Baker Street SC will close tonight.
Where are they moving to? HammersmithBaker Street SC will close tonight.
Yes, to join the Line Controllers and other service operators
It is also worth mentioning that what is closing tonight is the 'interim' signallingIs Baker St SCC (Met) closing tonight
Commissioned on Saturday morning.I don’t know if the signalling has been changed yet.
What’s the speed improvements following this?Commissioned on Saturday morning.
As with the District, up to 62mph maximum in certain sections.What’s the speed improvements following this?
officially 100kph (62mph) on certain sections, though the ATO system seems to have more minor lower restictions programmed in - notably at Neasden where it slows down more than some of the trains did previously.What’s the speed improvements following this?
The Amersham and Chesham services are running Semifast (calling at Wembley Pk) during the daytimes and evenings when they would otherwise run all stations. It’s worth pointing out that this timetable notice is only for Mon-Thurs, the normal timetable will resume on Friday.North of wembley, the signalling changeover at the boundary seems to extend journey times for the semi-fast trains not stopping at Preston Road or Northwick Park slightly - but under the current timetable there are more semi-fast trains although fewer trains on the met network than normal. So if you are heading north of Wembley, there is a chance you could end up on a faster service than a stopper. I think the Amersham Chesham and some Watford's are semi-fast right through the day!
Yes, next for the MET is SMA 9 Preston Road-West Harrow/Moor Park, likely early-2026.Will this get beyond Harrow? More journey time savings to be made up to Moor Park, I would say.
The project is not just about speed , though the time savings are welcome. It is also about capacity and being able to run more trains closer together.Will this get beyond Harrow? More journey time savings to be made up to Moor Park, I would say.
Update is provided in latest TfL Board papers, Programmes and Investment Committee, ahead of next weeks meeting
section 7.1.5 says SMA14 (Rayners Lane - Uxbridge) is expected to go live in 2027, and programme close out will be 2028 once software optimisations completed.
Section 7.1 has a table showing final expected cost is £5,622 million
You'd have to go back through all the minutes to identify a step change when the contracts were changed, but this graph:Is that £5.6b "With a B" only for the Thales contract, or does it also include the aborted costs of the Siemens Invensys and the Bombardier contracts as well...?
Yes, it is the capital expenditure (purchase, installation, commissioning) of new signalling and trains, plus some alterations to infrastructure to accommodate it.Is this figure for the whole of the 4 lines modernisation - including the S stock trains?
section 7.1.7 on the page after the graph says ’the programme […] has already provided 92 modern, air-conditioned walk-through trains’
192 S Stock trainsIs this figure for the whole of the 4 lines modernisation - including the S stock trains?
section 7.1.7 on the page after the graph says ’the programme […] has already provided 192 modern, air-conditioned walk-through trains’
Is there any indication which SMAs will be indefinitely deferred, as of that date?programme close out will be 2028
Is there any indication which SMAs will be indefinitely deferred, as of that date?
Does that mean the problems with the platform indicators at places like West Brompton (no clue where the trains are going; to) and Earls Court (no clue about trains coming from the Wimbledon direction until a few minutes before they arrive) that were caused by the SSR are going to continue indefinitely?No update on what will happen to descoped parts (District south of Fulham area, west of Stamford Brook), and Ealing depot (sometimes called Ealing radio island, as it allowed testing before exiting depot).
The TfL Board papers in post #439 say last migration in 2027, and project close 2028 after some final updates.Does that mean the problems with the platform indicators at places like West Brompton (no clue where the trains are going; to) and Earls Court (no clue about trains coming from the Wimbledon direction until a few minutes before they arrive) that were caused by the SSR are going to continue indefinitely?
Does that mean the problems with the platform indicators at places like West Brompton (no clue where the trains are going; to) and Earls Court (no clue about trains coming from the Wimbledon direction until a few minutes before they arrive) that were caused by the SSR are going to continue indefinitely?
As said by @bluegoblin7 above, SMA12 Fulham Bdwy-East Putney will be commissioned, likely in early 2026.No update on what will happen to descoped parts (District south of Fulham area, west of Stamford Brook),