Why did Eurostar go with Siemens Velaro rather than the Alstom AGV?

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

woolwinder

Member
Joined
2 Feb 2009
Messages
26
Location
stevenage
Is anybody going to answer the question; was it technical, political, greased palms, downright bloody mindless, or pro siemens or anti Alstom clic within SNCF (you can forget any E* board input was minimal as usual)?
 

MCR247

Established Member
Joined
7 Nov 2008
Messages
9,602
I don't know what kind of answer you want. Since presumably none of us were apart of the process where E* looked at designs and chose one, all we can do is speculate? You say within SNCF as if it was wholly their decision
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,932
Location
Nottingham
The process would have been, approximately:

- Decide what is important for your train and write a specification.

- Publish an advertisement in the Official Journal.

- Send all responders a prequalification document inviting them to respond to specific questions and including the selection criteria that will determine how bidders are selected according to the answers.

- After the deadline for prequalification responses, select the prequalified bidders making sure the selection criteria are strictly followed. If properly done this will result in enough credible bidders to ensure competition but not so many that the process becomes unworkable.

- Send the prequalified bidders the full Invitation to Tender including the spec and the final selection criteria, which will be similar to the prequalification but hugely more detailed. Notify the others of failure to prequalify. Hold breath awaiting possible challenge.

- Assuming no challenge, await responses from bidders by deadline. Evaluate responses again, also paying attention to strict adherence to selection criteria. Possibly negotiate with a preferred bidder while keeping the others in reserve in case no agreement can be reached.

- Announce winning bidder. Wait for "standstill period" when other bidders can challenge. Sign contract.

The above is intended to ensure that all bidders compete on merit. If not strictly followed there is a strong chance of legal challenge from either unsuccessful bidders or the European Commission. In particular, requirements and selection criteria have to be based on genuine needs of the client, not things that are included to favour the selection of the supplier that the client really wants! These issues are likely to be at the root of the various battles arising from the Eurostar procurement.
 

ainsworth74

Forum Staff
Staff Member
Global Moderator
Joined
16 Nov 2009
Messages
27,703
Location
Redcar
Is anybody going to answer the question; was it technical, political, greased palms, downright bloody mindless, or pro siemens or anti Alstom clic within SNCF (you can forget any E* board input was minimal as usual)?

Perhaps it was a process where the design which best met the criteria won? Why do you suggest there was corruption?
 