• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Hope Valley Capacity Scheme updates

Mugby

Established Member
Joined
25 Nov 2012
Messages
1,931
Location
Derby
Tamping is planned tonight and tomorrow at Woodsmoor and Hazel Grove respectively relating to resignalling & line speed increase through these areas.
Oh that's good to hear, any idea what the new linespeed will be? It always seems painfully slow between Hazel Grove and Davenport!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
See

Current Platform 1, that has existed for over 150, years gets downgraded to Platform 2 because Manchester is considered the priority destination - both by Nerwork Rail for signalling reasons, and by passengers because the service going west is better than going the short distance into Sheffield! Reinstatement of Platforms 3 and 4 is not anticipated, although the new Platform 1 is supposedly future proofed to permit that.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,755
Location
Leeds
Press release with video


Further developments on the Hope Valley Railway Upgrade are in place, as we undertake essential improvements to the line between Manchester and Sheffield.

Recent line closures have seen major work completed, with key milestones hit by the project team.

The lift shafts for the newly built accessible footbridge have now been constructed at Dore & Totley station, whilst a bridge has been extended in Bamford to facilitate the new passing loop between Bamford and Hathersage stations as the installation nears completion.
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
In theory scheduled trains should start using the new tracks and platform from Monday 25th March. The Bamford loop should be ready well before then. The Dore loop should be ready by the end of February and Dore station's new Platform 1 about then too.

Weather will be the critical factor. We can get a lot of ice and snow in the Peak District and the Hope Valley line was closed for about a week as recently as 2010.
 

Jamesrob637

Established Member
Joined
12 Aug 2016
Messages
5,255
In theory scheduled trains should start using the new tracks and platform from Monday 25th March. The Bamford loop should be ready well before then. The Dore loop should be ready by the end of February and Dore station's new Platform 1 about then too.

Weather will be the critical factor. We can get a lot of ice and snow in the Peak District and the Hope Valley line was closed for about a week as recently as 2010.

Will there be any new tracks or platforms in use next week at the TT change?
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
Will there be any new tracks or platforms in use next week at the TT change?
No, it won't be operational until after a long blockade from the evening of Saturday 16th March until early on Monday 25th - just in time to test it all the week before Easter. A lot to do yet, see yesterday.

IMG_20231206_112317.jpg
 

Jozhua

Established Member
Joined
6 Jan 2019
Messages
1,859
Rail minister saying this is part of the network north plan is embarrassing.

At least TRU may be getting some funding from that pot of money.
 

GardenRail

Member
Joined
26 Mar 2023
Messages
330
Location
Yorkshire
Rail minister saying this is part of the network north plan is embarrassing.

At least TRU may be getting some funding from that pot of money.
They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.
 

Legolash2o

Member
Joined
27 Sep 2018
Messages
602
They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.
Are there any plans in the near future to improve the signalling?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
13,440
Location
Bristol
Are there any plans in the near future to improve the signalling?
Vague intentions yes, anything firm with a pathway to funding, highly doubt it. (E.g. presumably at some point there's a plan Manchester ROC will take over the line, but exactly when and with what money nobody has yet said).
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
It's been somewhat unfavourable weather recently for construction work with very heavy rain, snow, frost and very high winds on almost every gloomy day. Construction of the extended Dore loop/chord was supposed to have been completed over the summer months. Today's picture suggests it's going to be quite a few more weeks yet, now suggested to be by the end of February. Rails are delivered ready for the loop once the track bed is ready.

At Dore & Totley station work continues although locally announced dates for controversial demolition of the now unlit 1985 shelter have once again passed and it remains for a few more days/weeks? Brick facing of the lift towers has slowed down. That is necessary before the span and steps can be installed.

Operationally local users of the Manchester bound trains were heartened to hear of EMR's December introduction of 6 car 170's on their previously 2 car 158 1R52 7.36 from Dore as an alternative to TPE's recently unreliable 1B65 and 1B67. Yesterday and today's both TPE trains have been 6 car. On Monday EMR did provide 6 but it was 40 minutes late at Dore, delaying the following TPE and Northern services! Teething problems we hope. Today it was only a single 3 car 170.

20231212_153623.jpg 20231212_153008.jpg
 

louis97

Established Member
Joined
14 May 2008
Messages
1,906
Location
Derby
They don't tell everyone that it's still going to be Absolute Block Signalling from Earles Westward. So we'll still have trains waiting for a clear section, only at Earles rather than Totley as it is now. Then again, with the new tunnel controls in Totley and Bradway, they might. Get rid of one problem and create two more. South Bound trains won't be able to leave the South Chord on anything less than a green. We can move them on Yellows at the moment.
What tunnel controls are being implemented at Totley?
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,304
Tamping is planned tonight and tomorrow at Woodsmoor and Hazel Grove respectively relating to resignalling & line speed increase through these areas.
Track tamping is scheduled again at Hazel Grove for the very early hours of Sunday.

Access site

Egress site
 

pharrc20

Member
Joined
29 Jul 2022
Messages
36
Location
Northwich
Does anyone know of a diagram to show what signalling alterations are taking plave between Edgeley No. 1 and Hazel Grove please? Do the alterations continue onwards towards New Mills South Jn.?
Thanks Paul
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
Work continues on the extended Dore chord/loop. It was understood that it would have been completed with soil nailing over the summer and restorative planting begun in October. Now needing to be completed with green painted retention wall by early March for line reopening on 24th. Fine weather will be very welcome. Recent rain, frost and snow can't have been helpful.

20231218_103530.jpg20231218_103511.jpg
 
Last edited:

td97

Established Member
Joined
26 Jul 2017
Messages
1,304
Do the alterations continue onwards towards New Mills South Jn
Edgeley all the way to Dore has SP to MU conversion (i.e. new speed boards throughout where required).
 
Last edited:

cuemaster

Member
Joined
26 Feb 2023
Messages
62
Location
London
Work continues on the extended Dore chord/loop. It was understood that it would have been completed with soil nailing over the summer and restorative planting begun in October. Now needing to be completed with green painted retention wall by early March for line reopening on 24th. Fine weather will be very welcome. Recent rain, frost and snow can't have been helpful.

View attachment 148762View attachment 148763
Will the new loop here be used by freight trains leaving hope valley line or do they join the existing chord?
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
It will be an extention of the existing chord. This morning a southbound freight for the MML could have pulled in there instead of delaying an eastbound TPE service due to leave Dore at 8.04 until 8.18, the following Northern from 8.22 to 8.26 and westbound TPE at 8.15 to 8.22. Knock on delays from them across the north.
 

GardenRail

Member
Joined
26 Mar 2023
Messages
330
Location
Yorkshire
Well, training has begun for the Signallers regards the new Sheffield Outer Workstation. As you can see, we won't be able to give a freight at Dore South a proceed until the train in front has got to Dronfield Station. So Greens only from S48. Makes it almost impossible to find a decent gap in times of disruption for the late 1900 ton freight, for example. As it is now, at least we can move a train from Dore South as soon as the train in front leaves Bradway Tunnel.....PXL_20231219_111442591.jpgPXL_20231219_111446234.jpg
 

8stewartt

Member
Joined
18 Mar 2013
Messages
75
Well, training has begun for the Signallers regards the new Sheffield Outer Workstation. As you can see, we won't be able to give a freight at Dore South a proceed until the train in front has got to Dronfield Station. So Greens only from S48. Makes it almost impossible to find a decent gap in times of disruption for the late 1900 ton freight, for example. As it is now, at least we can move a train from Dore South as soon as the train in front leaves Bradway Tunnel....
Why can’t 6L45 be given the road once the train in front has passed S46 and give the freight 2 yellows so it can begin climbing the bank?
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
Well, training has begun for the Signallers regards the new Sheffield Outer Workstation. As you can see, we won't be able to give a freight at Dore South a proceed until the train in front has got to Dronfield Station. So Greens only from S48. Makes it almost impossible to find a decent gap in times of disruption for the late 1900 ton freight, for example. As it is now, at least we can move a train from Dore South as soon as the train in front leaves Bradway Tunnel.....View attachment 148798View attachment 148799

Present practice sounds far more practical. I used to be able to hear the freights slowly starting away from a stand and there's no way they'd catch any southbound rolling train on the MML. In recent years they've seemed quieter. Of course a light engine movement possibly could.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,950
Location
Nottingham
Why can’t 6L45 be given the road once the train in front has passed S46 and give the freight 2 yellows so it can begin climbing the bank?
I'm assuming S48 is a 3-aspect so that would be a green as mentioned above.

Present practice sounds far more practical. I used to be able to hear the freights slowly starting away from a stand and there's no way they'd catch any southbound rolling train on the MML. In recent years they've seemed quieter. Of course a light engine movement possibly could.
It seems very unlikely unless the previous train unexpectedly has problems and runs very slowly or stops completely before clearing the overlap of S46.
 

ayubdaud

Member
Joined
11 Mar 2020
Messages
24
Location
Bolton
Blimey, that would probably be the first time 1B66 running to time following 6L45 if so.

Interestingly, the TPRs at Dore South Jn reference the first movement as Up depart Dronfield and then second movement depart from Dore West Jn. Slightly more generous than the potential reality?

1703187703439.png
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
6,317
Location
West Wiltshire
Network Rail reporting that track for loop between Bamford and Hathersage is now complete. Will come into use in Sring 2024 when signalling is done

 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
Network Rail reporting that track for loop between Bamford and Hathersage is now complete. Will come into use in Sring 2024 when signalling is done

Somewhat old news. There's currently no specific bottleneck at Bamford.

There certainly is a bottleneck on the current short chord between the Hope Valley and Midland Mainlines.There is also a more visible and obvious bottleneck on the single track through Dore station on the line between Sheffield and Manchester. (Manchester is apparently the most sought destination from Sheffield.)

The Dore loop is very much not complete, see Post 1525 above, and the critical work on new Platform 1 at Dore, see Post 1521, still has a long way to go in only 3 months.
 

GardenRail

Member
Joined
26 Mar 2023
Messages
330
Location
Yorkshire
Somewhat old news. There's currently no specific bottleneck at Bamford.

There certainly is a bottleneck on the current short chord between the Hope Valley and Midland Mainlines.There is also a more visible and obvious bottleneck on the single track through Dore station on the line between Sheffield and Manchester. (Manchester is apparently the most sought destination from Sheffield.)

The Dore loop is very much not complete, see Post 1525 above, and the critical work on new Platform 1 at Dore, see Post 1521, still has a long way to go in only 3 months.
It's looking very, very optimistic to get the Dore Curve completed on time...
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,912
Location
Sheffield
It's looking very, very optimistic to get the Dore Curve completed on time...

Blockades are scheduled over Xmas and the New Year so I'll update again with pictures in about 10 -14 days time. In fairness it isn't a very long section once they can get down to it, but proximity to running trains and housing makes it sensitive. Residents in the West View Lane flats complex are most unhappy.

Earlier in this process much was made of completing civils in summer and the Dore loop was supposed to be finished about August with green replanting from October. The recent weather has proved why the summer time window was originally planned. It has been very wet recently, and now windy as well.

Looking at the press release it says;

The Hope Valley Railway Upgrade will remove several bottlenecks between Manchester and Sheffield to allow passenger trains to overtake slower freight trains along the line.

The main improvements include:

  • A new platform and accessible footbridge with lifts at Dore & Totley station
  • A railway loop between Bamford and Hathersage
  • A new overbridge at Hathersage West, replacing the current foot crossing to improve safety
  • Signalling improvements along the line to improve reliability
  • Platform extensions to allow for more carriages on services
No mention of the Dore loop.

Nor any mention that the footbridge installed at Hathersage West in January is still not open and awaits painting of one part of the structure that was delivered without its final layer of green paint. It's got impressive scaffolding and sheeting around it but it seems it can't be painted until warmer weather. Safety of the crossing has improved greatly. It has now been closed for over a year, yet trains are still expected to whistle.

20231217_150843.jpg
 
Last edited:

Top