YourMum666
Member
Which parts of the railway network (when electrified) would take the most diesels off the railway ?
Is there a limit of STkm or cost?Which parts of the railway network (when electrified) would take the most diesels off the railway ?
That should be top of thelist with Didcot-Oxford in my opinion.Surely the lines through Birmingham Moor St and Snow Hill must be up there ?
You'd also need to do the terminals as well.If we think along the lines of various freight trains that are diesel hauled throughout because that is easier than switching locos, then IIRC somewhere around North London is about a mile and a half which if it were to be electrified would enable many freights to do away with diesel haulage completely. No idea if there are sufficient electric locos available to haul all these trains?
But XC don't have bi-modes and aren't in line to get any. Didcot-Oxford would let the hourly stopper be replaced by an re-extended Pad-Didcot and the IETs to use electricity through to Oxford. That's probably the single best return per STkm on the network, Bristol both ways being second (again because of the IETs).As I mentioned elsewhere on the forum Didcot-Oxford would take 4toh, 6 if XC got bi modes. Reading to Basingstoke could do 3.
A cost limitIs there a limit of STkm or cost?
I'd say Chiltern would probably be the largest amount of diesel services since Birmingham Snow Hill lines went to 4tph but it depends where you draw the lines.
Cost wise,A cost limit
As I mentioned elsewhere on the forum Didcot-Oxford would take 4toh, 6 if XC got bi modes. Reading to Basingstoke could do 3.
That should be top of thelist with Didcot-Oxford in my opinion.
Snow Hill lines are 4tph for the foreseeable.On the basis XC doesn't have bi-modes - then actually you're looking at 4tph - I suspect the Snow Hill lines are more than that - even if you didn't wire the Chiltern in its entirety and focused instead on Leamington, Stratford, Kidderminster and Worcester.
Snow Hill lines are 4tph for the foreseeable.
So I'd do Didcot-oxford because it's basically as ready as it'll ever be for work to start on site, and having Oxford wired ticks another box for EWR and Chiltern.TBF I hadn't checked - but given those are stop / start 'inner suburban' style commuter services running through the UK's 2nd city, it would have far greater impact than Didcot - Oxford which is an 'outer suburban' limited stop in a largely rural area.
If I were spending the money, it would go on the West Mids every time.
Agreed, then do the Furness line afterwards.At the other end of the scale, Oxenholme to Windermere ought to be a no brainer given the 4 trains per day from Manchester Airport run under the wires for the vast majority of the journey and the electrification is simply wiring a single track with no points. Indeed this ought to be a test location for some carbon fibre posts to minimise the insulation required using metal and reducing the expensive foundations in rocky terrain. Once done the entire service is 100% electric and the 195s freed up can go to replace older units elsewhere in Northern's franchise. There's no shortage of EMUs needing a new home.
At the other end of the scale, Oxenholme to Windermere ought to be a no brainer given the 4 trains per day from Manchester Airport run under the wires for the vast majority of the journey and the electrification is simply wiring a single track with no points. Indeed this ought to be a test location for some carbon fibre posts to minimise the insulation required using metal and reducing the expensive foundations in rocky terrain. Once done the entire service is 100% electric and the 195s freed up can go to replace older units elsewhere in Northern's franchise. There's no shortage of EMUs needing a new home.
Agreed, then do the Furness line afterwards.
Liverpool South Parkway-Warrington Central-Deansgate, with trains from Sheffield to Manchester terminating at Piccadilly (main trainshed).
AgreedAt the other end of the scale, Oxenholme to Windermere ought to be a no brainer given the 4 trains per day from Manchester Airport run under the wires for the vast majority of the journey and the electrification is simply wiring a single track with no points.
Im not sure carbon fibre would save much piling on Windermere. Generally you need deep piles for soft ground and more substantial piles double track cantilevers. GWEP had both and inadequate ground surveys.Indeed this ought to be a test location for some carbon fibre posts to minimise the insulation required using metal and reducing the expensive foundations in rocky terrain.
Ooh that looks interesting, do you know anywhere it's proposed for use?A more interesting trial would be the Mott and Moxon wood laminate (and metal post!) cantilever below as it looks nicer....
The problem with painting them green is that then people complain they stand out against the sky....also if the UK could finally start painting OLE masts green so they are less obvious.
Nowhere in the UK afaik, they've only unveiled a single track cantilever. Id expect Network Rail to want double track cantilevers and portals before mainline use. Windermere would be fine though.Ooh that looks interesting, do you know anywhere it's proposed for use?
The current grey stands out from everythingThe problem with painting them green is that then people complain they stand out against the sky....
I don’t think many (if any) would be displaced. It would just allow fully electric running for GWR IET’s. It would also be another area of XC then electrified and build their case for bi modes.How many diesels would be displaced if electrifying Chippenham to Bristol happens?
Traditionally wooden poles have been used on the railway at voltages as high as 50kV in South Africa and North AmericaYou'd want the post to be made out of a conductor (and earthed) anyway, 25kv can make its way through a very thin layer of water. While the insulators on the cantilever should prevent the water I'd still the concerned about a non metal post.
Fair point. Though carbon fibre supports (as suggested above) would still cost a lot more and wouldn't save much piling.Traditionally wooden poles have been used on the railway at voltages as high as 50kV in South Africa and North America
If a solid earthing strap is provided to the cantilever equipment then I don't think the pole itself has to be conductive.
After all, wooden poles are used for voltages as high as 132kV in grid applications.
Someone will come along and suggest Yellow for Health and Safety.Ooh that looks interesting, do you know anywhere it's proposed for use?
The problem with painting them green is that then people complain they stand out against the sky....
I wasn't aware that XC had any services on that stretch of line, unless diverted?I don’t think many (if any) would be displaced. It would just allow fully electric running for GWR IET’s. It would also be another area of XC then electrified and build their case for bi modes.