• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

North Wales Main Line Electrification

Status
Not open for further replies.

Along the bay

Member
Joined
2 Sep 2018
Messages
98
A new alignment would be very expensive and its already a project with a barely positive business case.

Doubling Halton Curve would add very little capacity because it is only one and a half miles long. It takes about two minutes for a train to pass through it. There isn't sufficient capacity between Lime Street and the curve for more services than currently planned. Once the Merseyrail timetable is updated following completion of 777 introduction the service via the curve will be at least ten minutes slower.



Do you mean the Voyagers? I was a child when they were introduced and wasn't a train enthusiast, so don't know. The freight line has been used during engineering works more recently. I think the last time was about five years ago. The loop remains in place to allow an hourly service. It was a horrifically slow diversion due to the line speed being 20 mph. I think it took over an hour to run Crewe to Chester.
No Pendolinos have worked to Holyhead whilst being hauled by class 57s.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,693
To allow the number of daily train movements that will need to be scheduled on the Middlewich line, what upgrading works will need to be done to bring that line up to an acceptable passenger standard whilst the stated Chester to Crewe line is closed for several months?
None. You do it as you do now and accept the journey time penalty. The shuttle doesnt run and Avanti run 1tph.
 

Caaardiff

Member
Joined
9 Jun 2019
Messages
1,090
What about Train Crew route knowledge? I don't believe TFW drivers sign that route anymore.
 

RobShipway

Established Member
Joined
20 Sep 2009
Messages
3,337
No Pendolinos have worked to Holyhead whilst being hauled by class 57s.
Er... How do you explain
or

I think that it is safer to say that no Pendolino's have been dragged by a class 57 into holiday in the last few years, rather than No Pendolino's have worked to Holyhead!
 

sprinterguy

Veteran Member
Joined
4 Mar 2010
Messages
11,320
Location
Macclesfield
Er... How do you explain
or

I think that it is safer to say that no Pendolino's have been dragged by a class 57 into holiday in the last few years, rather than No Pendolino's have worked to Holyhead!

They most certainly have. I went on one in around 2004 on the way to Ireland.
I could be wrong, but I suspect that Along the bay's post was supposed to have a comma after the word "No", which would alter the meaning somewhat.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
Acceptting the time penalty for a short period of time may be acceptable, but not if matters continue for months on end, as intimated in an earlier posting.
Why would it be months?
if you did a lot of work simultaneously it would just be a handful of week long blockades wouldn’t it?
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
34,066
Location
A typical commuter-belt part of north-west England
Why would it be months?
if you did a lot of work simultaneously it would just be a handful of week long blockades wouldn’t it?
Can I refer you to what @Chester1 said in his posting #116 and to which my responses have been based, that there are 25+ Victorian bridges that will need required works on the Chester to Crewe line in order electrification can be installed on that line section. The mind boggles at the thought of that part of the required works only needing "a handful of week long blockages" to meet the time requirements
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
Can I refer you to what @Chester1 said in his posting #116 and to which my responses have been based, that there are 25+ Victorian bridges that will need required works on the Chester to Crewe line in order electrification can be installed on that line section. The mind boggles at the thought of that part of the required works only needing "a handful of week long blockages" to meet the time requirements
25 Victorian bridges does not equal 25 bridge replacements.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,693
Can I refer you to what @Chester1 said in his posting #116 and to which my responses have been based, that there are 25+ Victorian bridges that will need required works on the Chester to Crewe line in order electrification can be installed on that line section. The mind boggles at the thought of that part of the required works only needing "a handful of week long blockages" to meet the time requirements
You wouldn't do it all at once, you wouldn't get the resource. It would be multiple instances of week or fortnight blocks. Normally a bridge replacement is 4 to 5 days. During which you could be doing all sorts in terms of piling/stanchion installation/signal work/track renewal etc etc...
 

Chester1

Established Member
Joined
25 Aug 2014
Messages
4,272
To allow the number of daily train movements that will need to be scheduled on the Middlewich line, what upgrading works will need to be done to bring that line up to an acceptable passenger standard whilst the stated Chester to Crewe line is closed for several months?

The western end of mid Cheshire line is single track. A coach would have a comparable journey time. The advantage of using Middlewich line is maintaining London services. If there was a long blockade then relaying some of the track might be worthwhile to increase line speeds. Even 40mph would be a considerable improvement.

None. You do it as you do now and accept the journey time penalty. The shuttle doesnt run and Avanti run 1tph.

The shuttle could be replaced by a coach too.

What about Train Crew route knowledge? I don't believe TFW drivers sign that route anymore.

Only Avanti drivers would be need to sign it. There isn't capacity on the Middlewich freight line or mid Cheshire line for more than an hourly Avanti service because both have significant single track sections. Compared with the cost of the work it wouldn't cost much to get drivers signed off again.

25 Victorian bridges does not equal 25 bridge replacements.

Its still a heck of a lot of work! Its a really tough line to electrify and Network Rail doesn't have a good record. Chester to Llandudno would be much easier but Llandudno Junction to Holyhead would be challenging.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,992
You wouldn't do it all at once, you wouldn't get the resource. It would be multiple instances of week or fortnight blocks. Normally a bridge replacement is 4 to 5 days. During which you could be doing all sorts in terms of piling/stanchion installation/signal work/track renewal etc etc...
At about the same time that these (apparently listed) bridges were cited as the reason Crewe - Chester couldn't be wired an engineer came up with a system for putting ties across the bottom of the arch and lifting it up whole while you raised the abutments. I thnk they were looking at just a few days line closure after doing the prep works. I thought it was a shame they didn't even pilot it on one bridge.
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,656
It would undoubtedly be cheaper in cash terms to stop the job for several months until the work is done.

However, I doubt the government would look kindly on such disruption.
 

Krokodil

Established Member
Joined
23 Jan 2023
Messages
4,528
Location
Wales
None. You do it as you do now and accept the journey time penalty. The shuttle doesnt run and Avanti run 1tph.
Avanti can't even manage 1tph on that route now, let alone with the longer journey time requiring diagrams to be stepped back.

Acceptting the time penalty for a short period of time may be acceptable, but not if matters continue for months on end, as intimated in an earlier posting.
People would tolerate a longer journey for a few months, provided that it's reliable and avoids having to change for a bus.

25 Victorian bridges does not equal 25 bridge replacements.
Here it may well do.
 
Last edited by a moderator:

cle

Established Member
Joined
17 Nov 2010
Messages
4,652
Could it be quicker or easier to funnel people via Warrington. They take a non-stop ride on the Glasgow, and then there is a longer service waiting for Llandudno/Holyhead in addition to the usual service on that line - which could be non-stop to Chester and then onwards.

Or if that was wired, a reversal (or better via Runcorn if Halton was done?)
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,992
Could it be quicker or easier to funnel people via Warrington. They take a non-stop ride on the Glasgow, and then there is a longer service waiting for Llandudno/Holyhead in addition to the usual service on that line - which could be non-stop to Chester and then onwards.

Or if that was wired, a reversal (or better via Runcorn if Halton was done?)
Apparently those Glasgows are so overcrowded that they can't be allowed to call at Crewe, as so many extra people would use them that it would be unsafe!
(That was the railway's excuse to my MP when he protested after the Crewe stops were withdrawn...) I wouldn't think they would want to encourage Chester and N Wales people to use them as well.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,205
Location
Bristol
At about the same time that these (apparently listed) bridges were cited as the reason Crewe - Chester couldn't be wired an engineer came up with a system for putting ties across the bottom of the arch and lifting it up whole while you raised the abutments. I thnk they were looking at just a few days line closure after doing the prep works. I thought it was a shame they didn't even pilot it on one bridge.
They tried that or a very similar system on EWR. The problem is that you are raising the crown of the road which causes road traffic and under-road services problems and you risk the settlement of the arch awkwardly on the modified abutments. Given the sensitivity of a brick arch to movement impacting the strength of the structure this is a big problem.
Clearance at the crown of the arch tends not to be a problem, it's clearance on the corners. So replacing an arch with a flat deck means you can clear the railway without adversely impacting the road profile, while also giving a structure that can accept a moderate amount of shifting as it settles onto the abutment.
 

Cowley

Forum Staff
Staff Member
Global Moderator
Joined
15 Apr 2016
Messages
17,251
Location
Devon
The Bristol discussions are in a new thread now, which is here:
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,992
They tried that or a very similar system on EWR. The problem is that you are raising the crown of the road which causes road traffic and under-road services problems and you risk the settlement of the arch awkwardly on the modified abutments. Given the sensitivity of a brick arch to movement impacting the strength of the structure this is a big problem.
Clearance at the crown of the arch tends not to be a problem, it's clearance on the corners. So replacing an arch with a flat deck means you can clear the railway without adversely impacting the road profile, while also giving a structure that can accept a moderate amount of shifting as it settles onto the abutment.
OK, then if the bridges really are listed then it's time for a new public debate:

Given that decarbonising rail haulage and encouraging modal shift from road to rail are recognised by most people as quite high priorities (even if not by the PM,) ought we to look at relatively minor landscape features, e.g. brick arch bridges in the Cheshire countryside, and decide whether electrifying the railway is more important?
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,656
OK, then if the bridges really are listed then it's time for a new public debate:

Given that decarbonising rail haulage and encouraging modal shift from road to rail are recognised by most people as quite high priorities (even if not by the PM,) ought we to look at relatively minor landscape features, e.g. brick arch bridges in the Cheshire countryside, and decide whether electrifying the railway is more important?

I suppose you could replace the bridges with architecturally comparable designs, but the listing people really don't like pastiches like that.
Neither do they like them being demolished, so we are at an impasse.

Unless someone wants to relay the railway with slab track!
 

Krokodil

Established Member
Joined
23 Jan 2023
Messages
4,528
Location
Wales
I suppose you could replace the bridges with architecturally comparable designs, but the listing people really don't like pastiches like that.
Neither do they like them being demolished, so we are at an impasse.

Unless someone wants to relay the railway with slab track!
Surely you just "accidentally" send an out of gauge load down the line. "Oh dear, they're unsafe, they'll have to come straight down"
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,693
OK, then if the bridges really are listed then it's time for a new public debate:

Given that decarbonising rail haulage and encouraging modal shift from road to rail are recognised by most people as quite high priorities (even if not by the PM,) ought we to look at relatively minor landscape features, e.g. brick arch bridges in the Cheshire countryside, and decide whether electrifying the railway is more important?
If you look on the Historic England website, the interactive map doesn't show any listed structures on the railway between Crewe and Chester.
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,656
Surely you just "accidentally" send an out of gauge load down the line. "Oh dear, they're unsafe, they'll have to come straight down"
That will just get you forced to rebuild it brick by brick to the exact same design, using the same methods used originally.

If you look on the Historic England website, the interactive map doesn't show any listed structures on the railway between Crewe and Chester.
You can guarantee that they will be listed the second anyone proposes to demolish them though.
 

krus_aragon

Established Member
Joined
10 Jun 2009
Messages
6,101
Location
North Wales
Surely you just "accidentally" send an out of gauge load down the line. "Oh dear, they're unsafe, they'll have to come straight down"
Are you suggesting we revert to 57+390 haulage, but with an armour-plated pantograph left up by mistake? <D
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,992
If you look on the Historic England website, the interactive map doesn't show any listed structures on the railway between Crewe and Chester.
In that case I wonder how that notion got any traction? Maybe the anti-rail lobby were fighting a rearguard campaign using disinformation... I swallowed it!
I suppose it might even have been like the supposed difficulties of wiring Standedge tunnel, a pretend reason for not proceding.

I think the only conclusion we can draw is that there is a deep-seated determination in Whitehall to prevent any rail upgrades or modernisation. Without postulating some sort of determined opposition it's hard to understand why blindingly obvious next steps in the efficiency improvements and reductions in costs of our railways just don't happen.
 

Sir Felix Pole

Established Member
Joined
21 Oct 2012
Messages
1,374
Location
Wilmslow
The Christleton Tunnel (near Chester) under the Shropshire Union Canal is the other tricky issue to resolve with its tight clearances.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
In that case I wonder how that notion got any traction?
Because somebody posted it on here?

I suppose it might even have been like the supposed difficulties of wiring Standedge tunnel, a pretend reason for not proceding.
And the statements that have frequently been posted on here over the years about the supposed impossibility of wiring the Forth Bridge and the Severn Tunnel.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,992
The Christleton Tunnel (near Chester) under the Shropshire Union Canal is the other tricky issue to resolve with its tight clearances.
And the statements that have frequently been posted on here over the years about the supposed impossibility of wiring the Forth Bridge and the Severn Tunnel.

Good points... time to wheel out my low-clearance pantograph again! (Not for the Severn Tunnel, obviously.)

Fit a low height, narrow pan as well as the standard one... most places where it is needed have speed restrictions anyway so the full width wouldn't be needed. Either use technology or just trust drivers to drop the big one and put up the lower narrow one for the distance needed...
 
Status
Not open for further replies.

Top