The plan was always for all 4 MNOs, I believe. There's sufficient infrastructure (4 sets of radio panels) in the planning docs for this.
View attachment 157028
I believe so but contractual agreements could be imposed to force them to join every site rather than a selection.
Thanks, you have been a font of knowledge on this.
Sorry for the slightly dumb questions but if one MNO has good coverage on a part of the route already, are they going to let other MNOs use the site under this scheme or will they build a new one? I understood one of the tunnels had a situation with good coverage on O2/VF but not EE and Three.
Additionally, I understood they planned to install infrastructure in the tunnels too and also some specialist solutions in the cuttings, do these also require planning permission?
I am also always curious what "good" coverage on a train is, is there a figure the MNOs will target to consider sufficient coverage?
Thanks!