• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Hope Valley Capacity Scheme updates

Status
Not open for further replies.

Mag_seven

Forum Staff
Staff Member
Global Moderator
Joined
1 Sep 2014
Messages
10,953
Location
here to eternity
Just a reminder that this is an infrastructure section discussion to discuss Hope Valley Capacity Scheme Updates.

If anyone wants to discuss other things such as timetabling then they are welcome to start a new thread in the appropriate forum section.

thanks
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Jozhua

Established Member
Joined
6 Jan 2019
Messages
1,890
Some photos coming up to Sheffield yesterday.

First is of the Liverpool service heading in the opposite direction - obviously a little while to go yet before the other platform is in place!

Second is of some of the dual track going in.

Third is some of the new cable conduit under construction.
 

Attachments

  • PXL_20220729_173513882.jpg
    PXL_20220729_173513882.jpg
    2.4 MB · Views: 163
  • PXL_20220729_173553403.jpg
    PXL_20220729_173553403.jpg
    3.4 MB · Views: 160
  • PXL_20220729_173655948.jpg
    PXL_20220729_173655948.jpg
    2.8 MB · Views: 161

LowLevel

Established Member
Joined
26 Oct 2013
Messages
8,256
Screenshot_20220730-142445_Chrome.jpg

Glad to see TPE's diversion contingency plans are working well. 8 hour gap at Sheffield today and the signallers at York ROC presumably unimpressed at having one of their more useful platforms blocked all day long by an abandoned train. Photo shows an Open Train Times Map screen shot of Sheffield Station with "THNX TPE*" entered into the berth train describer for platform 2.
 

Killingworth

Established Member
Joined
30 May 2018
Messages
5,776
Location
Sheffield
View attachment 118415

Glad to see TPE's diversion contingency plans are working well. 8 hour gap at Sheffield today and the signallers at York ROC presumably unimpressed at having one of their more useful platforms blocked all day long by an abandoned train. Photo shows an Open Train Times Map screen shot of Sheffield Station with "THNX TPE*" entered into the berth train describer for platform 2.

The substitute services provided by the 3 TOCs to cover these blockades have been less than satisfactory. The industry seems to have expected each to make their own arrangements and passengers to get by with whatever works out on the day. TPEs diverted services could almost be matched for time by a direct coach between Sheffield and Hope and a half hourly shuttle from there to Manchester, alternating via Stockport and Marple. A minibus for the smaller stations would cope with traffic around Grindleford better. But I'm off on a digression. When time allows I could write more for a separate thread, but tomorrow is the last day for the current round of blockades.
 

LittleAH

Member
Joined
24 Oct 2018
Messages
1,159
The substitute services provided by the 3 TOCs to cover these blockades have been less than satisfactory. The industry seems to have expected each to make their own arrangements and passengers to get by with whatever works out on the day. TPEs diverted services could almost be matched for time by a direct coach between Sheffield and Hope and a half hourly shuttle from there to Manchester, alternating via Stockport and Marple. A minibus for the smaller stations would cope with traffic around Grindleford better. But I'm off on a digression. When time allows I could write more for a separate thread, but tomorrow is the last day for the current round of blockades.
All of which isn't true. As I will be commenting on such a thread once it begins.
 

dosxuk

Established Member
Joined
2 Jan 2011
Messages
2,111
The substitute services provided by the 3 TOCs to cover these blockades have been less than satisfactory. The industry seems to have expected each to make their own arrangements and passengers to get by with whatever works out on the day.

No different to their normal behaviour on this route - all three are well known for short notice cancellations and telling passengers to use alternative operators - and not looking at whether the alternatives are actually operating. The whole Manchester-Sheffield link seems to be so far down the list of priorities at all three operators that none of them can be relied on, even on a good day.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,459
The trough route looks more like new Cess walkway.
That's how it was explained to me, see bottom right hand corner.View attachment 118402
The cable trough and walkway route from Dore Station to Dore Station Jn hasn't even been designed yet, as it is awaiting NR input. Whatever is in the photograph is either temporary or to be moved elsewhere. There is other miscellaneous timber on the track panel in the tenfoot and just before the crossover.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
6,034
The cable trough and walkway route from Dore Station to Dore Station Jn hasn't even been designed yet, as it is awaiting NR input. Whatever is in the photograph is either temporary or to be moved elsewhere. There is other miscellaneous timber on the track panel in the tenfoot and just before the crossover.
perhaps they are just getting it done in the usual/obvious way and hoping (whatever design emerges eventually) any differences won't be noticed?
 

Killingworth

Established Member
Joined
30 May 2018
Messages
5,776
Location
Sheffield
Unfortunately today's strike has impacted on this weekend's work. Stressing of the newly laid tracks has been proceeding however installation of the new turnout for the extended Dore South curve/loop has had to be postponed.
 

Nicholas Lewis

On Moderation
Joined
9 Aug 2019
Messages
7,323
Location
Surrey
Unfortunately today's strike has impacted on this weekend's work. Stressing of the newly laid tracks has been proceeding however installation of the new turnout for the extended Dore South curve/loop has had to be postponed.
More disruption for passengers no doubt to recover the works
 

IanXC

Emeritus Moderator
Joined
18 Dec 2009
Messages
6,509
Unfortunately today's strike has impacted on this weekend's work. Stressing of the newly laid tracks has been proceeding however installation of the new turnout for the extended Dore South curve/loop has had to be postponed.

Todays ASLEF strike?
 

ricoblade

Member
Joined
28 Sep 2015
Messages
465
What does this all mean for "normal" services please? Is it a combination of TPE (shudder) and EMR? I'm looking to travel to Dore on a weekday in August and don't want to deal with cancellations, etc.
 

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
73,679
Location
Yorkshire
Can we stick to infrastructure developments in this thread please?

Service provision can be discussed in another thread (either an existing one, if there is one, or by creating a new thread if there isn't).

Many thanks :)
 

Jozhua

Established Member
Joined
6 Jan 2019
Messages
1,890
I stand corrected on the cable trough!

Bad if Network Rail hasn't agreed on a final design yet - apparently that's a major issue with them not finalising designs properly and leaving contractors to guess, or have to redesign/rebuild things.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,733
Location
Between Beeston (Notts) & Bedlington
From Edgeley Junction to Hazel Grove:
Down linespeed increase to 60mph (from 40)
Up linespeed increase to 55mph (from 35)
Resignalling throughout (boxes remain, not a ROC transfer). Of significance is a new platform signal at Woodsmoor P2.
OLE modifications over whole route
Track renewal through Woodsmoor station P2.
Reballasting from Hazel Grove Station area to the sidings. Full track renewal of the mainlines adjacent to the sidings and towards Woodsmoor.
New track drainage throughout Hazel Grove area.
Most likely no construction will be happening until next year as the June NR strike meant the start of the Hazel Grove work was deferred.
Do you know what the scope of the "OLE modifications" involves? My bets would probably rest with modifications to cater for the new platform signal at Woodsmoor and re-registration through Woodsmoor, Davenport & Hazel Grove to make the OLE mechanically independent.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,459
Do you know what the scope of the "OLE modifications" involves? My bets would probably rest with modifications to cater for the new platform signal at Woodsmoor and re-registration through Woodsmoor, Davenport & Hazel Grove to make the OLE mechanically independent.
The existing MkIIIc OLE (expectedly) contains many non-compliances and as such any modifications will be the bare minimum to provide compatibility with the line speed increases and new track alignments at Hazel Grove and Woodsmoor. Mainly limited to height and stagger adjustments/re-registration across the route.
There is a wire height issue at Woodsmoor LC where the OLE is significantly too low (4.9m, minimum should be 5.6m) due to Moorland Rd overbridge 200m away, which will be addressed if it can be done so cheaply.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,733
Location
Between Beeston (Notts) & Bedlington
The existing MkIIIc OLE (expectedly) contains many non-compliances and as such any modifications will be the bare minimum to provide compatibility with the line speed increases and new track alignments at Hazel Grove and Woodsmoor. Mainly limited to height and stagger adjustments/re-registration across the route.
There is a wire height issue at Woodsmoor LC where the OLE is significantly too low (4.9m, minimum should be 5.6m) due to Moorland Rd overbridge 200m away, which will be addressed if it can be done so cheaply.
Ah, I see. Hopefully it can be addressed!
 

londonmidland

Established Member
Joined
22 Dec 2009
Messages
2,095
Location
Leicester
If this doesn’t scream congestion then I don’t know what does!

6F78 freight was waiting for a northbound XC, which was running late. It then cleared the section which allowed it to take the curve, however 1B80 TransPennine Cleethorpes service was stuck behind it, which had to wait for 6M86 freight to pass before it could continue.

The 15:11 TPE Cleethorpes left Sheffield 28 minutes late as a result.531D1346-5AE8-482D-87E2-32162A9BD9E2.jpeg
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,396
The fact that the 1B80 was only behind 6F78 due to being 11 late off Piccadilly due to waiting driver dilutes it a little. 6F78 only picked up 5/6 minutes.
 

Killingworth

Established Member
Joined
30 May 2018
Messages
5,776
Location
Sheffield
If this doesn’t scream congestion then I don’t know what does!

6F78 freight was waiting for a northbound XC, which was running late. It then cleared the section which allowed it to take the curve, however 1B80 TransPennine Cleethorpes service was stuck behind it, which had to wait for 6M86 freight to pass before it could continue.

The 15:11 TPE Cleethorpes left Sheffield 28 minutes late as a result.View attachment 119253
Situation fairly typical hereabouts! Come 2023, or maybe 2024, that will be eased when the extended Dore chord will be able to hold a freight service.

However 6F78 was only 5 minutes late across Dore West Junction. 1B80 should have preceded the freight but had started 11 minutes late from Piccadilly. It then had to wait for 6M87 to clear the single track through Dore station in the opposite direction - something that shouldn't be a problem from 2023/24 either.

This is a critical time of day which explains why there's no 15.14 Northern stopper out of Sheffield, it being delayed until 15.46.
 

Mugby

Established Member
Joined
25 Nov 2012
Messages
2,031
Location
Derby
Is there any progress to report on theworks
I passed through this evening on a Manchester-Sheffield service and not much seems to be happening at the present time. Some work has been done on the new Loop at Hathersage and lots of materials are piled up ready for it to continue.
Work on the extended Dore Chord seem to be minimal as yet but I imagine a pretty substantial retaining wall will need to be put in place to protect the properties above before any more of the bank can be dug out.
 
Status
Not open for further replies.

Top