I assume that by "Main Street, Market Harborough" it means Main Street, Great Bowden.
Both bridges are to be demolished; the more northern of the 2 bridges, O/B 24, is to be reconstructed, while O/B 25 won't be replaced. O/B 25 will be kept open while O/B 24 is rebuilt.
Note that the application is, at the time of this post, still pending approval.
Thanks for the pics Flying Phil, on a trip north today I counted some more piles, again north of Great Bowden and around the A6 bridge. So, on the up side I counted approximately 30 piles. There was also a lot of vegetation clearance.
One.network reporting that the closure of Pipewell Rd (SPC3-42, the bridge at Rushton) has been extended by 18 days, to the 23rd of December.
It's also reporting that:
U/B SPC3-26 (B6047 Melton Rd, East Langton) will have two-way traffic signals to control access to the East Langton Compound from 21/11/22 to 31/05/24;
F/B SPC3-18 (Grammar School Footbridge, Kibworth Harcourt) will be closed from 19/12/22 to 23/12/22;
O/B SPC3-15 (Wistow Rd, Kibworth Harcourt) will have two-way traffic signals to control access to the Wistow Rd Compound from 21/11/22 to 31/05/24;
O/B SPC3-10 (Station Rd, Great Glen) will be closed from 04/01/23 to 23/07/23.
I agree. There were also tree clearance works at Sheffield last week (my cousin complained about the loss of screening), so I think it's taking advantage of winter when the vegetation is easier to handle and things aren't nesting to deal with problem areas.
There might be some overrun at South Wigston Junction, but I'd be very surprised if they got as far as Narborough.
== Doublepost prevention - post automatically merged: ==
Speaking of - the small gap at Rushton (between SPC3-44 & SPC3-43) has now been closed. SPL teams were fitting cantilevers, and other dangly bits to various structures here and elsewhere in the Rushton area.
The missing structures were SPC3/121.973/UM (TTC in picture 1; note the cantilever assemblies next to the mast awaiting installation), SPC3/122.017/DM+UM (MPA Portal in picture 1, with the linesfolk working on it) and STC pair SPC3/122.072/DM+UM (DM cantilever in picture 1, UM mast in picture 2). Note also in Picture 1 the tall mast on the Kettering side of SPC3-44 - this is an ATF Anchor, numbered SPC3/121.918/UM - positioned 5 metres south of 121.923/UM, the TTC just the other side of the bridge. Picture 3 shows detail of this, and picture 4 shows another UM SSA to anchor the ATF; this being numbered SPC3/122.132/UM.
== Doublepost prevention - post automatically merged: ==
Further west, from the bridge works compound for SPC3-42 to underbridge SPC3-41, the masts are all now gaining ATF insulators. At DEP (Designated Earthing Point) locations, this involves many more insulators being added to allow for ease in the earthing process (picture 5 shows masts SPC3/123.524/DM+UM, which have all these insulators on. Note that the ATF and EW clamps extend towards the track to keep the conductors over NR land).
Back at the LR191 to LR194 signal gantry, the 2 shortened STC pairs (SPC3/122.836/DM+UM and SPC3/122.891/DM+UM) which were removed have been replaced with 2 Portals (122.831 & 122.896) to overcome what I can only assume to be a signal sighting issue (see picture 4). I can't tell yet if the existing piles are to be re-used for ATF purposes, but time will reveal all. Note that in the far background of picture 6, a pair of very tall SSAs can be seen - these will anchor the ATF conductors and bring them down to ground level via cable sealing ends.
== Doublepost prevention - post automatically merged: ==
Speaking of - the small gap at Rushton (between SPC3-44 & SPC3-43) has now been closed. SPL teams were fitting cantilevers, and other dangly bits to various structures here and elsewhere in the Rushton area.
The missing structures were SPC3/121.973/UM (TTC in picture 1; note the cantilever assemblies next to the mast awaiting installation), SPC3/122.017/DM+UM (MPA Portal in picture 1, with the linesfolk working on it) and STC pair SPC3/122.072/DM+UM (DM cantilever in picture 1, UM mast in picture 2). View attachment 125051View attachment 125050
More images will be coming...
== Doublepost prevention - post automatically merged: ==
Further west, from the bridge works compound for SPC3-42 to underbridge SPC3-41, the masts are all now gaining ATF insulators. At DEP (Designated Earthing Point) locations, this involves many more insulators being added to allow for ease in the earthing process (picture 3 shows masts SPC3/123.524/DM+UM, which have all these insulators on. Note that the ATF and EW clamps extend towards the track to keep the conductors over NR land). View attachment 125053
Back at the LR191 to LR194 signal gantry, the 2 shortened STC pairs (SPC3/122.836/DM+UM and SPC3/122.891/DM+UM) which were removed have been replaced with 2 Portals (122.831 & 122.896) to overcome what I can only assume to be a signal sighting issue (see picture 4). I can't tell yet if the existing piles are to be re-used for ATF purposes, but time will reveal all. Note that in the far background of picture 4, a pair of very tall SSAs can be seen - these will anchor the ATF conductors and bring them down to ground level via cable sealing ends. View attachment 125054
Many thanks for those. I was interested to read about the autotransformer provision. Can someone please remind me whether any of the already-wired section of MML is currently equipped with ATF?
Many thanks for those. I was interested to read about the autotransformer provision. Can someone please remind me whether any of the already-wired section of MML is currently equipped with ATF?
Currently, only the section between Kentish Town SATS (Sectioning Autotransformer Site) & Borehamwood ATFS (Autotransformer Feeder Station) is equipped with ATF. This was done as part of the Thameslink Programme works.
The new TSCs at Napsbury (KO1a), Ampthill (KO1), Bedford (KO1), Irchester (KO1), Harrowden (KO1) and Kettering North (KO1), along with the MPTSCs at East Hyde (KO1a) and Sharnbrook (KO1) are all autotransformer ready. Long Meadow Farm (Chalton) ATFS (also KO1), which came online last Christmas, also has AT capability, and Braybrooke ATFS (KO1a) will have it from the outset.
IMO it makes sense to do all the work, including ATF, right now on the Kettering - South Wigston section as the contractors won't have to come back to retrofit it later, on a section of route without the ability to keep one pair of tracks open.
Further west, the SPL teams were hard at work installing ATF insulators around bridge SPC3-35AA (Braybrooke Bridleway Bridge) - see pictures below.
I arrived around 3pm, just before sunset; at this point, the team had just finished installing their 5th pair of insulators on the TTCs in the area. They started their 6th pair as I left, and are probably complete through there now. They seemed to have missed out the MPA Portal in the area (SPC3/129.070/DM+UM), but they might have returned to it today (11th December).
Trial Holes have also been dug for the northern ATF Anchors on the other side of the footbridge. The existing SSA piles to signify the southern end of the next run of wires, numbered SPC3/129.439/DM+UM, now have holes 5m north, at 129.444km. (The UM hole has Armco Barrier next to it.)
Earlier that day I also checked around Judges Bridge, Desborough (SPC3-38) - piles and Armco Barriers (on the DM side) for the new ATF anchor masts either side of the bridge have gone in now too. There are also 2 pairs either side of SPC3-37F (the A6 Desborough Bypass) but it's impossible to get a snap there unless you're on track!
ATF insulators have also reached Market Harborough, although only around U/B SPC3-31 (Scotland Road), and only on the southern anchors and both TCM pairs. The big monoboom Anchor (the Series 1 Portal) looks to be anchoring the ATF on the DM side - couldn't speak for the UM on this trip.
== Doublepost prevention - post automatically merged: ==
Update 12/12/22: Trains still running via the Corby route all day today as one of the engineers' trains derailed yesterday.
As of 1445 today, the engineers' trains are all still on site...
(Images show the line block still being in place between Kettering and Wigston Junctions)
Thanks for these. Can I ask what is the thing that looks like an angled house drainpipe at the end of the TTC in pic #5? Is it for an Earth wire on the outside track?
Thanks for these. Can I ask what is the thing that looks like an angled house drainpipe at the end of the TTC in pic #5? Is it for an Earth wire on the outside track?
Thank you. I had understood that earlier post was referring to the round pipes, which I think are called "stovepipes". But I see now they seem to do have the same function. (Image from pic #1 above)
Am I right to assume that round ones are used when they are straight, and square ones when there is an offset? (Which has to be secured against rotation forces, I imagine).
Thank you. I had understood that earlier post was referring to the round pipes, which I think are called "stovepipes". But I see now they seem to do have the same function. (Image from pic #1 above)
View attachment 125141
Am I right to assume that round ones are used when they are straight, and square ones when there is an offset? (Which has to be secured against rotation forces, I imagine).
A lot of them would be "desginer's preference" - so whoever designed the OLE layouts/cross-sections would have allocated different pipe types for different situations.
AFAICT, the straight cylindrical pipes are used for Earth Wires and ATF Insulators, the straight square pipes are used for cantilevers, and the "cranked" square pipes are used for EWs as well when a cranked pipe is needed (e.g. to maintain signal sighting around a curve).
== Doublepost prevention - post automatically merged: ==
North of Market Harborough over the weekend:
Track lowering in evidence beneath Main St, Gt Bowden (Bridge SPC3-28D); photos taken from footbridge SPC3-28E.
This was when works were still on schedule and one of the works trains hadn't derailed...
Alongside the lowering of the Up Main, new track drainage was installed in the "6-foot" between the Dn Main & Up Main. Follow-up works are taking place this week to get it back to linespeed - although the strikes might affect this somewhat.
Further lowering works are to take place this weekend (again, strikes depending) - all the details are on the MMLE Map.
Outside Mkt Hboro, piles have now been installed either side of bridge SPC3-28: 2 pairs to the north (up to SPC3-27F - the A6 Harboro' Bypass), and 4 pairs to the south (up to signals LR221/LR223).
Note that the southernmost DM pile hasn't been fully hammered down yet. Also, this seems to me like the start of the next tension length after the one immediately north of Market Harborough - which hasn't been started on yet AIUI owing to the track lowering work.
A question about bridges like that for the M.H.by-pass, possibly due to not being well-informed.
Someone I know is a retired bridge engineer. When I saw him recently he said that some of the bridge rebuilds / new bridges he'd P.M.'d on un-electrified lines had been future proofed in the sense that they were built to clear O.L.E. but subsequent E.U. legislation required a larger clearance and they therefore would need rebuilding again. Have any bridges on the MML fell foul of this?
Someone I know is a retired bridge engineer. When I saw him recently he said that some of the bridge rebuilds / new bridges he'd P.M.'d on un-electrified lines had been future proofed in the sense that they were built to clear O.L.E. but subsequent E.U. legislation required a larger clearance and they therefore would need rebuilding again. Have any bridges on the MML fell foul of this?
I don't believe any of the rebuilds on the MML have - certainly nothing east of M.H. The bypass has more than enough room.
The new footbridge north of the bypass (SPC3-27EA) looks to be alright too.
Speaking of...there are 3 pile pairs (2 of which are complete) between bridge 27EA & 27F. The DM pile nearest 27F has only had its trial hole dug.
The pile pair nearest bridge 27EA have been confirmed (by virtue of the kilometrage being written on the inside of the rails) as SPC3/136.263/DM+UM.
North of bridge 27EA, there's a pile pair (confirmed to be SPC3/136.306/DM+UM) which looks as if it will carry a portal for a mid-point anchor. (The piles have 6 bolts to take an adapter plate to fit the masts.)
Then, after signals LR222/LR224, there's a UM TTC pile, then the 84.75 milepost, then 7 more UM TTC piles before the 85MP. (All 8 TTC piles have their adapter plates on.)