Looks as if all but 1 or 2 of the foundations are now complete in the Desborough area. They've opted for concrete foundations on the DM side between the Co-Op & bridge SPC3-39 (B576 Harborough Rd). I counted 4 on the DM side in total that were curing, and 1 more by bridge 39 that's still a Work In Progress.

This is the WIP one - based on the chalk on the DM cess side rail, I think this will be SPC3/125.918/DM (+UM on the other side). I don't know for certain if this will be an SSA-style mast combining a cantilever with an ATF anchor, but I'd say that's likely. If it does, I think both the DM & UM ATFs will be anchored together, as that is the situation on the Derby side of the bridge.

These are the four "curing" foundations in place on the DM side. One north of the Co-Op car park, beside the Old Station House, one by the access steps from Gladstone Street, and two north of there - this last pair will be for the RHS MPA Portal mentioned further upthread.
Additionally, some more info on road closures for bridge works has popped up on one.network.
SPC3-7 (Wigston Rd, Newton H): 31/07/23 to 16/02/24.
Footpath "C34" linking SPC3-8 (The Square) & SPC3-9 (Wistow Rd) (both Newton H): 30/05/23 to 22/12/23.
SPC3-9 (Wistow Rd, Newton H): 30/05/23 to 22/12/23.
SPC3-10 (Glen Station Rd): 13/01/23 to 26/05/23. A month until reopening!
Footpath "B1" over SPC3-18 (Grammar School Bridge, Kibworth): 05/06/23 to 08/12/23.
Roadworks (not closure) on W Langton Rd for access to SPC3-24 & SPC3-25: 15/05/23 to 04/08/23.
Footpath "A47" over SPC3-28 (Chaters Bridge, Gt Bowden): 04/05/23 to 22/09/23.
Footpath "A49" over SPC3-28E (Gt Bowden Footbridge): 10/07/23 to 10/09/23.
Also of note are next month's engineering dates on EMR.
08/05 to 12/05: work taking place between Wellingborough & Kettering, adding time to late night/early morning journeys. Maybe something to do with Harrowden TSC?
15/05 to 19/05: work taking place between Harpenden & Bedford, causing 2335 STP-NOT & 2354 STP-COR to run Slows only. Can't help but wonder if that's to do with East Hyde or any of the other substations installed south of Bedford...
21/05: Another total line block via Market Harborough. Not sure what for...
23/05 to 26/05: 0432 COR-STP unable to stop at Bedford due to engineering works. Not sure why...