SeeOh that's good to hear, any idea what the new linespeed will be? It always seems painfully slow between Hazel Grove and Davenport!
See
Hope Valley Capacity Scheme updates
Also no Southbound trains will serve Chesterfield in any July weekend. Interesting - presuming they will be routed via "Platform 4".www.railforums.co.uk
Further developments on the Hope Valley Railway Upgrade are in place, as we undertake essential improvements to the line between Manchester and Sheffield.
Recent line closures have seen major work completed, with key milestones hit by the project team.
The lift shafts for the newly built accessible footbridge have now been constructed at Dore & Totley station, whilst a bridge has been extended in Bamford to facilitate the new passing loop between Bamford and Hathersage stations as the installation nears completion.
In theory scheduled trains should start using the new tracks and platform from Monday 25th March. The Bamford loop should be ready well before then. The Dore loop should be ready by the end of February and Dore station's new Platform 1 about then too.
Weather will be the critical factor. We can get a lot of ice and snow in the Peak District and the Hope Valley line was closed for about a week as recently as 2010.
They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.Rail minister saying this is part of the network north plan is embarrassing.
At least TRU may be getting some funding from that pot of money.
Are there any plans in the near future to improve the signalling?They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.
Northwest don't seem as bothered as Northeast when it comes to resignalling.Are there any plans in the near future to improve the signalling?
Vague intentions yes, anything firm with a pathway to funding, highly doubt it. (E.g. presumably at some point there's a plan Manchester ROC will take over the line, but exactly when and with what money nobody has yet said).Are there any plans in the near future to improve the signalling?
What tunnel controls are being implemented at Totley?They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.
Track tamping is scheduled again at Hazel Grove for the very early hours of Sunday.
Edgeley all the way to Dore has SP to MU conversion (i.e. new speed boards throughout where required).Do the alterations continue onwards towards New Mills South Jn
Will the new loop here be used by freight trains leaving hope valley line or do they join the existing chord?Work continues on the extended Dore chord/loop. It was understood that it would have been completed with soil nailing over the summer and restorative planting begun in October. Now needing to be completed with green painted retention wall by early March for line reopening on 24th. Fine weather will be very welcome. Recent rain, frost and snow can't have been helpful.
View attachment 148762View attachment 148763
Why can’t 6L45 be given the road once the train in front has passed S46 and give the freight 2 yellows so it can begin climbing the bank?Well, training has begun for the Signallers regards the new Sheffield Outer Workstation. As you can see, we won't be able to give a freight at Dore South a proceed until the train in front has got to Dronfield Station. So Greens only from S48. Makes it almost impossible to find a decent gap in times of disruption for the late 1900 ton freight, for example. As it is now, at least we can move a train from Dore South as soon as the train in front leaves Bradway Tunnel....
Well, training has begun for the Signallers regards the new Sheffield Outer Workstation. As you can see, we won't be able to give a freight at Dore South a proceed until the train in front has got to Dronfield Station. So Greens only from S48. Makes it almost impossible to find a decent gap in times of disruption for the late 1900 ton freight, for example. As it is now, at least we can move a train from Dore South as soon as the train in front leaves Bradway Tunnel.....View attachment 148798View attachment 148799
I'm assuming S48 is a 3-aspect so that would be a green as mentioned above.Why can’t 6L45 be given the road once the train in front has passed S46 and give the freight 2 yellows so it can begin climbing the bank?
It seems very unlikely unless the previous train unexpectedly has problems and runs very slowly or stops completely before clearing the overlap of S46.Present practice sounds far more practical. I used to be able to hear the freights slowly starting away from a stand and there's no way they'd catch any southbound rolling train on the MML. In recent years they've seemed quieter. Of course a light engine movement possibly could.
Somewhat old news. There's currently no specific bottleneck at Bamford.Network Rail reporting that track for loop between Bamford and Hathersage is now complete. Will come into use in Sring 2024 when signalling is done
Final track installed to remove Hope Valley bottleneck
The final pieces of rail track have been installed to help relieve a long-standing bottleneck on the Hope Valley railway line, providing faster and more reliable rail journeys for passengers.www.networkrailmediacentre.co.uk
It's looking very, very optimistic to get the Dore Curve completed on time...Somewhat old news. There's currently no specific bottleneck at Bamford.
There certainly is a bottleneck on the current short chord between the Hope Valley and Midland Mainlines.There is also a more visible and obvious bottleneck on the single track through Dore station on the line between Sheffield and Manchester. (Manchester is apparently the most sought destination from Sheffield.)
The Dore loop is very much not complete, see Post 1525 above, and the critical work on new Platform 1 at Dore, see Post 1521, still has a long way to go in only 3 months.
It's looking very, very optimistic to get the Dore Curve completed on time...
No mention of the Dore loop.The Hope Valley Railway Upgrade will remove several bottlenecks between Manchester and Sheffield to allow passenger trains to overtake slower freight trains along the line.
The main improvements include:
- A new platform and accessible footbridge with lifts at Dore & Totley station
- A railway loop between Bamford and Hathersage
- A new overbridge at Hathersage West, replacing the current foot crossing to improve safety
- Signalling improvements along the line to improve reliability
- Platform extensions to allow for more carriages on services