Quite. I seriously wonder if a span in two halves is the best way, one crane takes each and then they are bolted together in situ. Would be better done in calm weather! Or a couple of Chinooks with a full span... Edit - I've also just looked more closely at the photo with the class 69, and it looks like there is an area of discolouration on the deck above the DFL, which could just be old graffiti or paint, etc., from an impact.The problem is that if the deck comes in by rail, it has to be turned through 90° - and it's long. Not too hard to tandem lift with two crawlers, since they can move with a load on the hook, but I doubt if the Kirovs can.
No-one is going to use this discussion as the basis of a method statementMeanwhile I quite enjoy speculating - I used to do this sort of stuff for a living, and it's so much easier as a spectator!