mike57
Established Member
The WCML electrification from Weaver Junc to Glasgow was delivered in just over from 4 years for about 220 miles of railway from announcement to completion. Current projects such as parts TPE electrification seem to be progressing at glacial pace by comparision.
What can be done to speed them up? What has changed? Costs have also increased massively even taking into account inflation.
The original project cost for 1970 WCML work was apparently £25,000,000 which adjusted for inflation equates to around £500,000,000 in 2022 terms. Depending on the source the GWML electrification, which was a similar scale seems to have come in around £3bn, thats a 6 fold increase in real terms.
Was the BR approach more efficent, is the current obsession with sub-contacting everything making an environment where the companies involved get bogged down with the contractual arrangements rather than actually delivering the work.
The underlying technology is similar, and other technology advances should speed things up.
Where is the extra money going, assuming my 6 fold figure is roughly correct, the 'value' of the resulting infrastructure doesn't seem to be 6 times better. Or did BR hide the cost of projects in order to get approval?
So what would we have to do to deliver large scale electrification at inflation adjusted 1970 costs and similar timescales.
What can be done to speed them up? What has changed? Costs have also increased massively even taking into account inflation.
The original project cost for 1970 WCML work was apparently £25,000,000 which adjusted for inflation equates to around £500,000,000 in 2022 terms. Depending on the source the GWML electrification, which was a similar scale seems to have come in around £3bn, thats a 6 fold increase in real terms.
Was the BR approach more efficent, is the current obsession with sub-contacting everything making an environment where the companies involved get bogged down with the contractual arrangements rather than actually delivering the work.
The underlying technology is similar, and other technology advances should speed things up.
Where is the extra money going, assuming my 6 fold figure is roughly correct, the 'value' of the resulting infrastructure doesn't seem to be 6 times better. Or did BR hide the cost of projects in order to get approval?
So what would we have to do to deliver large scale electrification at inflation adjusted 1970 costs and similar timescales.