When do overnight possessions/engineering work get confirmed?

Status
Not open for further replies.

ivorytoast28

Member
Joined
10 Dec 2018
Messages
176
Location
Sheffield
I'm hoping to use the 24hr thameslink on the 20th July but the nationalrail journeyplanner still is showing as unconfirmed journey
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

ivorytoast28

Member
Joined
10 Dec 2018
Messages
176
Location
Sheffield
I believe I read that engineering possessions are nornally planned 26 weeks in advance.
Thanks, So it should have been decided by now? Where can I confirm that there isn't any engineering works as nationalrailenquires still shows it as:
We don't yet know if this journey will be affected by engineering work.

Please check back closer to the time of travel.
 

hexagon789

Veteran Member
Joined
2 Sep 2016
Messages
15,793
Location
Glasgow
Thanks, So it should have been decided by now? Where can I confirm that there isn't any engineering works as nationalrailenquires still shows it as:
Well, I'm sure someone will be along to correct/ammend what I'm saying if I've understood wrongly, but my basic understanding is that engineering possessions are "drawn-up" if you like and put in a document called the Confirmed Period Possession Plan. This document is published 26 weeks before the planned work within it, AIUI.

That's where I got the 26 weeks from.
 
Last edited:

Peregrine 4903

Established Member
Joined
18 Aug 2019
Messages
1,456
Location
London
Engineering works are confirmed 26 weeks in advance, although that doesn't include decisions and late notice possessions.

But the timetable around engineering works currently doesn't get confirmed until 6 weeks in advance, and sometimes it can be even less than 6 weeks in advance if operators are bidding late.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,971
Well, I'm sure someone will be along to correct/ammend what I'm saying if I've understood wrongly, but my basic understanding is that engineering possessions are "drawn-up" if you like and put in a document called the Control Period Possession Plan. This document is published 26 weeks before the planned work within it, AIUI.

That's where I got the 26 weeks from.
Close. Confirmed Period Possession Plan or CPPP.
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
2,892
Location
Near where the 3 ridings meet
As a track renewals contractor to Network Rail, we used to have to submit our possession requests 52 weeks out.
Sometimes for big disruptive jobs, possessions and key resource requests could be planned in about 5 years out.
 

717001

Member
Joined
4 Aug 2018
Messages
221
This page on NRE is useful https://www.nationalrail.co.uk/service_disruptions/254145.aspx

Engineering pages might be correct longer ahead, but it currently states for Thameslink, that journey planners are up to date until (NB final comment):
Saturday:
9 July

Sunday:
10 July

Monday to Friday:
15 July

Notes and exceptions:
Alterations because of engineering work on Mondays to Fridays may not be shown until 12:00 on the day before the timetable operates
 

Romsey

Member
Joined
30 Nov 2019
Messages
334
Location
Near bridge 200
The 26 weeks Confirmed Period Possession Plan is to allow time for the TOC's to plan their service alterations, for them to be validated and uploaded to TSDB and all the down stream systems 12 weeks before operation (Informed Traveller timescales.)

OK I know Informed Traveller Timescales are still an aim rather than a fact for part of the country, but I gather much of the network is getting back to those timescales.

There are late notice engineering works alterations, but anything which disrupts the planned service has to be agreed at a high level within NR, often Route Director level. This is to stop engineers, making use of staff and equipment because they are spare, but any change would wreck the engineering works plan. I have seen engineering functions get very upset then they couldn't have an additional block. It was pointed out that the extra possession would block the only route to site for material trains for their high profile 52 hour multiline multi part possession. Suddenly the request was dropped.

Then s### happens, a cable arcs out taking out the traction current supply, lining in a tunnel is dislodged or there are unexpected earthmovements.
 

Peregrine 4903

Established Member
Joined
18 Aug 2019
Messages
1,456
Location
London
The 26 weeks Confirmed Period Possession Plan is to allow time for the TOC's to plan their service alterations, for them to be validated and uploaded to TSDB and all the down stream systems 12 weeks before operation (Informed Traveller timescales.)

OK I know Informed Traveller Timescales are still an aim rather than a fact for part of the country, but I gather much of the network is getting back to those timescales.

There are late notice engineering works alterations, but anything which disrupts the planned service has to be agreed at a high level within NR, often Route Director level. This is to stop engineers, making use of staff and equipment because they are spare, but any change would wreck the engineering works plan. I have seen engineering functions get very upset then they couldn't have an additional block. It was pointed out that the extra possession would block the only route to site for material trains for their high profile 52 hour multiline multi part possession. Suddenly the request was dropped.

Then s### happens, a cable arcs out taking out the traction current supply, lining in a tunnel is dislodged or there are unexpected earthmovements.
Informed traveller at 12 weeks :D
:D :D :D :D :D :D :D :D

Its 6 weeks now for publishing, and I can't see it ever pushing out much further ever again.
 

SteveHFC

Member
Joined
1 Nov 2014
Messages
117
Informed traveller at 12 weeks :D
:D :D :D :D :D :D :D :D

Its 6 weeks now for publishing, and I can't see it ever pushing out much further ever again.
It's 8 weeks for publishing, and I know this as I'm the person who publishes the Informed Traveller schedules for my team at NR each Friday. Certainly no plans at the moment to get back to publishing at 12 weeks out - and from what I've been told, there is a significant chance it'll remain at 8 weeks on a permanent basis.

Thing to remember regarding engineering works is that there can be late notice possessions at any time if something breaks on the infrastructure, and there are numerous late notice possessions (possessions confirmed after the CPPP has been published) going into the system on a daily basis.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,971
It's 8 weeks for publishing, and I know this as I'm the person who publishes the Informed Traveller schedules for my team at NR each Friday. Certainly no plans at the moment to get back to publishing at 12 weeks out - and from what I've been told, there is a significant chance it'll remain at 8 weeks on a permanent basis.

Thing to remember regarding engineering works is that there can be late notice possessions at any time if something breaks on the infrastructure, and there are numerous late notice possessions (possessions confirmed after the CPPP has been published) going into the system on a daily basis.
Nothing significant about the chance, it will be 8 weeks.
 

Peregrine 4903

Established Member
Joined
18 Aug 2019
Messages
1,456
Location
London
It's 8 weeks for publishing, and I know this as I'm the person who publishes the Informed Traveller schedules for my team at NR each Friday. Certainly no plans at the moment to get back to publishing at 12 weeks out - and from what I've been told, there is a significant chance it'll remain at 8 weeks on a permanent basis.

Thing to remember regarding engineering works is that there can be late notice possessions at any time if something breaks on the infrastructure, and there are numerous late notice possessions (possessions confirmed after the CPPP has been published) going into the system on a daily basis.
Thought I typed 8, whoops!

But same principal applies.
 

MedwayValiant

Member
Joined
8 Jan 2013
Messages
363
This discussion relates to something that has been going round my head for the last 24 hours.

There will be some sections of railway for which engineering work is booked in to happen on Saturday 25 June. That engineering work will still happen since the people who do that work will not be on strike, and contracts to operate replacement bus services will be in place.

Can the affected TOCs at this point look to cancel those replacement bus services on the basis that the train services into which they are intended to connect won't be running? Or will people who had planned to use those sections of railway get lucky, and the replacement bus services will operate as planned?
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,971
This discussion relates to something that has been going round my head for the last 24 hours.

There will be some sections of railway for which engineering work is booked in to happen on Saturday 25 June. That engineering work will still happen since the people who do that work will not be on strike, and contracts to operate replacement bus services will be in place.

Can the affected TOCs at this point look to cancel those replacement bus services on the basis that the train services into which they are intended to connect won't be running? Or will people who had planned to use those sections of railway get lucky, and the replacement bus services will operate as planned?
There is no guarentee the works will take place at all. You still need singallers to get trains to/from/in/out of the works. If boxes are working 0700-1900 as suggested those trains won't be running.
 