Some updates from this week. Additional ballast for the new P1 and P2 tracks has been added, P1 station canopy supports going up, concrete poured for the main station building first floor, and the forecourt starting to be levelled.
The station structure looks a month or two away from completion with internal fitout then required then commissioning/training so maybe tight for May 25 and im surmising it needs a tweak to the timetable to allow times for additional calls so Dec 25 looks the most likely date. I guess they could incorporate times in the May TT so giviing themselves such earlier option.What is the latest thinking on the opening date? I had been hoping for work to substantially finish in Q1 2025, with the station opening for the May timetable change, but now there are media references to "late" 2025 and I've even seen December mentioned.
Brilliant - thank you for the continued photographic updates. We shall be moving to the area soon, so look forward to being users of the station, in due course!Update 17th October: I had the drone up again yesterday, so here are some photos. Good progress on the access path this week plus a chance to see how quickly the station roof is coming along - it looks like there might be some soil up there now for the green roof. Also work underway on the water main under the railway, OLE for P1/P2 and the extension to the country park.
AIUI no definite opening date has been set but the plan is the end of 2025, presumably the timetable change date in December 2025. If the opening of Cambridge South Station requires the new East Coast Mainline timetable the earliest possible opening date anyway would be the timetable change date in December 2025.What is the latest thinking on the opening date? I had been hoping for work to substantially finish in Q1 2025, with the station opening for the May timetable change, but now there are media references to "late" 2025 and I've even seen December mentioned.
Don’t know for sure, but my best guess was that a certain amount of 4 track running was needed for the timetable and it was perhaps easier to fit this in on the north side.Does anyone know why it is different to the southern end?
Signals usually require an overlap past the signal to be clear before a train can be signalled towards that signal. For a train to be signalled into one platform while the other platform has a train present requires the merge point to be clear of the overlap. However on approach to a station the rear of the train just needs to be clear of the points before they can be switched and another train signalled into the other platform. If there are physical constraints north of the station the northbound lines would be prioritised for the longer distance.A random question about the track layout.
At the southern end of the station the lines converge from four to two quite in quite a short distance after the platforms end, but at the northern end the two lines of the eastern (hospital side) platform converge at a turnout that is already in place, but the lines from the western platform continue for some distance before it all merges back down to two lines.
Does anyone know why it is different to the southern end?
Thank you for the new pictures.Some photos from this morning. Another crane has arrived. Maybe they are going to lift in the P1 canopy now?
== Doublepost prevention - post automatically merged: ==
Edit 30th October: progress this week on the new OLE with one contact wire now in place. The canopy is also being installed for P1 and some supports have appeared in the forecourt which I guess are for bike parking.
Yes, this is my understanding, that with Cambridge station been so close to Cambridge South. Having two platforms available for both the up and down lines allow a 3 mins headway between services to be maintain.Don’t know for sure, but my best guess was that a certain amount of 4 track running was needed for the timetable and it was perhaps easier to fit this in on the north side.
Meanwhile at the site there has been work again this weekend. Crane has been on site lifting then island roof in to place. Also work going on on the track north and south of the new station.
Anyone know what the big metal H on the ground is for to the north of P2/P3? Looks like it might be a signal gantry or OLE but both already look catered for and it’s very substantial.
And for those following along - yet more helicopters and cranes together!
EWR, on the current plan, will need four tracks not only between Cambridge and Cambridge South, but also between Cambridge South and Shepreth Branch Junction. I would have voted for four-tracking the whole stretch now to build in resilience and future capacity. As it stands we will have -Yes, this is my understanding, that with Cambridge station been so close to Cambridge South. Having two platforms available for both the up and down lines allow a 3 mins headway between services to be maintain.
For example, a train can be dispatched from Cambridge in the up direction without the need for a second train which is already at platform at Cambridge South to have left as the first train can be signalled into the vacant platform at South. The same in reverse in the down direction.
In addition, though, I believe that East West Rail will require more four tracking between Cambridge and Cambridge South (In addition to extra platforms at Cambridge). But that possible belongs on another thread!
They probably could do it from start of July to end of August without causing too much congestion. During term time the congestion would be awfulI would have also liked to see four tracks all the way south to the junction, but I assume the risk of objections to the land take derailing the whole project wasn’t worth it.
As a local I am more sanguine on the long road bridge. It is heavily used by cars and the diversion would be long and on congested roads. I hope EWR can come up with a way of doing it over Easter or Christmas as the thought of months of gridlock doesn’t fill me with much joy.
Don't think so as it's on quite a high embankment and the college sports ground is right below it and the access road for st Mary's sport ground is on the other sideDepending on the duration required at Long Road...would it be viable to build a parallel temporary bridge with severe weight/speed restrictions for the duration of the construction of the real new bridge? Anything heavier than a car would still be sent on the diversion, but it would hopefully provide connectivity for the vast majority.
The high embankment that takes Long Road over the railway extends westwards to the bridge over the busway (the old track towards Bedford). The western end of the skew onto a temporary bridge would have to be constructed at embankment level, not ground level.Depending on the duration required at Long Road...would it be viable to build a parallel temporary bridge with severe weight/speed restrictions for the duration of the construction of the real new bridge?
I also think that it would have to be a summer holiday road and rail closure. Hopefully there would be a way of still bringing trains in and out of Cambridge South in the London direction. If so, then it is something far easier done after the new station is open than before.They probably could do it from start of July to end of August without causing too much congestion. During term time the congestion would be awful
I would have also liked to see four tracks all the way south to the junction, but I assume the risk of objections to the land take derailing the whole project wasn’t worth it.
I think I have said this elsewhere but the pairing methods used I feel depends upon whether EWR terminates at Cambridge or carries on beyond Cambridge to Ely / Norwich or towards Ipswich as has been talked about over the years.I get the narrowing between Cambridge and Cambridge South - saves rebuilding the bridge taking Long Road over the railway. If it's not essential now, leave it until later. The narrowing between Cambridge South and Shepreth Branch Junction, AIUI, serves the purpose of merging the lines and getting the trains in position so that the platforms at Cambridge South can be paired by direction, which if there's the line capacity for it, saves you building any grade separation.
When EWR comes though and the bottlenecks get removed, then AIUI the current plan is that lines become paired by use. Presumably at Cambridge main Shepreth Branch trains will get exclusive use of platforms 1-4, and the WAML services will get 7 and 8 (and maybe 9 and 10, if they get built).
The railway probably won't be closed as long as the roadI also think that it would have to be a summer holiday road and rail closure. Hopefully there would be a way of still bringing trains in and out of Cambridge South in the London direction. If so, then it is something far easier done after the new station is open than before.
Depending on the duration required at Long Road...would it be viable to build a parallel temporary bridge with severe weight/speed restrictions for the duration of the construction of the real new bridge? Anything heavier than a car would still be sent on the diversion, but it would hopefully provide connectivity for the vast majority.
Anyone know if the abutments at Long Road are far enough apart for 4 tracks? The existing bridge is supported on them and additional metal supports either side of the track bed. I wonder if there is enough space (and strength) such that the deck could be replaced with one that doesn’t require the intermediate support. Or perhaps a single central support. I fear we are getting into speculation though.