Slowing to a crawl when approaching Crewe station (northbound)

Status
Not open for further replies.

All Line Rover

Established Member
Joined
17 Feb 2011
Messages
5,221
Why, in this video, around the 37 minute mark, does the locomotive slow to a crawl a short distance south of Crewe station, only to speed up again quite considerably, and then slow down again when arriving at the station? And why, 15 years later, does this continue to happen? The majority of VTWC trains that run on time, or early, as far as Basford, slow down and arrive into Crewe a minute or two late.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,845
As Cherry Picker says, he gets restrictive aspects back at Basford Hall as it is approach control into Platform 6. You can see the feather on the approach signal.
 

Senex

Established Member
Joined
1 Apr 2014
Messages
2,752
Location
York
There are a number of regular movements in the Crewe station area that were actually made significantly slower by the 1980s works, and down fast to the principal down platform (now 6) is one of them. The turnout is 50, so the iron on the ground would allow a fast run in, but the signalling involves severe approach control out at Basford Wood. IIRC this is because the turnout down fast to up fast at 60 has flashing yellows, so the turnout to platform 6 at 50 can't. (I can't recall hearing of any modification since.)
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,556
Location
Mold, Clwyd
I'm pretty sure it applies southbound into the station too, from all directions.
On the Warrington line you always find yourself crawling along on the far outskirts of Crewe, only to eventually speed up into P5.
I think the through lines (mostly Glasgows now) can get a clear run, but not sure, haven't done it very often.
The way the Down Slow merges with the Up Slow at Crewe South is also restrictive. There is no clear run into P11, say.
Never mind, all going to be sorted for HS2... ;)
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,845
No need to wink, something will get done at Crewe regardless as it is approaching life expired.
 

Senex

Established Member
Joined
1 Apr 2014
Messages
2,752
Location
York
No need to wink, something will get done at Crewe regardless as it is approaching life expired.
Dare one hope that someone will dust off the early plans for the 1980s work (before it was descoped) and deliver the better and faster connections to the Manchester line that were originally conceived (before they settled for a layout that for Manchester is very much worse than the previous one)?
 

Oxfordblues

Member
Joined
22 Dec 2013
Messages
651
It wouldn't be a problem if the schedules accounted for it, but most Euston-Birmingham-Scotland trains lose a couple of minutes arriving at Platform 11 and the advertised xx09 departure times are hardly ever achieved.

Similarly southbound from Preston trains get only 4 mins to passing Euxton Jn but with the mandatory moving brake test this is always extended to at least 5 mins and departures from Wigan NW are always late.

Both represent an unfortunate lack of attention to detail by the timers.
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,061
It wouldn't be a problem if the schedules accounted for it, but most Euston-Birmingham-Scotland trains lose a couple of minutes arriving at Platform 11 and the advertised xx09 departure times are hardly ever achieved.

This also regularly delays the xx08 ATW South Wales service from Platform 6. The Virgin is due to arrive first but is almost invariably late,and in common with most signal boxes in the Northwest ,if Virgin runs late, everything else stops to keep out of the way <D
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,845
Similarly southbound from Preston trains get only 4 mins to passing Euxton Jn but with the mandatory moving brake test this is always extended to at least 5 mins and departures from Wigan NW are always late.

Both represent an unfortunate lack of attention to detail by the timers.

Virgin could always bid for it.....
 

kieron

Established Member
Joined
22 Mar 2012
Messages
3,048
Location
Connah's Quay
If attention to detail is something Virgin would have to bid for separately, I imagine it could be quite expensive. ;)
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,075
This also regularly delays the xx08 ATW South Wales service from Platform 6. The Virgin is due to arrive first but is almost invariably late,and in common with most signal boxes in the Northwest ,if Virgin runs late, everything else stops to keep out of the way <D

You are right, the northbound "class 9"(!) Virgin is invariably late at Crewe, and it also affects the following Euston - Manchester off platform 5 too. It is usually down to a Bham N St to Wolves local, which delays the EUS - BHM - CRE - Scotland train, which in turn knocks the Manchester at Stafford.
I have given up on catching the Crewe to Manchester Pendolinos because I keep missing the start of things, now get the local before!
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,061
You are right, the northbound "class 9"(!) Virgin is invariably late at Crewe, and it also affects the following Euston - Manchester off platform 5 too. It is usually down to a Bham N St to Wolves local, which delays the EUS - BHM - CRE - Scotland train, which in turn knocks the Manchester at Stafford.
I have given up on catching the Crewe to Manchester Pendolinos because I keep missing the start of things, now get the local before!

Indeed - I'd be very interested to see what the reliability of the Manchester via Crewe's are and how they compare to the via Stoke's.
 

All Line Rover

Established Member
Joined
17 Feb 2011
Messages
5,221
Indeed - I'd be very interested to see what the reliability of the Manchester via Crewe's are and how they compare to the via Stoke's.

They generally manage to catch up the time by Piccadilly. Therefore the PPM statistics are unaffected, which might explain why VT does not appear to care about the problem (which is fair enough - Manchester is the most important destination). But it's still a nuisance for passengers with connections at Crewe, Wilmslow or Stockport.
 