It's soon to be underway...
Platforms 21-24 were taken out of use during the Christmas possession. AWS and signalling was disconnected.
13th February 2016 will be the last day of Platform 20's use.
14th February 2016 Platform 20 out of use and starter signal will be disconnected and removed.
April 2016 - June 2017. Waterloo International will be no longer be Network Rail infrastructure whilst construction takes place. Still physically connected to the rail network. Construction trains will run in and out of the station to carry out the required track and signal remodeling. Movements in and out will be under the control of Wimbledon Box and the Construction Manager. To be treated as a private railway during the works.
December 2016. Possession of Waterloo during Christmas to test and install interlocking for Waterloo International.
February 2017. Platform 20 handed back to Network Rail infrastructure.
June/July 2017. Platforms 21-24 handed back to Network Rail infrastructure.
August 2017. 21 day possession of Waterloo platforms 1-8 and South sidings. Platforms 21-24 in service. Reduced service into Waterloo during the possession. Once lifted platforms 1-6 will be available for 10 car workings. One of the sidingings in South sidings will be removed.
August 2017 - December 2018. Waterloo International closed again once platforms 1-8 are reopened to allow for station construction including shops, escalators and lifts level with road access.
December 2018. All works finished ready for the timetable change all platforms reopened.
All tallys up with the slightly sketchy information provided here http://www.networkrail.co.uk/wcip/
Platforms 21-24 were taken out of use during the Christmas possession. AWS and signalling was disconnected.
13th February 2016 will be the last day of Platform 20's use.
14th February 2016 Platform 20 out of use and starter signal will be disconnected and removed.
April 2016 - June 2017. Waterloo International will be no longer be Network Rail infrastructure whilst construction takes place. Still physically connected to the rail network. Construction trains will run in and out of the station to carry out the required track and signal remodeling. Movements in and out will be under the control of Wimbledon Box and the Construction Manager. To be treated as a private railway during the works.
December 2016. Possession of Waterloo during Christmas to test and install interlocking for Waterloo International.
February 2017. Platform 20 handed back to Network Rail infrastructure.
June/July 2017. Platforms 21-24 handed back to Network Rail infrastructure.
August 2017. 21 day possession of Waterloo platforms 1-8 and South sidings. Platforms 21-24 in service. Reduced service into Waterloo during the possession. Once lifted platforms 1-6 will be available for 10 car workings. One of the sidingings in South sidings will be removed.
August 2017 - December 2018. Waterloo International closed again once platforms 1-8 are reopened to allow for station construction including shops, escalators and lifts level with road access.
December 2018. All works finished ready for the timetable change all platforms reopened.
All tallys up with the slightly sketchy information provided here http://www.networkrail.co.uk/wcip/