90019
Established Member
Apart from the possible exception of rail!
And the buses.
Apart from the possible exception of rail!
And the buses.
Out of the new systems, Sheffield is the one most on new alignments, it's only the Meadowhall line that is mostly on former heavy rail alighnment (most still in place but singled). Nottingham is mostly sharing the alighnment of the Robin Hood line, other than the final part into the city. Croyden, West Midlands and Manchester use large amounts of old railway, with Manchester re-using old track, stations and on the Altrincham line, OHLE. Edinburgh does have large amounts of new off street track, wheras the other systems are mostly using heavy rail alighnments for off street running. That should be cheaper and easier than street running though.
The tram system originally envisaged would have been the jewel in Edinburgh's crown. Now we just have another two railway lines between the Airport and Haymarket
And the buses.
Not frequent enough, though.
And the guided buses?
Parts of the current Manchester extensions are pretty extensive new build out to Ashton-under-Lyne and the Airport, as was the line through Salford Quays out to Eccles. They did, though, have the basic rail infrastructure to get things started to Bury and Altrincham (and now Chorlton/Didsbury)Is there any tram system in the UK that has been built in the last 20 years where all the lines have been newly constructed opposed to converting some existing or disused railway lines and adding on extensions?
What routes were you using :?
Parts of the current Manchester extensions are pretty extensive new build out to Ashton-under-Lyne and the Airport, as was the line through Salford Quays out to Eccles. They did, though, have the basic rail infrastructure to get things started to Bury and Altrincham (and now Chorlton/Didsbury)
Well I mainly used route 48, among several others including 35, and I was impressed by the network (very good coverage, good quality everywhere, well managed...) but I sometimes had to wait more than 20 minutes for a bus, and they were often late. If only they had 2 sets of doors of their buses...
Not quite. Salford Quays opened in 1999, 7 years after the first lines, the 2 miles of on street track to Eccles took a further 2 years to finish. Chorlton so is a reopened ex-rail line, the new build Airport extension is going to take 5 years to complete.Exactly. They just built a new section between around Cornbrook, Victoria and Piccadilly initially. It's taken them 20 years to add on the Eccles and Chorlton bits.
Not quite. Salford Quays opened in 1999, 7 years after the first lines, the 2 miles of on street track to Eccles took a further 2 years to finish. Chorlton so is a reopened ex-rail line, the new build Airport extension is going to take 5 years to complete.
What I don't understand is if they have laid track along Princess street and they are running as far as Haymarket what is still required to get to Waverley? Also is there no way they could cover the rails on Princess street so if the money was found later it could be extended?
What I don't understand is if they have laid track along Princess street and they are running as far as Haymarket what is still required to get to Waverley? Also is there no way they could cover the rails on Princess street so if the money was found later it could be extended?
What about tram-trains?
What I don't understand is if they have laid track along Princess street and they are running as far as Haymarket what is still required to get to Waverley?
What about a heavy rail station or link?
What for ?
To do Haymarket-Waverley on the heavy rail line if they aren't going to build the tram line in to the centre.