again. My personal view is this is what they should do / have done in chunks between Kettering and Nottingham, Derby and Sheffield.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
225
Location
Oxford
I don't think Doncaster to Hull has a better business case than Micklefield to Hambleton. 5 to 6 trains daily that could use the wires doesn't look great. I think you need Hull to Leeds with the links between Selby and Doncaster and Selby and York (via both routes) all wired to make it worthwhile.


In a way I think the East Kilbride wiring will be a better measure of how costs could be reduced simply because its a simple close, construct the scheme and reopen again. My personal view is this is what they should do / have done in chunks between Kettering and Nottingham, Derby and Sheffield.
Certainly on sections without lots of rail freight they should look at avoiding bridge changes etc.
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,334
That depends if they are delivering the cost improvements needed to justify continuing electrification.

The contractors and the customer need continual pressure to get costs down, and to disseminate best practice across the industry. And my limited understanding of the process suggests that isn't really happening.

A major problem with such an approach is that it leads to a seemingly constant stop-start process when someone decides this isn't the most effect way here, or that isn't the most effective way there. All you end up with then is the increased costs and overruns you were seeking to avoid; it's a self fulfilling prophesy. The best way of going about it is by customer driven even pressure so that you get a measured response, and that's usually done nice and quietly, at least to those on the outside, not through some media or political driven scrum.

Well it's both. The MML and GWEP projects mentioned were pure electrification. TRU is electrification and upgrade with extra tracks too.

But the cost of TRU was estimated at £2.9bn in 2018, and then jumped to £11.5bn in 2022. (plus an extra £1bn added since then) So TRU has been suffering from the same unconstrained cost explosion that all rail projects seem to have experienced in the past five years. Just letting the rail industry get on with it and paying whatever bill they eventually present to the taxpayer is not getting good value for money,

The last I heard TPU approved funding was £7.2bn but whatever it is, and even putting inflation aside the costs have been growing because the scope has been growing, from electrification to large scale rebuilds and route improvements. Few people were thinking seriously about big rebuilds between Huddersfield and Dewsbury or at Mossley when the program of electrification was launched. When 6tph was first mooted over 10 years ago a colleague and I decided the only way to get it to work reliably would be grade separation at Ravensthorpe, but we never seriously considered it happening!
 

Mag_seven

Forum Staff
Staff Member
Global Moderator
Joined
1 Sep 2014
Messages
10,815
Location
here to eternity
Another reminder that posts in this thread should be confined to Transpennine Route Upgrade and Electrification updates

thanks :)
 

Scotrail88

Member
Joined
21 Jul 2014
Messages
375
Sorry if noted above but are bi modes still changing at York when heading to Leeds?
If so, when will they continue to run on electric to Church Fenton?
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,032
Location
West Yorkshire / Birmingham
Sorry if noted above but are bi modes still changing at York when heading to Leeds?
If so, when will they continue to run on electric to Church Fenton?
It’s around Askham Bar, where the park and ride is that the changeover currently happens. I’m not familiar with the timescale that the electrification to Church Fenton will be used.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,047
Location
Bristol
Sorry if noted above but are bi modes still changing at York when heading to Leeds?
If so, when will they continue to run on electric to Church Fenton?
According to the Network Rail March update (screenshotted in the quoted post), Entry into service for Church Fenton - York electrification is currently programmed for April 2026.
https://www.networkrail.co.uk/who-we-are/publications-and-resources/ Is worth keeping an eye on, as at the bottom is the current Enhancement works document. (Latest is March 2025) https://www.networkrail.co.uk/wp-content/uploads/2025/04/CP7-EDP_March-2025.pdf
 

Top