spark001uk
Established Member
- Joined
- 20 Aug 2010
- Messages
- 2,326
No that was the early morning one.Is this the same working discussed between posts 982 and 985 above?
No that was the early morning one.Is this the same working discussed between posts 982 and 985 above?
That doesn't seem likely, given the number delivered recently increased from three to four and none have been sent back. I doubt it would be something for the public domain in any case.Finally I ponder whether GWR have any fall-back plan should the 769s not prove acceptable.
Four delivered, 930 / 943 / 946 / 959, but one of those (943) went to Eastleigh this week to get it out of the way and one (930) was at Oxford sidings last week, on its return from Rail Live at Long Marston, again to keep it out of the way.1) How many are now are at Reading. Possibly 4?
It was described elsewhere by an informed source as 'mileage based accumulation' rather than 'fault free running'.2) How many have been involved with Fault Free Testing (FFT).
3) Have any passed FFT?
No record of them having been to Henley or Bourne End appears to have been posted here, neither Basingstoke other than 769943's transfer to Eastleigh.5) Have the units been operated on all their intended routes?
It has been posted that the testing at Shalford Junction at the end of May was culmination of the clearance work but it does seem that current attention is being focused on platform / train interface with longer dwells at specific stations on the test runs.5) Have any track/platform related problems arisen?
If you look at the schedule in the direct award, based on an April 2020 delivery for the first unit, it was never expected that any would be in service until the September 2020 timetable change with the last introduced in May 2021. Given the first unit was about a year later than that, it should give some idea of timescales in better circumstances than those which currently prevail.6) Is there any realistic hope of driver training starting anytime soon?
7) Is it possible, with due regard to Covid19, to estimate how long it will take to train all the Reading drivers
What do you think should be in the public domain? It does seem that some progress is being made.Rightly or wrongly I sense that GWR are being a shade backwards in coming forwards about the progress of these units.
Seems a bit optimistic to me.Behind all the above queries is a desire to obtain a best estimate of when further Turbos will be able to transfer West. A recent observation stated 'not before September'. Is that realistic or optimistic?
Whilst I have no gen on the trains in question, the two pairings of backward/forwards and rightly/wrongly in one sentence read like unintentional poetry, it rather ticked me.Rightly or wrongly I sense that GWR are being a shade backwards in coming forwards about the progress of these units.
The existing distance from the point blades to the buffer stops is already almost exactly 80m — the length of a 4-car Class 769 train. Four carriages of Class 166 are much longer, at 92m, so that's why a 4-car service has previously been infeasible.getting a 4 car unit to reverse at Bourne End which can only accommodate a 2 car reversal for Marlow would be very interesting.
That's an interesting suggestion. One point in it's favour is that trackbed level (according to Google Earth) at the buffers is nearly two metres higher than the points at the Maidenhead end of the platform. If that is correct, then a 1:40 gradient would reduce the likelihood of overrunning into the buffers. I don't know how slow TPWS can be set but if the buffers were modified to use the 5m of track that they had to give a progressive deceleration, that would mitigate the impact of a collision as far as possible.The existing distance from the point blades to the buffer stops is already almost exactly 80m — the length of a 4-car Class 769 train. Four carriages of Class 166 are much longer, at 92m, so that's why a 4-car service has previously been infeasible.
Of course, a safe buffer stop distance, as well as track circuit overlap and signal sighting needs to be taken into account — not just the length of the train. However, looking at a satellite view, it does not seem impossible to realign the track from the Maidenhead direction a little further north, so that the track from Marlow joins it enough further west to accomodate four carriages of 20m stock. Selective door opening would likely be required, with I believe only three to three-and-a-half carriages being platformed.
The private gardens between the two might end up being slightly reduced, but it does look like they don't reach as far as they possibly could into what probably remains 'railway land' nestled right in the crook of the junction — so it may even be possible without clipping the gardens at all.
They just need a big sector plateThat's an interesting suggestion. One point in it's favour is that trackbed level (according to Google Earth) at the buffers is nearly two metres higher than the points at the Maidenhead end of the platform. If that is correct, then a 1:40 gradient would reduce the likelihood of overrunning into the buffers. I don't know how slow TPWS can be set but if the buffers were modified to use the 5m of track that they had to give a progressive deceleration, that would mitigate the impact of a collision as far as possible.
Is this 769930's return to Reading today?
Realtime Trains - 538T 1120 Oxford Down Carriage Sdg to Reading Traincare Depot
Realtime Trains is an independent source of live realtime running information for the Great British railway network.www.realtimetrains.co.uk
Today's NDL run appears (according to RTT) to have been aborted again. Is this another diesel engine problem?
View attachment 99465Realtime Trains - 549U 0915 Reading Traincare Depot to Reading Traincare Depot
Realtime Trains is an independent source of live realtime running information for the Great British railway network.www.realtimetrains.co.uk
Thank you. The afternoon one isn't doing well either, being 23 down from an 8 late start from Reading. May be nothing mechanical of course. That run also aborted - at Redhill. The time gradually but steadily lost from Reading to Guildford with nothing in front of it suggests a performance problem.Not happening tomorrow. (maybe next week)
769946 has failed but not sure what the actual issue is. 769959 will be out for this afternoons run.
Did 959 make it out this afternoon?Not happening tomorrow. (maybe next week)
769946 has failed but not sure what the actual issue is. 769959 will be out for this afternoons run.
Well something did!Did 959 make it out this afternoon?
And, meanwhile, Realtime Trains says the test runs scheduled for Monday and today didn't happen.
https://www.realtimetrains.co.uk/service/gb-nr:K05112/2021-07-16/detailed
Is this another 769 storage move, does anyone know which one it'll be?
No sign of the Burton LD move.Nothing has been notified to the depot Movement Controllers so may not happen (Or we’ll get told right at the last minute!)
Same goes for the move from Burton also posted above.
769930 currently working this.
Realtime Trains - 507A 0915 Reading Traincare Depot to Reading Traincare Depot
Realtime Trains is an independent source of live realtime running information for the Great British railway network.www.realtimetrains.co.uk
Looks to me as if it just turned round at Redhill to regain its booked path.Yet another 769 NDL run seems to have aborted, including some bizarre times reported (not accounted for by the earlier-than-scheduled return leg, either):
View attachment 99907Realtime Trains - 508A 1232 Reading Traincare Depot to Reading Traincare Depot
Realtime Trains is an independent source of live realtime running information for the Great British railway network.www.realtimetrains.co.uk
Many of these runs seem to have erroneous data at North Camp, Chilworth and Dorking West.
Have the previous runs not used DC at all?Real TID 5Q10
And running on DC where available (Reading Spur - Wokingham, Ash - Guildford, Reigate to Gatwick)
Precisely, but why was it so late to start with and why do the North Camp times, for example, look like fiction, not being accounted for by the return leg either? A large number of these runs seem to start very late or lose so much time en route to require them to be aborted.Looks to me as if it just turned round at Redhill to regain its booked path.
I think there have been a few reports of DC running since back in mid June, for instance post #877 refers to a departure from Gatwick.Have the previous runs not used DC at all?