Some photos from earlier today. The edge for platform 3 has been extended and the OLE to the north of the busway bridge is now partially wired up. There was lots more activity down by Addenbrookes road but I did not have time to go have a look there today.
Anyone have any ideas what the blue pipes are for?
Great pics as always neill! Lots of OLE works this weekend indeec. We're making some great progress.
Blue pipes - these are for the diversion of a water main. There's an existing main across the site that gets destroyed by the new station building, so this is the replacement.
Question for people who know more: Are we going to continue having bus replacement most weekends for the whole of the next 3(?) Years whilst they build this? ( + Possibly another X years as they rip it all up again to build EWR!)
Getting pretty b****** annoying not have a weekend train service on either line most of the time.
Yeah, sorry, we have been quite busy!
There's another possession next weekend and then we let you take some trains again for many weeks. We've got a lot to do but I appreciate the disruption is annoying.