I see - in that case, will the new alignment be simply a larger radius curve in the current place?No, this old line is not being reinstated in any way.
I see - in that case, will the new alignment be simply a larger radius curve in the current place?No, this old line is not being reinstated in any way.
I edited my earlier post to say essentially that, yes, although it's probably more to do with replacement pointwork than the radius of the curve.I see - in that case, will the new alignment be simply a larger radius curve in the current place?
Carstairs South Jn goes from 30mph to 50mph crossing between the mains and 40mph towards Edinburgh but still a single lead. Main lines go up 100/120EPS. Up Passenger loop is 60at the north end and 40 through the station and round the chord to Carstairs East.
Even when HS2 was proposed to go to Leeds with a link to Church Fenton, the main London-Edinburgh route was proposed to be via the WCML between Wigan and Carstairs.
The issue today is that without the Golborne branch, but with a proposed ECML upgrade to improve Leeds/Newcastle times, the advantages of the WCML route to Edinburgh are less obvious.Fair enough. I thought at one point the fastest London-Scotland route was proposed to be up the ECML via Leeds.
The yellow perils I got were issued without diagrams - both the PDF and paper copies.that slide show doesn't represent what will be install. Not aware of any publicically available diagrams, no idea why not as the changes have been communicated to TOCs and FOCs via the yellow perils as usual.
Carstairs Junction will be modernised as part of a £164m Scottish Government investment in the railway.
Passengers are being reminded that the West Coast main line will close for 16 days from Saturday (March 4) as engineers deliver a vital programme of work to upgrade Carstairs Junction.
The closure of the line, between March 4 and March 19, is the first phase of a three-month programme of work which will also see trains diverted and journey-times extended all services between Glasgow/Edinburgh and Carlisle until June.
The work is part of a £164m Scottish Government investment to modernise the key junction for passenger and freight services.
Engineers will simplify and upgrade the track-layout to clear an existing bottleneck on the network, making it more reliable and able to better cope with passenger and freight demands.
Work on this strategically important route will be complex and Network Rail will complete it in three phases designed to manage the effect on services in the least disruptive way.
During the first phase of the project there will be no direct services to Glasgow Central and Edinburgh on the West Coast main line through Carstairs.
The closure of the junction will affect cross-border operators including Avanti West Coast, Caledonian Sleeper, CrossCountry Trains, London North Eastern Railway and TransPennine Express, who will be operating via diversionary routes or offering alternative journey options during this time.
Liam Sumpter, Route Director, Network Rail Scotland, said: “Carstairs Junction is coming to the end of its life cycle and with the volume of freight and passenger trains passing through each week it’s important that we modernise this part of the network.
“By completing this crucial upgrade work we will improve the capabilities and reliability of this strategically important junction, providing better future journeys for passengers and more capacity for freight.
“There’s never a good time to close such an important line but this is a huge and extremely complex piece of work that will safeguard the future of the route for years to come.
“We appreciate that this will cause some inconvenience and would like to thank customers for their patience during this time.”
Notes to Editors
Notes to editors
During the first phase of the project – between Saturday March 4 and Sunday March 19 - there will be no direct services to Glasgow Central and Edinburgh on the West Coast main line through Carstairs.
Phase two of the work, taking place between Monday March 20 and Friday April 21, will see part of the junction re-opening, allowing some trains to run directly to Edinburgh – and via diversion routes to Glasgow – on weekdays, however, journey times will be longer than normal.
The final phase, between Saturday April 22 and Sunday June 4, will see most services return to normal during weekdays with the junction fully closed each weekend.
During the later phases of the project, there will be no direct services between Glasgow Central or Edinburgh and Carlisle on the West Coast main line each weekend.
The closure of the junction will affect cross-border operators including, Avanti West Coast, Caledonian Sleeper, CrossCountry Trains, London North Eastern Railway and TransPennine Express, who will be operating via diversionary routes or offering alternative journey options during this time.
Services operating on the East Coast main line during this time are also likely to be busier than normal.
There will be no ScotRail services to or from Carstairs for the full three-month period. ScotRail will run a range of alternative journey options throughout with Carstairs station re-opening on Tuesday May 30.
Carstairs junction sits 26 miles to the south-east of Glasgow on the West Coast main line. Currently the junction requires regular maintenance work as much of the infrastructure through the area is reaching the end of its operational lifespan. Speed restrictions are often imposed which can affect performance.
The layout of the junction is no longer suited to today’s pattern and volumes of service with 200+ services passing through the junction on an average midweek day.
Enabling works for the project have been underway since 2020 and the work delivered during the line closure will see over 200 engineers working 24/7 to upgrade the junction.
The new power supply being installed will allow engineers to switch off the overhead lines remotely to carry out maintenance, reducing the amount of time the railway is closed in future. The improvements will also bring reduced overall journey times through the removal of a 50mph speed restriction.
Passengers are advised to check with National Enquiries www.nationalrailenquiries.co.uk or with their train operator for the alternative travel plans for their route.
Yes. But it's nevertheless a capacity improvement as the linespeed will be significantly higher.Single lead junction...really? Is that how it was before?
It's a flat junction across a major route - any substantial increase in resilience would need grade separation.For all the work going in, whole new section, why not just make it double and increase the resilience?
Chances are you wouldnt have got the speed increase as you wouldnt have had the space.For all the work going in, whole new section, why not just make it double and increase the resilience?
Chances are you wouldnt have got the speed increase as you wouldnt have had the space.
For all the work going in, whole new section, why not just make it double and increase the resilience?
Mods, please delete if sharing from another site is a problem.
screenshot of the new junction layout.
Passengers are being advised of changes to their journeys as the first phase of work to upgrade Carstairs Junction nears completion.
Following a 16-day closure of the West Coast main line, phase two of the programme, will see part of the junction re-opening to allow some trains to run directly to Edinburgh – and via diversion routes to Glasgow – on weekdays.
The work is part of a £164m Scottish Government investment to modernise this key junction for passenger and freight services on one of Scotland’s two cross-border routes.
The three-month programme will see trains diverted and journey-times extended on services between Glasgow/Edinburgh and Carlisle until June.
Engineers are working around the clock to simplify and upgrade the track-layout to clear an existing bottleneck on the network, making it more reliable and better able to cope with increasing passenger and freight demands.
During the first 16 days of the work, the focus was primarily on completing the south junction -installing and upgrading the track, signalling and overhead line equipment to enable passenger and freight services to connect to Edinburgh and to add an additional diversionary route for services to Glasgow.
Work on this strategically important junction is complex and challenging and Network Rail, alongside contractor partners, developed the staged programme to manage the effect on services in the least disruptive way.
The closure of Carstairs junction impacts on cross-border operators including Avanti West Coast, Caledonian Sleeper, CrossCountry Trains and TransPennine Express, who are operating via diversionary routes or offering alternative journey options during this time.
Open and trains RunningPress release
First phase of Carstairs Junction remodel nearing completion
Passengers are being advised of changes to their journeys as the first phase of work to upgrade Carstairs Junction nears completion.www.networkrailmediacentre.co.uk
Glasgow-Euston trains running (via Midcalder), but still very few direct Edinburgh services running.Open and trains Running
Be good to see if any notable speed benefits or probably too early given route knowledge and TSRs if work still ongoingI'll be travelling over this later this afternoon and will send in some photos of the Junction/station.
You would only see them on the day as it stands, they aren't reflected in the timetable.Be good to see if any notable speed benefits or probably too early given route knowledge and TSRs if work still ongoing
I’ve uploaded a video of passing over the south junction here:
The 40mph certainly makes a huge difference, feels much quicker already!
It’s been a good stroke of foresight that maintained the ability to use that last little section of the Up Shotts as a loop when the junction was reconfigured to double lead a few years ago.