Here is a summary of the response to my FOI:
https://www.whatdotheyknow.com/request/escalators_at_birmingham_new_str
BHM has 22 concourse to platform escalators and 18 were in use on 24th
March 2015, the date of the request.
At present, 11th June 2015, all 22 escalators are in working order.
Network Rail plans to install two additional escalators at BHM.
Cost of installation of escalators was refused.
Network Rail entered in to long term maintenance contracts
nationally for Lifts and Escalators with Stannah Lifts Limited and Schindler
Limited respectively. Both contracts started April 2014 and will expire March
2024. Network Rails current maintenance spend for lifts & escalators is £7.59
Million (financial year 2014/15). This figure changes annually due to additional
assets, replacement of old assets, and unforeseen circumstances, such as
misuse and vandalism.
818 individual recorded escalator faults at BHM in financial year 2014-15 (detailed in spreadsheet).
There is a current programme in place for the chain replacement of various
escalators. A end chain replacement is due to complete by 6th July 2015 and B
end chain replacement complete by 21st June 2015. However these dates are
dependent on other VA Works and station operations.
Each current escalator at BHM is calculated to have a capacity of 100
passengers per minute, or 6,000 passengers per hour.
NR don't know how many passengers are actually using the escalators, recorded or estimated.
Amount spent on crowd control at BHM:
Dec 2013 £62,000 (I will reply to check if this should be Dec 2014)
Jan 2015 £36,979
Feb 2015 £15,338
Mar 2015 £70,817