• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Cross-City Electrification from Barnt Green to Bromsgrove

Status
Not open for further replies.

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
just got a letter from NR (Simon Pugh, community relations))- salient points - wiring and energising of first stage to Barnt Green switch was completed on 12th March, All wiring runs were complete and registered by end of April. Now Completing last couple of weekends of final alignment, earthing and bonding. Energising of this section due on morning of 20th May
MENTOR runs on 24/25 April af 40, 60 and 75mph confirmed ok, Mechanical setup of catenary is very good.
ORR will be asked to approve by mid July. Driver training ls in progress, currently using a class 170 shuffling between Cofton and Bromsgrove. Current start of electric passenger service is 29th July
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
7,905
Location
Dalton GA USA & Preston Lancs
just got a letter from NE - salient points - wiring first stage to Barnt Green switch completed on 12th March, All wiring runs completed and registered by end of April. Energising of this section due on morning of 20th May
MENTOR runs on 24/25 April af 40, 60 and 75mph confirmed ok, Mechanical setup of catenary is very good.
ORR asked to approve by mid July Current start of electric passenger service is 29th July

Great news thanks for the update.
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
don't understand this RTT stuff for 5T62 - why are these dates out by a month, april not may apparently
 
Last edited:

Shrewbly

Member
Joined
21 Jan 2017
Messages
112
don't understand this RTT stuff for 5T62 - why are these dates out by a month, april not may apparently
Hi linuxlad7 - try this link

http://www.realtimetrains.co.uk/sea.../20/0000-2359?stp=S&show=all&order=wtt&toc=LM

Should show some test runs to Bromsgrove on Sunday 20th May.

5T62 (and some others) are the training runs that have been running for the last few weeks using diesel units. The ones on Sunday seem to be the first electric test runs with a 323, which fits in with what you've been told about energisation.
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
Hi linuxlad7 - try this link

http://www.realtimetrains.co.uk/sea.../20/0000-2359?stp=S&show=all&order=wtt&toc=LM

Should show some test runs to Bromsgrove on Sunday 20th May.

5T62 (and some others) are the training runs that have been running for the last few weeks using diesel units. The ones on Sunday seem to be the first electric test runs with a 323, which fits in with what you've been told about energisation.
Well that's better - found it.
In that context is 323 a generic term for an emu or can we take it as being the full and genuine article, with magical hill climbing powers
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,995
No, its timed for a 323 as that is all that goes down there. We are not going to work out running times for a random type of traction for the sake of it.
 

Shrewbly

Member
Joined
21 Jan 2017
Messages
112
Well that's better - found it.
In that context is 323 a generic term for an emu or can we take it as being the full and genuine article, with magical hill climbing powers

It's *probably* a 323, since it's coming out of Soho depot, it's a West Midlands Railway service, there'll be no shortage of 323s on a Sunday evening, and it would make sense to do a test run with a 323 into each of the platforms, but...

No, its timed for a 323 as that is all that goes down there. We are not going to work out running times for a random type of traction for the sake of it.

...and of course whether it runs or not depends whether energising goes OK.

I'm sure somebody will be there with a camera if it does run!
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
so has anything more been energised today yet (NR impied that was a morning job to finish lt off


The RTT log seems to refer to 323 movements much later in the day
 
Last edited:

Shrewbly

Member
Joined
21 Jan 2017
Messages
112
Well something just ran from Soho depot to Bromsgrove - so maybe, just maybe, it's live!
 

Laurencemcd

Member
Joined
4 Mar 2018
Messages
7
Was just at Vigo Bridge and yes a 6-car 323 did run to Bromsgrove, seemed to have no trouble racing up the Incline!
 

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
19,284
Location
West of Andover
Lovely video there Chris. Glad to see that the sparks effect is finally bearing fruit for Bromsgrove - now we just need to wait for the 29th of July!

Good news indeed, it will be a step change for Bromsgrove especially on Sundays going from 0.5 tph to 2.5 tph and to roughly 4tph during the week
 

bluenoxid

Established Member
Joined
9 Feb 2008
Messages
2,466
What would a diesel achieve and what would a non stopping Voyager achieve?
 

XDM

Member
Joined
9 Apr 2016
Messages
483
The 323 cleared the top of Lickey at 60+mph from the standing start

Interesting to know how many kWh of electricity were needed to get the 115tonnes of 323 to pass the top at 61 mph from stationary at Bromsgrove. Bet the air cooled traction motors were hot.
 

Class172

Established Member
Associate Staff
Quizmaster
Joined
20 Mar 2011
Messages
3,780
Location
West Country
What would a diesel achieve and what would a non stopping Voyager achieve?
The difference between a 170 and a 172 would also be an interesting one - I've only been in the latter up the Lickey Incline a couple of times, but it felt like it was near 40 at the top perhaps?
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
so now that the end is in sight
1 well done to all

2 how much did it cost

3 where next? Worcester ? Cheltenham/Gloucester Newtown?

4 wheres the freight??
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,498
Location
Between Peterborough & Bedlington
3 where next? Worcester ? Cheltenham/Gloucester Newtown?

4 wheres the freight??
I suspect Q3 & Q4 can be answered simultaneously; until such time as a long-distance electrified corridor between Bristol (at Westerleigh Jct) and Derby exists, there won't be much in the way of electric freight (if any).
If Worcester were to be done, it would make sense to do the Snow Hill Lines (i.e. Leamington/Stratford-u-Avon - Dorridge/Whitlock's End - Tyseley - B'ham Moor St/Snow Hill - Smethwick GB High Level - Stourbridge Jct - Kidderminster - Droitwich - Worcester Shrub Hill/Foregate St - Great Malvern - Hereford) as a whole package, throwing Stoke Works Jct - Droitwich in for good measure.
That's going to be some way off though, as the new Class 196s for WMR are bound for Snow Hill services.

I suspect politicians will want Bristol - Birmingham - Leicester/Derby to be done soon too, in tandem with the MML programme; again, this depends on the MML OLE reaching north of Market Harboro'!
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
we have some early leaf fall on milbury heath
(could indicate an early test of traction for the lickey?)
bob
 

linuxlad7

Member
Joined
9 Nov 2017
Messages
132
I ve seen the system described in Rail Engineer as boosterless classic but ATF ready - does this mean it can go faster before the solder melts
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,751
Location
Leeds
Probably means autotransformers could be added if ever the whole line to Bristol is wired.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,719
Location
North
What would a diesel achieve and what would a non stopping Voyager achieve?
Never been on a Voyager, but when they were loco-hauled by class 45/46/47 in the 1970s/80s/90s charging at 80mph at the bottom with 10 on, they would be doing around 34mph at the top. I couldn't put my hand on 35/42/43 hauled logs but I have some double headed Warships somewhere from 1968/69. I have only been down the Lickey behind Westerns. Notable was a run from New Street to Cheltenham stop in a few seconds over 36 minutes behind 1066 Western Nobleman in 1975 with a late running train off the 25kv to Plymouth. We touched 100 mph over the River Avon at Defford.
HSTs were only a few mph faster than loco hauled despite the higher power to weight ratio.
Once, on a charter from Gloucester, a class 40 struggled to make 20mph at the top.
 
Status
Not open for further replies.

Top