And if/when the plan collapses under the fundamental inability of the industry to deliver, should the government just keep pouring money into the bottomless pit?
I dread to think how much the cost of the GWRM would have reached by the end if the government hadn't put the thing out of its misery
The government has no reason to have confidence that Network Rail's programme is going to go any better than the last time.
Or any better than Railtrack's did.
And how many mainlines are not already electrified at this point?
And many of the unelectrified ones are being partially or totally relieved of much of their traffic by the HS2 programme.
Are you sure you’re not Marvin The Paranoid Android? Have you lost the ability to be optimistic?
Any plan can go wrong. Fact. Absolutely everything made by mankind can be described as a bottomless pit, as everything either needs continuing maintenance or eventually replacing.
The fact is, an OLE programme has to be done. If we keep pushing it back, it will only get more expensive. At some point, using diesel engines will become unacceptable.
Part of the reason that the GWML OLE project failed was that they tried to go too fast, use new techniques and did not properly take into account learning experiences from previous engineering works. There was absolutely no reason for any signalling cables to have been hit, for example.
Now, there is nothing wrong with trying to find ways of doing things quicker, or using new techniques, but you don’t plan an entire large scheme on this without having back up plans and doing extensive trials first.
And you do some actual research before finalising the plans, and definitely before starting construction work. From what I know about the GWML OLE project, they didn’t do this (example, the problem of dealing with Box tunnel on the route, not knowing that there was both an underground signalling cable and an underground river to deal with, both of which some of the local engineering staff knew about).
There are still substantial amounts of unelectrified main line route miles across the country. The HS2 project does not mean that the existing lines can be ignored. One of the points of HS2 is to add much needed capacity in addition to the existing lines. The existing lines will not end up being lightly used.