59CosG95
Established Member
Could not DafT have specified the use of Brecknell Willis pantographs?
I believe they are Brecknell Willis pans on the IEPs.
Could not DafT have specified the use of Brecknell Willis pantographs?
25kV cable along the train, is it beyond the wit of man to connect 2 units? Even if it is not possible for a 25kV cable to connect 2 units could DafT not have specified longer units?
That is so ugly by comparison with BR designs or the type used on the French-designed high speed lines.
--- old post above --- --- new post below ---
Are we in danger of setting the clock back here?
The 2 pantographs at high speed problem has been known since at least the 1970s. It was the reason why BR built the APT-P with 2 power cars in the middle of the set rather than one at each end - so they could share a pantograph.
Meanwhile, SNCF built the LGV Paris Sud-Est for 270km/h running (167mph) with only a single pantograph by putting a 25kV cable along the roof of the train to supply a power car at the other end. Atmittedly they used stiff OHLE with a high-pressure Faiveley Pantograph.
BR approached the high speed problem differently and developed the Brecknell Willis high speed pantograph which effectively became the British Standard. The design Brief for the new "pan" was - correct me if I am wrong - to work at high speeds (up to 250km/h) and was supposed to obviate, or at least reduce, the standing wave problem with multiple pantographs.
In the early 90s BR trialled 140mph running on the ECML using the new pantograph (albeit only one per train) and the Flashing Green "Fifth Aspect".
But now we will have IEP running on the ECML with 2 Faiveley pantographs per train - so we need to upgrade the ECML OHLE!
Could not DafT have specified the use of Brecknell Willis pantographs?
Since the TGV (and Pendolino???) have demonstrated the safety of the 25kV cable along the train, is it beyond the wit of man to connect 2 units? Even if it is not possible for a 25kV cable to connect 2 units could DafT not have specified longer units?
Since the TGV (and Pendolino???) have demonstrated the safety of the 25kV cable along the train, is it beyond the wit of man to connect 2 units? Even if it is not possible for a 25kV cable to connect 2 units could DafT not have specified longer units?
Chard-based Brecknell Willis will provide two twin-strip single arm pantographs for each of the 92 trains for the Intercity Express Programme, which are destined for the newly electrified Great Western Main Line and the East Coast Main Line.
Richard Whitefield, Managing Director for Brecknell Willis and Jamie Foster, Procurement Director for Hitachi Rail Europe marked the event with an official photo opportunity.
The first pantograph systems will be shipped from the UK to Japan for installation and testing on the first three pre-series Class 800 series trains.
I don't think anyone has yet attempted to run a 25kV bus line through the end coupling of a unit that is coupled and uncoupled frequently. It's probably do-able in principle but it would be a new development of the kind that has a tendency to be unreliable.
It would need to be a double sealed connection with a dry air supply. The amount of contamination that the connector gets from water, salt, insects etc. would require a cleaning operation before 25kV was applied. Hardly worth the operational risk. Better to schedule 110 running for those diagrams. How much difference would that make on a run as far as Exeter or Plymouth?
Everyone except those who have to pay for it.However, nothing that is being proposed on the ECML is unreasonable in itself or would be totally unjustified if 140mph running never happens. Replacing headspans with gantries or cantilevers will benefit everyone, and the replacement and strengthening of the various wires will be helpful when more and more traffic on the line will use electric traction.
At the moment, it's only the London commuter services and the IC225s which need the wires, but in the not-too-distant future, it will be diesel services which will be in the minority.
Everyone except those who have to pay for it.
It is weird that a company that has recently squandered so much money on overspends that the electrification programme is in serious jeopardy is now proposing to spend some probably very large sum of money (possessions are going to be very expensive alone) on what is really gold plating.
I would think the leasing charges on the extra vehicles necessary to run 9-car sets instead of 5-car sets occasionally doubled could be paid for an awfully long time by the cost of this work. Even if you start crediting the delay minutes this is going to save - which are very minor as this does not solve the primary reliability issue on the ECML, which is between Newcastle and Edinburgh.
This is just an attempt to cover up how bad a decision the DfT Made with this obsession with doubling up trains.
The only services which are going to convert any time soon will be the HSTs when they are replaced by IEPs.
Everything else will still be diesel - especially now the MML project has effectively been axed.
The ECML scheme is not "gold plating" but providing an OLE system that is fit for purpose. The ECML OLE isn't all that far away from being life expired in any case and technical advancements with newer OLE systems make elements of the Mk.3 OLE very obsolete and undesirable.
Very interesting as always.
The WCML OHLE was replaced at around 40 years old, and was considered to be in very fragile condition for quite a time before that.
The ECML OHLE is already 25 years old, 30 years in CP6, so the same "wear and tear" issues are coming up.
I also noticed this week that the WCML north of Warrington now has an AT wire installed in some places (eg in the Lune Gorge), as part of the CP5 plan.
I imagine there is some plan to equip the ECML with this as well, during a future upgrade.
I also saw some auto-tensioners somewhere other than the Liverpool-Manchester scheme - maybe around Stafford, where the OHLE is being altered for the new layout and flyover.
So they must be part of the general OHLE design now.
Presumably they will be used on the GW scheme.
Reliability tends to follow an inverse bathtub curve, teething problems and manufacturing defects disappear rapidly to give good reliability through design life. Once end of service life is reached, failures occur at a rapidly increasing rate, and if timely renewal isn't undertaken you can quickly find your renewal budget being diverted to urgent repairs instead.It may well be that this system will have lower maintenance - but I am really doubting that you will be able to build a positive BCR for the insane amount of work you are proposing. Cutting down fully half the masts and replacing them all? That is going to be enormously expensive - especially since these masts would not necessarily be the ones suffering structural issues.
As to tensioning - it is hardly necessary to do a wholesale replacement of the entire system in order to replace the balance weight tensioners, since there is only roughly one per track kilometre anyway.
And surely the easiest method of dealing with the life expiry of the headspan assemblies are replacement of the single headspans as and when they fail, either with new headspans or these gantries - rather than some wholesale programme.
And the fact remains that the ECML's current arrangements still remain reliable - indicating that the kind of incredibly extensive work you are proposing is unlikely to have a good BCR.
After all - Network Rail's estimates for this kind of work are consistently under.
Has the spur line physically been connected to the Chiltern Main Line yet, or is this awaiting a final possession?
It may well be that this system will have lower maintenance - but I am really doubting that you will be able to build a positive BCR for the insane amount of work you are proposing.
There are a few piles in the ground around Llanwern West Jn alongside the up main - are these the first ones in Wales (other than Maliphant depot)? There's also more lying down ready to be put in on the way up towards Bishton Flyover. Things starting to progress in South Wales
--- old post above --- --- new post below ---
Forgot to add, there's also quite a lot of piles in, especially on the up side, between Pilning and Patchway Tunnel. Good to see.
I have just come back from a round trip from London to Cardiff and opposite the Llanwern Steel Works there are around 6 piles on the up side and 4 on the down side, these are installed to cover the relief lines as well but as I said before this does not mean that all four lines will get wired.
As mentioned already elsewhere there has been electrification work in the pilning area, there are around 8 piles on each side of the track here.
Since I last travelled on this line a month ago I have noticed that more masts have gone up west of Burham and now reaches just east of Maidenhead.
The Reading train depot is now nearly fully wired and more support arms have been installed from Tilehurst going west past Pangbourne.
Between Tilehust and the junctions just east of Didcot, masts installed is about 80%, there are gaps through each station, over viaducts either side of Cholsey and one or two missing here are there.
I think the important thing to say here is that if the electrification was between Tilehurst and Didcot only, they would have no problem getting this done by the original target date of Dec 2016, but the rest of it is too far behind, I cannot see the outer suburban electrification being completed in 16 months at the moment never mind getting to Bristol, anyway I hope I am wrong.
Perhaps a way out is if the HST's start to clap out then they could run the Class 801's electric of out Paddington and then diesel mode from Airport Junction!
Next trip for me on the GWML will be just before Christmas so it will be interesting to see the progress, or lack of it!
But everything is running late, no two ways about it, hence the talk of wiring the main line out to Swindon as a priority - and using 800s on diesel power further west - then trying to recover the rest of the scheme.
That's what is odd about the activity at Pilning/Llanwern.
Why are they bothering with anything west of Stoke Gifford at the moment?
The only reason I can think of is they are trial installations to test the ground conditions.
Either that or it is a completely separate team independent of the HOPS kit.
There are locations where for various reasons they cannot use the 'high-output' train, Pangbourne being a case in point, so more traditional techniques are used for piling at these sites, which presumably is on a separate work schedule. And it will all have to be done sooner or later, so if the resources are there they might as well crack on, even if it appears a bit hit and miss for the moment.
The intention always was to wire Reading-Didcot first, in order to have somewhere to play with the pre-series Class 800s in 125mph trials and I don't see that changing, though the odds of it happening later this year as previously planned now look slim.
Why do the IEPs need to be tested on GWML? If its not ready surely the best place to test them is on the ECML where tests have already started? Therefore the only tests needed for IEP should be GWML specific.
Therefore the only tests needed for IEP should be GWML specific.
Can I refer you to the second sentence where I said
Surely non-route specific tests can be carried out on the ECML using the IEP test programme currently underway thereby reducing the number of tests required on the GWML and hopefully re-gaining some lost time on the project?
The testing that is being carried out on the Great Western is testing that can only be carried out on the Great Western. We're talking about safety critical signalling system testing, electrical interference and the like, not mundane things like making sure the air conditioning and toilets work.
The completion of the Reading to Didcot OLE shouldn't unduly alter the delivery of other parts of the project, there are different teams responsible for different stages of electrification, the piling team responsible for Reading to Didcot will have moved on and will be piling in another area when the actual catenary is being installed between Reading and Didcot. That's how the electrification scheme was always intended to operate, and that's why the HOPS train is configured the way it is.
The testing that is being carried out on the Great Western is testing that can only be carried out on the Great Western. We're talking about safety critical signalling system testing, electrical interference and the like, not mundane things like making sure the air conditioning and toilets work.
The completion of the Reading to Didcot OLE shouldn't unduly alter the delivery of other parts of the project, there are different teams responsible for different stages of electrification, the piling team responsible for Reading to Didcot will have moved on and will be piling in another area when the actual catenary is being installed between Reading and Didcot. That's how the electrification scheme was always intended to operate, and that's why the HOPS train is configured the way it is.
Philip, I hope you will accept how much your inside knowledge is appreciated, by me anyway, and I have a question on that subject. I have wondered why the project team just does not publish the full plans with critical path?
I can't see any down side to doing so and you never know; a keen observer could bring up a potential snag that could be very useful to the project team.
Perhaps naive on my part.
Ok understood, the only reason I kept pushing is because of this project
http://www.railmagazine.com/trains/current-trains/tomorrow-s-train-today
As the article says the train was tested on the Colchester to Clacton branch but they do not operate there instead operating between Liverpool Street / Kings Cross and Peterborough / Kings Lynn.