reddragon
Established Member
Whilst numerically GWEP won, GOBLIN trashed it in numbers per km hit / severed!If you want to find lost drainage or cables, electrify. The piles are unbelievably good at finding em.
Whilst numerically GWEP won, GOBLIN trashed it in numbers per km hit / severed!If you want to find lost drainage or cables, electrify. The piles are unbelievably good at finding em.
At Heaton Lodge I believe the existing bridge will be reconstructed in situ on the existing lines, which will become the slow lines, with the new fast lines bypassing the junction to the south. I imagine this will require a blockade. Conceivably if the fast lines have been built by then, Hudds-Leeds trains would still be able to run, but there has been talk on here of several blockades. Once it's all built, works could be done on the fast lines with trains diverted to the slows for the full length of the 4-track section.So, would I be correct in assuming that the grade-seperated junctions at Thornhill and Heaton Lodge will only connect the Calder Valley line to the slow lines? If so, how would engineering work or obstruction diversions from the upgraded TP route be organised?
Thanks. That makes sense!At Heaton Lodge I believe the existing bridge will be reconstructed in situ on the existing lines, which will become the slow lines, with the new fast lines bypassing the junction to the south. I imagine this will require a blockade. Conceivably if the fast lines have been built by then, Hudds-Leeds trains would still be able to run, but there has been talk on here of several blockades. Once it's all built, works could be done on the fast lines with trains diverted to the slows for the full length of the 4-track section.
At Thornhill the new flyover will carry the new fast lines over everything else (except the Dewsbury-bound slow line), and will enable the fast lines to move from the south side to the middle, between the slows, before the 4 tracks reduce to 2.
If the 543 are indeed 40% complete, there must be another 90 or so somewhere.I counted 57 OHLE piles on the Up today, between Victoria and Ashton, and 70 on the Down.
I don't doubt I missed some, maybe on top of cutting walls and un-visible fixings on bridges/viaducts.If the 543 are indeed 40% complete, there must be another 90 or so somewhere.
Whilst numerically GWEP won, GOBLIN trashed it in numbers per km hit / severed!
Its Twyford to Newbury versus the Walthamstow carnage!Is there a league table of severity of hit ?
I recall that Leeds NW had a Biggie at Shipley when a pile hit the Oil Jacketed power supply to Bradford back in about 1993.
Rather than what happens if the fasts are closed, it's notable that when the slows are closed the stoppers will not be able to serve Ravensthorpe, Mirfield or Deighton. That's not enough of a problem to justify providing platforms on the fasts for occasional use, though I could see Mirfield being worthy of peak stops on the fast services if it were possible.At Heaton Lodge I believe the existing bridge will be reconstructed in situ on the existing lines, which will become the slow lines, with the new fast lines bypassing the junction to the south. I imagine this will require a blockade. Conceivably if the fast lines have been built by then, Hudds-Leeds trains would still be able to run, but there has been talk on here of several blockades. Once it's all built, works could be done on the fast lines with trains diverted to the slows for the full length of the 4-track section.
At Thornhill the new flyover will carry the new fast lines over everything else (except the Dewsbury-bound slow line), and will enable the fast lines to move from the south side to the middle, between the slows, before the 4 tracks reduce to 2.
I counted 57 OHLE piles on the Up today, between Victoria and Ashton, and 70 on the Down.
Nothing east of Ashton, and just 4 east of the M60 Bridge.
East of Church Fenton, there is an earth wire linking 26 masts on the west side, roughly where the fast/slow crossover is, and a couple on the east side.
The whole 5 miles looks ready for SPS, with just a few cantilever sections missing near Colton.
With Piccadilly-Marsden now being the NPR target, bypassing Stalybridge, is there any point in TRU re-re-modelling the layout at Stalybridge to favour Victoria?
Did they not use electricity detectors?Its Twyford to Newbury versus the Walthamstow carnage!
Not only were the buried pipes / cables marked correctly on their plans, visible in places on the surface and paint marked on the ground, they knew they'd hit them and carried on piling with liquid / sparks etc all over the place for up to half an hour!Did they not use electricity detectors?
...or used them after they'd piled
I hope the contractors responsible paid for the repairs to be made. Though I wouldn't be surprised it they didn't...Not only were the buried pipes / cables marked correctly on their plans, visible in places on the surface and paint marked on the ground, they knew they'd hit them and carried on piling with liquid / sparks etc all over the place for up to half an hour!
The GWEP 3rd party ones yes, NR ones not sure if they all got done.I hope the contractors responsible paid for the repairs to be made. Though I wouldn't be surprised it they didn't...
I would like to be shocked by that answer... but I'm not!The GWEP 3rd party ones yes, NR ones not sure if they all got done.
Goblin - No and many still not fixed flooding the railway each time it rains since 2016! NR are out of pocket on this one due to the scale of damage & unresolved issues.
With Piccadilly-Marsden now being the NPR target, bypassing Stalybridge, is there any point in TRU re-re-modelling the layout at Stalybridge to favour Victoria?
I hope the contractors responsible paid for the repairs to be made. Though I wouldn't be surprised it they didn't...
Why not? Is it covered by the seemingly infinite number of sub-contracts, or is it just a case of "pass it on to Network Rail, no-one cares of they have to pay"?It’s a rare major works contract that includes consequential damages such as this.
I almosthate to say but in those cases... rail replacement buses. It might not be right but you know it'll happen (which is why I mentioned potential problems on the fast lines, they'll always get the priority). Which is I wondered about two sets of crossings, either side of Mirfield.Rather than what happens if the fasts are closed, it's notable that when the slows are closed the stoppers will not be able to serve Ravensthorpe, Mirfield or Deighton. That's not enough of a problem to justify providing platforms on the fasts for occasional use, though I could see Mirfield being worthy of peak stops on the fast services if it were possible.
Why not? Is it covered by the seemingly infinite number of sub-contracts, or is it just a case of "pass it on to Network Rail, no-one cares of they have to pay"?
There seems to be 3 or 4 missing TTCs on the Normanton lines just north of Ulleskelf.East of Church Fenton, there is an earth wire linking 26 masts on the west side, roughly where the fast/slow crossover is, and a couple on the east side.
The whole 5 miles looks ready for SPS, with just a few cantilever sections missing near Colton.
Four tracking Micklefield to Church Fenton wouldn't give you the capacity to avoid the stoppers like the HS2 alignment would.I understand at Church Fenton they are looking to add two additional lines and the the two options on the table are.
A: Use the planned HS2 route and join where the current works have stopped just north of Church Fenton and put in a new section of track.
B: Add two new lines going past Rose Lane where they are closing the crossing and putting in a new highway to access the houses.
Indeed not!Four tracking Micklefield to Church Fenton wouldn't give you the capacity to avoid the stoppers like the HS2 alignment would.
The ideal solution would be to 4 track Marsh Lane to Thorpe Park and for the fasts to then take the HS2 route to Ulleskelf thereby overcoming the issue of stoppers standing on the fast lines at stations.I understand at Church Fenton they are looking to add two additional lines and the the two options on the table are.
A: Use the planned HS2 route and join where the current works have stopped just north of Church Fenton and put in a new section of track.
B: Add two new lines going past Rose Lane where they are closing the crossing and putting in a new highway to access the houses.
Though if you're building a new line on an alignment designed for high speed, you might as well build it to the design speed, so that you don't have to rebuild it in the future if/when a complete high speed line is built. There's no harm in running 100mph trains on a 250mph line, if they're the only trains using it.I suppose a non-high speed line could be built on the secured alignment, if responsibility for it were passed to Network Rail, but that likely depends on what benefit a short stretch of HSL brings.
I don't disagree, but we're talking about 8 miles here. Somebody will come along and tell us the time that saves.Though if you're building a new line on an alignment designed for high speed, you might as well build it to the design speed, so that you don't have to rebuild it in the future if/when a complete high speed line is built. There's no harm in running 100mph trains on a 250mph line, if they're the only trains using it.
You might get away with just four tracking from Cross Gates onwards, as long as you keep slower DMUs off of the Hull trains.The ideal solution would be to 4 track Marsh Lane to Thorpe Park and for the fasts to then take the HS2 route to Ulleskelf thereby overcoming the issue of stoppers standing on the fast lines at stations.
Not much.I don't disagree, but we're talking about 8 miles here. Somebody will come along and tell us the time that saves.