Sigh.
There is so much on this thread that is assumed and incorrect. I suggest everyone reads the Government announcement - and carefully
The project is not being paused for two years.
It was always the case that OOC - Curzon St would open first (a captive system), followed by Delta Jn to Handsacre for OOC - ‘the north’ trains. This doesn’t change, nor does the timing of that in the ‘2029-2033’ range. I expect to be on the first train.
Euston - OOC and Handsacre - Crewe were slated to open later, but at the same time. The announcement today is not of a two year delay, but of using the next two years to rephase 2a and deliver an ‘affordable‘ Euston. Euston is a massive job, as anyone who has looked at the site and the very large holes in the ground and thousands of tonnes of concrete already poured will testify. Work will continue.
The Government has restated its commitment to Euston to Manchester. Whilst it may be for the next Government to progress delivery, it would also be that next Government to decide if they didn’t want to do so. The chances of that are effectively nil, as by then the bill will be an Act, land will be purchased, and the business case even better.
For those that think it should have been built north to south - please do think about that. Specifically, about the benefits of doing so, compared to going south to north.