jonesy3001
Established Member
The 2040 transport strategy plan for greater manchester.
Last edited:
"strategy"The 2040 transport plan strategy for greater manchester.
The plan is now on Rochdale Council website (ref 23/00744)Replace concrete deck with steel deck or decks built nearby, move them using modular transported, would be the likely solution? A few days work over a long bank holiday weekend perhaps?
plan seems to be to cut off a section at top of abutments and instal a new cill beam, but majority of abutments stayUnless one or both of the abutments have failed, which would take a while longer.
The bridge plan actually makes reference to adding electrification masts to top flange which will be considered at later dateThey must be doing the bridges and other works before they electrify the line to rochdale in 2030.
the notes on right on the plans refer to various surveys that reveal the concrete has spalled, and the rusting steelwork tendons are exposed and appears to have been poorly groutedIts a post tensioned bridge apparently. Doesnt matter who built it, it appears that they dont degrade in a very linear manner.
SCOPE OF WORK - OPTION 2
REMOVAL OF TRACK FORMATION AND PROVISION OF
TEMPORARY SUPPORT FOR SERVICES ACROSS THE STRUCTURE
REMOVAL OF EXISTING POST-TENSIONED CONCRETE DECK
DEMOLITION OF TOP SECTION OF ABUTMENTS /
WINGWALLS AND CENTRAL PIER TO DEMOLITION LINE
INSTALLATION OF PROPOSED CILL BEAMS
INSTALLATION OF BEARING ELEMENTS
INSTALLATION OF PROPOSED SUPERSTRUCTURE
INSTALLATION OF NEW TRACK FORMATION AND
REINSTATEMENT OF SERVICES
The 2040 transport strategy plan for greater manchester.
"strategy"
Exactly, none of which is funded or signed off, its an aspiration."Plan"
As I understand it, underline bridges for road schemes are built in a separate contract from the road, with the railway, or people acting for the railway, as designer, employer of the contractor, and supervisor of the contract, even though the contractor is often the same as for the road, and even though construction is paid for by the road scheme. So I would have thought it's all the railway's responsibility.Presumably it was built by the Motorway contractors to a spec from BR If it turns out that the contractors cut corners by, eg, using substandard concrete, then the rebuilding cost should come out of the Highways England budget. If it was built to spec, but that was inadequate, then NR will need to pay.
It will be based on whatever National Highways accept for M62 closures. It won't be 36 weeks of solid disruption, it will screw up any TRU access plans if it is. They won't stand for that, neither will Northern.As I've previously said, that bridge is absolutely knackered. There's rumours on the area that it'll be a 36 week job to get it replaced. Those rumours have been going on since early this year though and no one is really sure what's going on.
It will be based on whatever National Highways accept for M62 closures. It won't be 36 weeks of solid disruption, it will screw up any TRU access plans if it is. They won't stand for that, neither will Northern.
It’s also confirmed in the planning application letter that NR were paid a lump sum to take over future maintenance responsibility: “Whilst the original agreement included split maintenance of the structure, Network Rail took a commuted sum in the 1970's for future maintenance, and therefore responsibility for the structure sits entirely with Network Rail…”As I understand it, underline bridges for road schemes are built in a separate contract from the road, with the railway, or people acting for the railway, as designer, employer of the contractor, and supervisor of the contract, even though the contractor is often the same as for the road, and even though construction is paid for by the road scheme. So I would have thought it's all the railway's responsibility.
Also I would have thought 50 years plus is far too long for legal arguments about liability for original defects.
How was Network Rail, founded in 2004, able to take a commuted sum in the 1970s? One imagine British Rail would not have been overly keen to take on extra maintenance at that particular moment in time, so I wonder why they did so?It’s also confirmed in the planning application letter that NR were paid a lump sum to take over future maintenance responsibility: “Whilst the original agreement included split maintenance of the structure, Network Rail took a commuted sum in the 1970's for future maintenance, and therefore responsibility for the structure sits entirely with Network Rail…”
From the track diagrams I can see, there's no way to reverse at Castleton without modified working and given the proximity to the bridge I think it's exceptionally unlikely they would do it.During the rebuild, would trains from Rochdale be allowed to serve Castleton or would everything just stop at Rochdale?
Mills Hill can't be served for the same reason, Moston could in theory be served with an empty shunt via Vitriol Works but at that point the cost of providing such a service goes through the roof for the number of people who might benefit.Similar question for Mills Hill and Moston (RRB from Victoria?) too.
The Vitriol Works crossover was taken out a few years back now.Mills Hill can't be served for the same reason, Moston could in theory be served with an empty shunt via Vitriol Works
Fair enough, I was going off OTT.The Vitriol Works crossover was taken out a few years back now.
Oh I just assumed it would be a BR decision passed on to RT then NR. Probably a bit of a side issue though, I just copied what it said in the letter without considering the changes to the organisation over so many years.How was Network Rail, founded in 2004, able to take a commuted sum in the 1970s? One imagine British Rail would not have been overly keen to take on extra maintenance at that particular moment in time, so I wonder why they did so?
Potentially yes, as there is a main to main crossover opposite Castleton East Box.During the rebuild, would trains from Rochdale be allowed to serve Castleton or would everything just stop at Rochdale? Similar question for Mills Hill and Moston (RRB from Victoria?) too.
Potentially yes, as there is a main to main crossover opposite Castleton East Box.
Bridge gets rebuilt at the end of Summer. 9 day blockade.I was on the M62 the other day driving under it and I thought it seemed to have cracks in it. I have now noticed there is a 20mph speed restriction over it.
Is there a noted issue and any plan for remediation? The route is important during the TPE upgrade process, so I'd have hoped it will get attended to quickly.
Interesting, thanks. I'd better get the dates checked, make sure I don't book any flights from Manchester at that time (admittedly unlikely if in the school holidays, which I assume it will be).Bridge gets rebuilt at the end of Summer. 9 day blockade.
Actually, double checking, its a 17 day block. 6th September to 24th September.Interesting, thanks. I'd better get the dates checked, make sure I don't book any flights from Manchester at that time (admittedly unlikely if in the school holidays, which I assume it will be).
Very much appreciated - that could well be an issue we would have to factor in.Actually, double checking, its a 17 day block. 6th September to 24th September.
Likely the payment represented many, many years of BR's then spend on the structure, so they viewed the sum as effectively free "borrowing" from the then highway authority. The cost of which funding is now being paid back, with inflation if course...Oh I just assumed it would be a BR decision passed on to RT then NR. Probably a bit of a side issue though, I just copied what it said in the letter without considering the changes to the organisation over so many years.