• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Working Of Possesions

Status
Not open for further replies.

wensley

Established Member
Joined
29 Jun 2008
Messages
2,045
Location
On a train...somewhere!
I was wondering if anyone could enlighten me on the way a posession for track re-placement is worked. Especially if works trains are requiring access to the section of line being worked. Diagrams would be superb! ;)

Cheers
Jonathon
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

TheSlash

Established Member
Joined
7 Jun 2005
Messages
2,336
Location
Marwell Zoo
Somebody else can do the diagrams but here goes

First of somebody known as the PICOP, Person in Charge of Possession, takes a total block of the lines that will be affected, this done using Section T3 of the rule book, so possessions are often referred to as "T3s"
The Signalman checks that the sections of line concerned are free from traffic, and then prevents trains from entering these sections by placing the protecting signals to danger.
He Signalman tells the PICOP that his part of the job is now done. The PICOP then phones the Hand Signalmen and asks them to place detonator protection at the entrance and exit to the possession. This is 3 detonators and a flashing red stop board.
Next up depends on the area.
In DC land, the PICOP phones the Electrical Control Room Operator and requests an isolation of the traction current on all lines within the possession. There might be some jiggery pokery with hook switches but we'll leave that bit.
After confirming he has isolation, the PICOP phones the Engineering Supervisor, to ask him to test the conductor rail and apply a safety device known as Short Circuiting straps. These stop the conductor rail becoming accidently re energised
Another conversation and the PICOP gives the ES permission to start work.

The ES then phones various Controllers Of Site Safety to give them permission to start work.

Trains are booked in and out of possessions at set times, by now the first train should be approaching. It's signalled normally until it reaches the signal protecting the possession.
The Signalman phones up the PICOP and asks permission for the train to approach the possession limits. The Signalman authorises the driver to pass the signal at danger and approach the possession limit markers
The PICOP phones the Hand Signalman and asks him to lift the detonator protection, to allow the train into the possession. The Train goes into the posession and the Detonator protection is replaced behind it
Various trains are needed for a possession. One to be loaded with scrap track panel and the odd wagon for general scrap {off cuts of rail, old signalling equipment etc}.
Another train will have hoppers ready to be loaded with old ballast
Another train with have earth movers and ground rollers which are unloaded in the possession.
The old track is cut into 60ft panels and lifted onto flat wagons and taken away.
The RRV machines will dig out the old ballast and the formation below it, to a set level.
Then the ground is prepared for the new formation. It's rolled flat and a membrane put down.
New ballast is laid on top of this in several layers. The new sleepers are laid out in a set spacing and there alignment checked. The rails are then thimbled onto the sleepers using a special attachment for the RRV.
The rails are then attached to the sleepers using key. Then the ballast is laid onto the new track and abit of kit known as a regulator comes along and tidies up the ballast, ready for tamping.
The track is tamped and then regulated again. If there is time, it's the rails are then 'stressed' to create fully functioning Continuous Welded Rail {CWR}
Trains and machines exit the possession in the reverse sequence of how they came. They approach the possession limits and the PICOP asks the signaller for permission to let them out. The Signalman agrees, Detonator protection is lifted, train leaves and protection replaced.
COSS sign out and the ES removes his Short Circuiting Straps. He signs out with the PICOP. The PICOP re energises and gives up the possession to the signalman.
All between the last train Friday night and first train Monday morning ;)
 

Bayum

Established Member
Joined
21 Mar 2008
Messages
2,994
Location
Leeds
Nice to know that my dad has some sort of intelligence somewhere...
 

Metroland

Established Member
Joined
20 Jul 2005
Messages
3,212
Location
Midlands
More detail here:

http://www.rgsonline.co.uk/docushare/dsweb/Get/Rail-41595/T3is2.pdf

Couple of things to add...

Trains approach the dets protecting the possession/worksite with permission of the PICOP

Trains approach the dets leaving the possession/worksite with permission of the signaller.

At possesion limits: Three detonators are placed on the line concerned, 20 metres (approximately 20 yards) apart on the same rail PLUS a possession limit board is placed in the four-foot next to the middle detonator.

Worksites are protected by marker boards, red going in, yellow out.

Points leading across the possession don't need markers, but must be locked in position at the controlling signal box, and a reminder placed on them.

As described about, the possession is broken up into worksites, under the control of engineering supervisors, who control movements in their section - unsignalled, points sometimes worked manually, and with hand signals. The line outside the work sites, within the possession, is controlled by the PICOP.

With overhead line, it isn't always isolated when there is a possession on the track, it depends on the work going on if there is a booked isolation.

Possession and OHL isolations are published in the weekly operating notice, and cannot be taken without prior notification.
 
Last edited:

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,773
I'm guessing doing that sort of work on a single track line is actually trickier? as you can't have an engineering train come alongside...
 

Metroland

Established Member
Joined
20 Jul 2005
Messages
3,212
Location
Midlands
Yep. Although they don't like doing single line working/bi directional working so much now, after some of the contractors put road-railers through the sides of trains.

With single line working, one line is closed on a double track. The other remains open, and is under the control of the pilotman, a qualified personal that rides through with trains or writes tickets to authorise them through.

Access to the open line from the opposite running direction is often through ground frames, that are manned and worked under the instructions of the signalman. Handsignalmen are also placed at Ground frames, certain sets of points, level crossings (which are often worked under local control), and at some signals. These all work to instructions from the signaller.

One train is allowed on the single line at one time, except in track circuit block areas, where they can run one behind the other, on signals, in the right direction. The pilotman either rides through with the train, with a appropriate form agreed with the signaller(s), or hand ones to the driver concerned, if a train is to be sent behind another.

The pilotman MUST be present to authorise a train through the single line.

Clearly the whole process is time/human resource intensive and requires a lot of organisation on the part of the signallers who must make sure points are clipped/scotched in the right position or worked manually, as well as looking after the level crossing aspect, where barriers are also worked manually in some cases. And clearly there is potential for error, although it is quite rare. Nevertheless, like possessions, it is down the safe working and clear communication of staff, to ensure overall safety, with little or no signalling interlocking back up.


Things have gone wrong in the past, the most famous incident in relatively recent times being at Singleton bank 1961

http://www.railwaysarchive.co.uk/documents/MoT_Singleton1961.pdf

Bi-directional working is simply where signals are provided - quite common on the continent to have both running likes signalled for each direction, here it is rare except on very busy main lines or around major stations.

Some lines, such as the WCML, ECML, MML, SWML and GWML have simplified bi-directional signalling to work around possessions and other problems.
 

GB

Established Member
Joined
16 Nov 2008
Messages
6,468
Location
Somewhere
Yep. Although they don't like doing single line working/bi directional working so much now, after some of the contractors put road-railers through the sides of trains.

With single line working, one line is closed on a double track. The other remains open, and is under the control of the pilotman, a qualified personal that rides through with trains or writes tickets to authorise them through.

Access to the open line from the opposite running direction is often through ground frames, that are manned and worked under the instructions of the signalman. Handsignalmen are also placed at Ground frames, certain sets of points, level crossings (which are often worked under local control), and at some signals. These all work to instructions from the signaller.

One train is allowed on the single line at one time, except in track circuit block areas, where they can run one behind the other, on signals, in the right direction. The pilotman either rides through with the train, with a appropriate form agreed with the signaller(s), or hand ones to the driver concerned, if a train is to be sent behind another.

The pilotman MUST be present to authorise a train through the single line.

Clearly the whole process is time/human resource intensive and requires a lot of organisation on the part of the signallers who must make sure points are clipped/scotched in the right position or worked manually, as well as looking after the level crossing aspect, where barriers are also worked manually in some cases. And clearly there is potential for error, although it is quite rare. Nevertheless, like possessions, it is down the safe working and clear communication of staff, to ensure overall safety, with little or no signalling interlocking back up.


Things have gone wrong in the past, the most famous incident in relatively recent times being at Singleton bank 1961

http://www.railwaysarchive.co.uk/documents/MoT_Singleton1961.pdf

Bi-directional working is simply where signals are provided - quite common on the continent to have both running likes signalled for each direction, here it is rare except on very busy main lines or around major stations.

Some lines, such as the WCML, ECML, MML, SWML and GWML have simplified bi-directional signalling to work around possessions and other problems.


Think he means actual single lines rather than double track lines.
 

Metroland

Established Member
Joined
20 Jul 2005
Messages
3,212
Location
Midlands
Thank you, I know. But there is some additional info there for when possessions are sometimes taken on double track lines.
 

heart-of-wessex

Established Member
Joined
11 Jun 2005
Messages
3,040
Location
Trowbridge
and of course remembering the signaler sets the signal to danger as slash said, but also collars the signal so there is no way you can set the route unless he is dumb enough to remove it all and let a say 158 pass, which would be silly and would trip the detonators and god knows what....doubt it'll ever happen :lol:

Very interesting read though!

BTW on that subject of work machines and engineers sets (be it 66 sets or just a tamper) does the drivers have route knowledge of a network or are they all piloted?


Cheers,

James.
 

chappers

Member
Joined
5 Mar 2008
Messages
76
I'm guessing doing that sort of work on a single track line is actually trickier? as you can't have an engineering train come alongside...

Yes, far far more so! Normally get much more mid-week night preparation possessions to lay out materials etc. Single Line renewals are far less dependent on trains initally - panels get stacked to the bank, spoil gets piled up. Plenty of fancy kit coming online to improve the productivity on single lines. I could go on and on about why they are more difficult though!
 
Status
Not open for further replies.

Top