Whistler40145
Established Member
Cheers for that info
Not sure how much drivervtraining on 319s/Pendos will be required after energisation, but some refamiliarisation will be required for all drivers surely after a 4 month total closure and remodelling/resignalling
I would have thought that they would want Blackpool up and running for the summer 2018.I think both blackpool and bolton line projects will open more or less at the same time, i`m going for the may 2018 timetable change.
I would have thought that they would want Blackpool up and running for the summer 2018.
...
It took 12 months before some diesel diagrams were replaced (and even then the times were still based on Pacer performance - basically they still are).
Is it possible to tell whether it assumes electrification operational between Manchester and Euxton?The new timetable starting December 2017 has just been released and at last the Lime Street services are timed for 100mph 319s and slightly accelerated.
For example, see http://www.charlwoodhouse.co.uk/rail/liverail/train/10806708
Is it possible to tell whether it assumes electrification operational between Manchester and Euxton?
The new timetable starting December 2017 has just been released and at last the Lime Street services are timed for 100mph 319s and slightly accelerated.
For example, see http://www.charlwoodhouse.co.uk/rail/liverail/train/10806708
Are these timetables open to all yet please.
Many thanks
The new timetable starting December 2017 has just been released and at last the Lime Street services are timed for 100mph 319s and slightly accelerated.
For example, see http://www.charlwoodhouse.co.uk/rail/liverail/train/10806708
The new timetable starting December 2017 has just been released and at last the Lime Street services are timed for 100mph 319s and slightly accelerated.
For example, see http://www.charlwoodhouse.co.uk/rail/liverail/train/10806708
Are these timetables open to all yet please.
Many thanks
Is it possible to tell whether it assumes electrification operational between Manchester and Euxton?
Going slightly off topic as its the Chat Moss route, will the Lime St-Manchester Vic/Air services be timed to 100 MPH from Dec 17 or will it that happen in May 18 when TPE over the Fasts Via Victoria and the Airports become the stoppers
Doesn't the other half need strengthening as well?
Would have thought that it would be subject to the same loads.
Or is that just assuming too much?
Or has it been done already?
The Wigan line bridge needs raising for electrification clearances but the Chorley line one does not - see previous posts #4415, #4439 & #4560:Is anyone in a position to explain why the existing Wigan spans are a write off but the Chorley ones can be salvaged through strengthening? Given the limited distance between the platforms and the bridge you would think the Chorley side would need more work not the other way around.
They aren't raising it much, from 4.5m to 4.866m clearance and its pretty much same width both above and below within rounding margin.
Only the Westhoughton line deck (aka LCN/1) is being rebuilt. for Reference 350mm is a lot when the deck is full of services and the entire bridge is the summit of a hill already.
The required overrun distance extends only a little beyond the bridge, but since phase 7 (Lostock to Wigan) will pick this wire and extend it the decision was made to get Phase 4 to build up the location of the OHNS between phase 4 and 7 so that phase 7 didn't have to redo anything (using the insulated overlap provided on the Lostock side of the OHNS). The OHNS is on the straight, which extended the wires from Lostock Junction beyond that required for the overrun.
Who says we don't think ahead ...
Is anyone in a position to explain why the existing Wigan spans are a write off but the Chorley ones can be salvaged through strengthening? Given the limited distance between the platforms and the bridge you would think the Chorley side would need more work not the other way around.
So will road traffic be presented with a new span over the Wigan line in series with an old span over the Chorley line, where the latter is still subject to a 3 tonne limit?The two bridges are identical and have been subject to a 3 ton weight limit for many years. Neither the planning application for the replacement of the Wigan line bridge, or Network Rail's press statement before work started made any mention of strengthening the Preston line bridge.
So will road traffic be presented with a new span over the Wigan line in series with an old span over the Chorley line, where the latter is still subject to a 3 tonne limit?
6 months without going over it, is the gap needed for VT drivers to require a refresh. A brief required for the resignalling and p/way changes.
I don't know if this is new news or not, but some wires are now up on the Bolton line north of Ordsall Lane Jn.
I was viewing from a Liverpool train so didn't see how far they went towards Salford Crescent, maybe only to the Liverpool St bridge.
The registration gear, although it is installed, has not yet been attached to the wires.
"Water St Junction" for the Ordsall Chord is now installed on the Castlefield viaduct, with masts and registration gear going up towards the new Irwell bridge.
This seems to have gone in without a blockade.
"Water St Junction" for the Ordsall Chord is now installed on the Castlefield viaduct, with masts and registration gear going up towards the new Irwell bridge.
This seems to have gone in without a blockade.