Class 170101
Established Member
- Joined
- 1 Mar 2014
- Messages
- 8,393
No Platform on the Down Fast I seem to recall?
No Fast line platforms at all. If Universal goes ahead and signs up to enhance the station then a lot will have to change!No Platform on the Down Fast I seem to recall?
2.1 The current position with regard to the project’s finances shows a combined actual and committed expenditure of £16M to the end of December 2024. This figure is still just below the total of secured s106 contributions of £18.7M.
2.2 As well as works on site to install further electrification masts and piles, key activities planned to take place in January 2025 include the ordering of overhead line booms, and the return and evaluation of tenders for a package of civil engineering ‘enabling’ works to commence in the Spring.
2.3 In the three-month period January to March 2025, it is currently anticipated that NR will undertake work that will commit expenditure of a further c. £5M.
The front gantry in the second picture is also from the OLEMI & UKMS design ranges.OLE booms were installed last weekend, and during this weekend's fast line possession work is underway to attach the stovepipes (see first attached picture).
In the second picture there are two gantries next to each other. The gantry behind is one of 11 (essentially) identical portals whereas the gantry in front is unique to the worksite; is the latter also an OLE portal, or something else? (Mast to the very left of picture is for an existing headspan.)
Track layout remains unchanged at present.
I believe that is its purpose, assuming it is where the north end of the platforms will be. The Down signals are being moved so the one on the Down Slow is a platform starter, and the one on the Down Fast will be adjacent as there would otherwise be a risk of drivers reading the wrong one.Recently, though, those portals have seen a little bit of a renaissance, but as signal gantries (notably on the WCML from Crewe northwards). As a result, I think the same principle is being applied here.
Reserved matters were approved early Feb, it turns out; I thought it would be subject to Planning Committee scrutiny. How far the modest build will progress (if it starts) before the likely Universal greenlight is another matter.Detailed design of the station is complete and another reserved matters application (24/01889/MAR) has been submitted with proposed changes to the approved station building and car park, listed in section 3.6 of the design & access statement (V19 on the documents page). The current target date for a decision is 19 December.