Thanks for the share.
Is there a list of platforms requiring extension available?
From the March 2019 enhancement plan:
“4 car
Appleford – Platform 1 and 2.
Aldermaston – Platform 2.
Bramley – Platforms 1 and 2
Mortimer –Platform 1
8 car
Tilehurst – Platforms 1, 2, 3 and 4
Pangbourne – Platforms 1 and 2.
Goring and Streatley – Platforms 1, 2, 3, 4
Cholsey – Platforms 1, 2, 3 and 4.
Culham – Platforms 1 and 2.
Radley – Platforms 1 and 2.
Reading West – Platform 2.
Theale – Platforms 1 and 2.
Thatcham – Platforms 1 and 2.
Iver –Platforms 4 (resurfacing)
12 car
Slough – Platforms 2, 3, 4 and 5.
Maidenhead – Platforms 1, 2 ,3, 4 and 5.
Twyford – Platforms 1, 2 and 3.
Didcot - Platform 3 – (funded by IEP).”
Hope this helps