MotorcycleAlan
Member
- Joined
- 4 May 2012
- Messages
- 309
How ironic that on a day of chaos at Waterloo this should appear:
https://assets.publishing.service.g..._data/file/756874/R192018_181119_Waterloo.pdf
https://assets.publishing.service.g..._data/file/756874/R192018_181119_Waterloo.pdf
Summary
At around 05:42 hrs on Tuesday 15 August 2017, a passenger train was leaving
London Waterloo station when it collided with a stationary engineering train at a speed
of 13 mph (21 km/h). No injuries were reported but both trains were damaged and
there was serious disruption to train services until the middle of the following day.
The passenger train was diverted away from its intended route by a set of points which
were positioned incorrectly as a result of uncontrolled wiring added to the signalling
system. This wiring was added to overcome a problem that was encountered while
testing signalling system modifications which were being made as part of a project
to increase station capacity. The problem arose because the test equipment design
process had not allowed for alterations being made to the signalling system after the
test equipment was designed.
The actions of a functional tester were inconsistent with the competence expected of
testers. As a consequence, the uncontrolled wiring was added without the safeguards
required by Network Rail signalling works testing standards, and remained in place
when the line was returned to service.
A project decision to secure the points in the correct position had not been
implemented.
An underlying factor was that competence management processes operated by
Network Rail and some of its contractors had not addressed the full requirements
of the roles undertaken by the staff responsible for the design, testing and
commissioning of the signalling works.
The RAIB has observed that there are certain similarities between the factors that
caused the Waterloo accident and those which led to the serious accident at Clapham
Junction in 1988. The RAIB has therefore expressed the concern that some of the
lessons identified by the public inquiry, chaired by Anthony Hidden QC following
Clapham, may be fading from the railway industry’s collective memory.
As a result of the investigation, the RAIB has made three recommendations. The
first, addressed to Network Rail, seeks improvements in the depth of knowledge
and the attitudes needed for signal designers, installers and testers to deliver work
safely. Recommendations addressed to OSL Rail Ltd and Mott MacDonald Ltd seek
development and monitoring of non-technical skills among the staff working for them.
The RAIB has also identified four learning points. One highlights the positive
aspects of a plan intended to mitigate an unusually high risk of points being moved
unintentionally. The others reinforce the need to follow established procedures,
prompt staff to clearly allocate duties associated with unusual activities and remind
staff that up-to-date signalling documentation must be available and easily identified in
relay rooms and similar locations.
Last edited by a moderator: